← Back
Office only, 2-6 stories
91 NEW DORP PLAZA
STATEN ISLAND · BIN 5107601
💬 Discuss this project
1950Year Built
2Stories
O2Building Class
R3-1Zoning
4,400 sfGross Floor Area
1Units
Office only, 2-6 stories · Owner of record: 91 NEW DORP PLAZA LLC · 3,200 sf lot · 1.38 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
91 NEW DORP PLAZA1203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
RAMPULLA ASSOCIATES ARCHITECTS, LLP505/24/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RAMPULLA ASSOCIATES ARCHITECTS303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MAXIMUM CONTRACTING INCGeneral Contractor303/21/2026
PANACEA CONTRACTING CORPGeneral Contractor303/21/2026
KCM PLUMBING & HEATING COPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738105/14/2020
Building Lifecycle
All (33)Filed (5)Permit Issued (4)Signed Off (3)Objection (6)Special Inspection (15)
12/09/2021
Signed off — Alteration
Plumbing work filed in conjunction with DOB alteration 1 # 520378555. Remove existing plumbing fixtures, install new plumbing fixtures as per plans.
S00340640-I1
11/09/2021
Signed off — Alteration
Mechanical work filed in conjunction with Application #520378555, work is OSP cell , 001, 002. Install (2) Air Handling Units ( OSP) and (1) Unit Heater (1st floor Stairway) , Exhaust fans, dampers as per plans
S00341434-I1
11/03/2021
Signed off — Alteration
Construction fence filed in conjunction with DOB application # 520378555
S00341432-I1
10/08/2021
Permit issued — Mechanical Systems
S00341434-I1-MS
07/15/2021
Permit issued — Plumbing
S00340640-I1-PL
05/24/2021
Filed — Alteration
Plumbing work filed in conjunction with DOB alteration 1 # 520378555. Remove existing plumbing fixtures, install new plumbing fixtures as per plans.
S00340640-P1
05/20/2021
Special inspection requirement — Mechanical Systems
anthony santoro
05/20/2021
Special inspection requirement — Final
anthony santoro
05/20/2021
Special inspection requirement — HVAC and service water heating equipment
anthony santoro
05/20/2021
Special inspection requirement — HVAC and service water heating system controls
anthony santoro
05/20/2021
Special inspection requirement — Maintenance information
anthony santoro
05/20/2021
Special inspection requirement — HVAC insulation and sealing
anthony santoro
05/20/2021
Special inspection requirement — Shutoff dampers
anthony santoro
05/17/2021
Filed — Alteration
Mechanical work filed in conjunction with Application #520378555, work is OSP cell , 001, 002. Install (2) Air Handling Units ( OSP) and (1) Unit Heater (1st floor Stairway) , Exhaust fans, dampers as per plans
S00341434-P1
04/08/2021
Special inspection requirement — HVAC insulation and sealing
04/08/2021
Special inspection requirement — Mechanical Systems
04/08/2021
Special inspection requirement — Final
04/08/2021
Special inspection requirement — Maintenance information
04/08/2021
Special inspection requirement — HVAC and service water heating system controls
04/08/2021
Special inspection requirement — HVAC and service water heating equipment
04/08/2021
Special inspection requirement — Shutoff dampers
07/27/2020
Permit issued — Plumbing
S00340640-I1-PL
07/08/2020
Permit issued — Construction Fence
S00341432-I1-FN
06/10/2020
Objection resolved — Addressed
06/02/2020
Objection raised — Other
06/02/2020
Objection resolved — Addressed
06/02/2020
Objection raised — Scope
06/02/2020
Objection resolved — Addressed
06/01/2020
Filed — Alteration
Construction fence filed in conjunction with DOB application # 520378555
S00341432-I1
05/21/2020
Objection raised — Scope
05/14/2020
Filed — Alteration
Plumbing work filed in conjunction with DOB alteration 1 # 520378555. Remove existing plumbing fixtures, install new plumbing fixtures as per plans.
