← Back
Miscellaneous warehouse
910 BEDFORD AVENUE
BROOKLYN · BIN 3055002
💬 Discuss this project
1968Year Built
3Stories
E9Building Class
R7AZoning
9,300 sfGross Floor Area
2Units
3 Open Violations ▸FDNY Report ↗
Miscellaneous warehouse · Owner of record: 910-912 BEDFORD LLC · 4,800 sf lot · 1.94 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction2p · 1 filing · 6 docs
Floor 8Under Construction18p · 1 filing · 20 docs
Floor 7Under Construction20p · 1 filing · 20 docs
Floor 6Under Construction20p · 1 filing · 20 docs
Floor 5Under Construction20p · 1 filing · 20 docs
Floor 4Under Construction20p · 1 filing · 20 docs
Floor 3Under Construction22p · 2 filings · 20 docs
Floor 2Under Construction21p · 2 filings · 20 docs
Floor 1Under Construction21p · 2 filings · 20 docs
CellarUnder Construction44p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
J G CONSTRUCTION SRVCS209/15/2026
JNY BEFFORD REALTY LLC1303/22/2026
JNY BEDFORD REALITY LLC3903/22/2026
MJH CONSTRUCTION103/22/2026
OWNER OF 910/12 BEDFORD A203/22/2026
NY.EXPRESS ENT INC103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPRESS FILING INC1803/21/2026
ALLSTATE EXPEDITERS1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MJH CONSTRUCTION CORPGeneral Contractor807/08/2026
BH GENERAL CONTRACTING INGeneral Contractor603/21/2026
J & G CONSTRUCTION SVCSGeneral Contractor109/12/2026
N TECH DESIGN OF AMERICAGeneral Contractor109/25/2026
SAT CONSTRUCTION SERVICESGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616608/12/2026
ADROIT ENGINEERING PLLC8885103/25/2024
Building Lifecycle
All (192)Filed (19)Permit Issued (11)Signed Off (1)Violation (60)Inspection (1)Objection (67)Special Inspection (30)Tax Incentive (3)
10/30/2026
421-a(16) construction completed
09/24/2026
Permit issued — Full Demolition
B01008674-I1-FD
09/21/2026
Objection raised — Other
09/10/2026
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
B01327889-I1
09/10/2026
Permit issued — Sidewalk Shed
B01327889-I1-SH
09/03/2026
Objection resolved — Addressed
08/17/2026
Objection raised — Other
08/12/2026
Filed — New Building
FOUNDATION AND EARTHWORK SPECIFICATIONS FILED IN CONJUNCTION WITH NB APPLICATION #B00977949-I1
B00977949-P1
07/29/2026
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
07/29/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
07/29/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
07/29/2026
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
07/29/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
07/29/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
07/29/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
07/29/2026
Special inspection requirement — Maintenance information
FAHAD FATEH
07/29/2026
Special inspection requirement — Metering
FAHAD FATEH
07/29/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
07/29/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
07/29/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
07/29/2026
Special inspection requirement — Exterior lighting power
FAHAD FATEH
07/29/2026
Special inspection requirement — Air barrier — testing
FAHAD FATEH
07/29/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
07/29/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
07/29/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
07/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/18/2026
Permit issued — Construction Fence
B00977949-S3-FN
03/17/2025
Permit issued — Construction Fence
B00977949-S3-FN
02/28/2025
Violation issued (ECB, closed)
Construction
12/23/2024
Permit issued — General Construction
B00977949-I1-GC
12/11/2024
Permit issued — General Construction
B00977949-I1-GC
12/10/2024
Permit issued — Support of Excavation
B00977949-S4-SE
09/09/2024
421-a(16) registration filed
06/10/2024
Objection resolved — Addressed
05/22/2024
Objection raised — Other
05/15/2024
Filed — New Building
