| Firm | Filings | Most Recent |
|---|---|---|
| Willy C. Yuin | 5 | 04/23/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| Sanark Consulting Engineering | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Pyramid Framers USA | General Contractor | 2 | 07/22/2026 |
| Power Direct Electric | Electrical | 1 | 03/22/2026 |
| Reliable Contracting | General Contractor | 1 | 03/21/2026 |
| Pyramid Framers USA | Scaffold | 1 | 04/09/2026 |
| Flow-Right Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| J Synergy Green | General Contractor | 1 | 12/28/2022 |
| New York Plumbing | Plumbing | 1 | 10/19/2009 |
| New York Plumbing | Plumbing | 1 | 07/05/2007 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF Services | 5616 | 2 | 11/14/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Pyramid Framers USA | 07/20/2026 |
| DOB NOW | Plumbing | Signed-off | Flow-Right Plumbing & Heating | 11/06/2025 |
| DOB NOW | Structural | Permit Issued | Pyramid Framers USA | 10/07/2025 |
| DOB NOW | Construction Fence | Signed-off | Pyramid Framers USA | 10/01/2025 |
| BIS | OT | ISSUED | J Synergy Green | 12/28/2022 |
| BIS | PL | ISSUED | AAA Plumbing & Heating | 10/19/2009 |
| BIS | PL | ISSUED | AAA Plumbing & Heating | 07/05/2007 |
| BIS | — | ISSUED | Reliable Contracting | 03/13/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2026 | Signed-off | Flow-Right Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/10/2026 | Complete | Power Direct Electric | General Wiring |
| 01/02/2023 | Complete | Green Light Electrical & Mechanical | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2026 | Signed-off | Pyramid Framers USA | Steel, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/28/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 04/28/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 04/28/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 04/28/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 04/28/2026 | Permanent certificate | SHAHRIAR QUAYYUM | energy_progress |
| 04/28/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 04/22/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 04/22/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 04/22/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 04/22/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 04/22/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 04/22/2026 | Permanent certificate | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 11/24/2025 | Permanent certificate | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Structural Steel - Details | SHAHRIAR QUAYYUM | special |
| 11/24/2025 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 11/24/2025 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 11/24/2025 | Structural Wood Frame | SHAHRIAR QUAYYUM | progress |
| 11/24/2025 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 11/24/2025 | Final | SHAHRIAR QUAYYUM | progress |
| 11/24/2025 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 11/24/2025 | Lighting in dwelling units | SHAHRIAR QUAYYUM | energy_progress |