Whole building & multi-floor projectsTemporary pipe scaffold installationUnder Construction3 filings
INSTALLATION OF TEMPORARY ENGINEERED ENCLOSURE SYSTEM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
INSTALLATION OF TEMPORARY PERSONNEL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
RoofTemporary overhead protection installationUnder Construction6p · 2 filings · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
BulkheadUnder Construction6p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 6 drawing sheets
Floor 13Installation of temporary needle beam1 filing · 2 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 7 drawing sheets
Floor 12Installation of temporary needle beam1 filing · 2 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 7 drawing sheets
Floor 11Installation of temporary needle beam1 filing · 2 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 7 drawing sheets
Floor 10
Floor 9
Floor 8Under Construction2p · 1 filing · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 2 drawing sheets
Floor 7Under Construction2p · 1 filing · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 2 drawing sheets
Floor 6Under Construction2p · 1 filing · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 2 drawing sheets
Floor 5
Floor 4
Floor 3
Floor 2Walton DevelopersUnder Construction1p · 1 filing
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Project M01473492Permit Issued · 10/13/2026
INSTALLATION OF OUTRIGGER PLATFORM AND C-49 BRACKET IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
1 drawing sheet
Floor 1Under Construction3p · 1 filing · 20 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Construction Fence · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Standpipe · Structural · Supported Scaffold
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 3 drawing sheets
CellarUnder Construction6p · 1 filing · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Earth Work · Foundation · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Support of Excavation
TEMPORARY STANDPIPE SPECIFICATIONS FILED IN CONJUNCTION WITH GC APPLICATION M01293643-I1
On file for this project
73 documents · 6 drawing sheets
Site & exteriorWalton DevelopersUnder Construction3 filings · 5 docs
ArchitectureEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
Project M01473492Permit Issued · 10/13/2026
INSTALLATION OF OUTRIGGER PLATFORM AND C-49 BRACKET IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
4 drawing sheets
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 3 drawing sheets