S00340640-I1
05/14/2020
Filed — Alteration
Mechanical work filed in conjunction with Application #520378555, work is OSP cell , 001, 002. Install (2) Air Handling Units ( OSP) and (1) Unit Heater (1st floor Stairway) , Exhaust fans, dampers as per plans
S00341434-I1
04/10/2020
Special inspection requirement — Final
anthony santoro
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offPANACEA CONTRACTING CORP10/08/2021
DOB NOWPlumbingSigned-offKCM PLUMBING & HEATING CO07/15/2021
DOB NOWPlumbingSigned-offKCM PLUMBING & HEATING CO07/27/2020
DOB NOWConstruction FenceSigned-offMAXIMUM CONTRACTING INC07/08/2020
BIS—ISSUEDMAXIMUM CONTRACTING INC02/17/2021
BIS—ISSUEDMAXIMUM CONTRACTING INC07/09/2020
1 project · most recent 08/28/2020
General Wiring
FiledStatusContractorScope
08/28/2020CompleteCATELLO ELEC'L CONT., INCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
05/20/2021Mechanical Systemsanthony santorospecial
05/20/2021Finalanthony santoroprogress
05/20/2021HVAC and service water heating equipment anthony santoroenergy_progress
05/20/2021HVAC and service water heating system controls anthony santoroenergy_progress
05/20/2021Maintenance informationanthony santoroenergy_progress
05/20/2021HVAC insulation and sealing anthony santoroenergy_progress
05/20/2021Shutoff dampersanthony santoroenergy_progress
04/08/2021HVAC insulation and sealing —energy_progress
04/08/2021Mechanical Systems—special
04/08/2021Final—progress
04/08/2021Maintenance information—energy_progress
04/08/2021HVAC and service water heating system controls —energy_progress
04/08/2021HVAC and service water heating equipment —energy_progress
04/08/2021Shutoff dampers—energy_progress
04/10/2020Finalanthony santoroprogress
▾Documents — 52 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/26/2026S00341434-I1Request digital key ↗
08/15/2026S00341434-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
08/26/2026S00340640-P1Request digital key ↗
08/14/2026S00340640-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/15/2026S00341432-I1Request digital key ↗
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION4
04/07/2021520378555Open ↗
05/07/2020520378555Open ↗
04/29/2020520378555Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
08/17/2021520378555Open ↗
▸BISWORK PERMIT APPLICATION1
07/09/2020520378555Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISVERIFY TAX LOT1
12/10/2021520378555Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
04/29/2020520378555Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
12/10/2021520378555Open ↗
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/26/2026S00340640-I1Open ↗
08/26/2026S00340640-P1Open ↗
08/26/2026S00341434-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/07/2026S00341432-I1Open ↗
08/25/2026S00341434-I1Open ↗
08/25/2026S00341434-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
03/13/2020520378555Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/25/2026S00341434-I1Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
03/13/2020520378555Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/26/2026S00340640-P1Open ↗
08/26/2026S00341434-I1Open ↗
08/14/2026S00340640-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/29/2020520378555Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
04/29/2020520378555Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
12/16/2021520378555Open ↗
07/09/2020520378555Open ↗
04/29/2020520378555Open ↗
▸BISLIGHTING CONTROLS1
10/14/2021520378555Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/23/2021520378555Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
12/10/2021520378555Open ↗
12/09/2021520378555Open ↗
10/21/2021520378555Open ↗
Showing 3 of 4 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/14/2021520378555Open ↗
▸Approvals, Objections & Sign-offs3
▸BISSCHEDULE A - OCCUPANCY / USE2
04/29/2020520378555Open ↗
03/13/2020520378555Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
05/24/2021520378555Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
11/23/2021520378555Open ↗
03/13/2020520378555Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
12/13/2021520378555Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION3
12/14/2021520378555Open ↗
05/24/2021520378555Open ↗
04/29/2020520378555Open ↗
▸BISEFILING COVER SHEET1
03/13/2020520378555Open ↗
▸Other Documents1
▸BISBPP - SUPPORTING DOCUMENTATION1
04/29/2020520378555Open ↗