← Back
BuildNYC
Two family frame
91 LIVINGSTON AVENUE
STATEN ISLAND · BIN 5020974
💬 Discuss this project
1965Year Built
2Stories
B2Building Class
R3-1Zoning
2,280 sfGross Floor Area
2Units
4 Active Violations ▸FDNY Report ↗
Two family frame · 5,360 sf lot · 0.43 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 3Vertical addition to two-family residence5p · 1 filing · 20 docs
Floor 2Vertical addition to two-family residence4p · 1 filing · 20 docs
Floor 1Vertical addition to two-family residence4p · 1 filing · 20 docs
CellarVertical addition to two-family residence6p · 1 filing · 20 docs
Site & exterior1p · 1 filing · 2 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Willy C. Yuin504/23/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Sanark Consulting Engineering403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Pyramid Framers USAGeneral Contractor207/22/2026
Power Direct ElectricElectrical103/22/2026
Reliable ContractingGeneral Contractor103/21/2026
Pyramid Framers USAScaffold104/09/2026
Flow-Right Plumbing & HeatingPlumbing107/08/2026
J Synergy GreenGeneral Contractor112/28/2022
New York PlumbingPlumbing110/19/2009
New York PlumbingPlumbing107/05/2007
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF Services5616211/14/2025
Building Lifecycle
09/23/2026
Permit expired, never signed off — Structural
The city's record still shows this permit as issued, with no sign-off on its filing
S01254012-I1-GC
07/20/2026
Permit issued — General Construction
S01254012-I1-ST
04/28/2026
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
04/28/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
04/28/2026
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
57 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPyramid Framers USA07/20/2026
DOB NOWPlumbingSigned-offFlow-Right Plumbing & Heating11/06/2025
DOB NOWStructuralPermit IssuedPyramid Framers USA10/07/2025
DOB NOWConstruction FenceSigned-offPyramid Framers USA10/01/2025
BISOTISSUEDJ Synergy Green12/28/2022
BISPLISSUEDAAA Plumbing & Heating10/19/2009
BISPLISSUEDAAA Plumbing & Heating07/05/2007
BIS—ISSUEDReliable Contracting03/13/2007
1 project · most recent 04/23/2026
Gas Water/Sanitary
FiledStatusContractorScope
04/23/2026Signed-offFlow-Right Plumbing & HeatingGas, Water/Sanitary
2 projects · most recent 02/10/2026
General Wiring
FiledStatusContractorScope
02/10/2026CompletePower Direct ElectricGeneral Wiring
01/02/2023CompleteGreen Light Electrical & Mechanical—
1 project · most recent 04/23/2026
Steel Wood
FiledStatusContractorScope
04/23/2026Signed-offPyramid Framers USASteel, Wood
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
03/16/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/03/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
04/28/2026HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
04/28/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
04/28/2026HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
04/28/2026HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
04/28/2026Permanent certificateSHAHRIAR QUAYYUMenergy_progress
04/28/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
04/22/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
04/22/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
04/22/2026HVAC-R and service water heating equipmentSHAHRIAR QUAYYUMenergy_progress
04/22/2026HVAC-R and service water heating system controlsSHAHRIAR QUAYYUMenergy_progress
04/22/2026HVAC-R and service water piping design and insulationSHAHRIAR QUAYYUMenergy_progress
04/22/2026Permanent certificateSHAHRIAR QUAYYUMenergy_progress
11/24/2025Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
11/24/2025Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
11/24/2025Permanent certificateSHAHRIAR QUAYYUMenergy_progress
11/24/2025Fenestration areasSHAHRIAR QUAYYUMenergy_progress
11/24/2025Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
11/24/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
11/24/2025Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
11/24/2025Structural Wood FrameSHAHRIAR QUAYYUMprogress
11/24/2025Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
11/24/2025FinalSHAHRIAR QUAYYUMprogress
11/24/2025Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
11/24/2025Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
11/24/2025Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
Latest 25 of 27.
79 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account