FOUNDATION AND EARTHWORK SPECIFICATIONS FILED IN CONJUNCTION WITH NB APPLICATION #B00977949-I1
B00977949-S8
05/09/2024
Filed — New Building
FOUNDATION AND EARTHWORK SPECIFICATIONS FILED IN CONJUNCTION WITH NB APPLICATION #B00977949-I1
B00977949-S6
05/09/2024
Filed — New Building
FOUNDATION AND EARTHWORK SPECIFICATIONS FILED IN CONJUNCTION WITH NB APPLICATION #B00977949-I1
B00977949-S5
05/06/2024
Objection resolved — Addressed
05/02/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
05/02/2024
Special inspection requirement — HVAC-R and service water heating system controls
05/02/2024
Special inspection requirement — Metering
05/02/2024
Special inspection requirement — Maintenance information
05/02/2024
Special inspection requirement — Duct leakage testing, insulation and design
05/02/2024
Special inspection requirement — Shutoff dampers
05/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/02/2024
Special inspection requirement — Post-installed Anchors
05/02/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
05/02/2024
Special inspection requirement — Seismic Isolation Systems
05/02/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/02/2024
Special inspection requirement — HVAC-R and service water heating equipment
04/18/2024
Objection resolved — Addressed
04/10/2024
Objection resolved — Addressed
03/25/2024
Filed — Full Demolition
B01008674-I1
03/22/2024
Objection resolved — Addressed
03/22/2024
Objection resolved — Addressed
03/21/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/04/2024
Objection raised — Other
03/04/2024
Objection raised — Structural
03/04/2024
Objection raised — Other
Latest 60 of 192 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFull DemolitionPermit IssuedN TECH DESIGN OF AMERICA09/24/2026
DOB NOWSidewalk ShedPermit IssuedJ & G CONSTRUCTION SVCS09/10/2026
DOB NOWConstruction FencePermit IssuedMJH CONSTRUCTION CORP02/18/2026
DOB NOWConstruction FencePermit IssuedMJH CONSTRUCTION CORP03/17/2025
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP12/23/2024
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP12/11/2024
DOB NOWSupport of ExcavationPermit IssuedMJH CONSTRUCTION CORP12/10/2024
DOB NOWConstruction FencePermit IssuedMJH CONSTRUCTION CORP02/22/2024
DOB NOWConstruction FenceSigned-offBH GENERAL CONTRACTING IN01/27/2023
DOB NOWConstruction FenceSigned-offBH GENERAL CONTRACTING IN01/26/2023
DOB NOWSidewalk ShedSigned-offSAT CONSTRUCTION SERVICES06/23/2022
BISPLISSUEDP.H. WORKS INC03/08/2023
BIS—ISSUEDBH GENERAL CONTRACTING IN02/10/2023
BIS—ISSUEDBH GENERAL CONTRACTING IN02/06/2023
BIS—ISSUEDSAT CONSTRUCTION SERVICES06/15/2022
BISOTISSUEDLEE & LIANG CONSTR INC03/02/1992
2 projects · most recent 08/12/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/12/2026Permit IssuedMJH CONSTRUCTION CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin RXTQ48TAVJU 49,500 BTU · Vrf Outdoor ×14
RXTQ60RAVJU 57,000 BTU · Vrf Outdoor ×1
RZQ18TBVJUA 20,000 BTU · Condensing Unit ×1
07/25/2023——Heating and Air Conditioning Systems
Heat / Cool
Daikin 4MXS36RMVJUA 36,000 BTU · Heat Pump Outdoor ×2
REYQ120TTJU 135,000 BTU · Vrf Outdoor ×2
RZQ18TAVJUA 20,000 BTU · Heat Pump Outdoor ×1
RZQ36TAVJUA 40,000 BTU · Heat Pump Outdoor ×1
RZQ48TAVJUA 54,000 BTU · Heat Pump Outdoor ×1
2 projects · most recent 08/12/2026
Gas Water/Sanitary Storm
FiledStatusContractorScope
08/12/2026——Gas, Storm, Water/Sanitary
07/25/2023——Gas, Water/Sanitary
4 projects · most recent 09/09/2026
General Wiring
FiledStatusContractorScope
09/09/2026Permit IssuedRICHARD NEU—
12/18/2025Permit IssuedS&R ELECTRICAL & MECHANICGeneral Wiring
02/15/2023CompleteTRUE POWER ELECL CONT LLC—
06/09/2022Permit IssuedACCURATE ELEC'L CORP.General Wiring
2 projects · most recent 08/12/2026
Concrete
FiledStatusContractorScope
08/12/2026Permit IssuedMJH CONSTRUCTION CORPConcrete
08/17/2023——1 scope_items
2 projects · most recent 09/10/2026
Sidewalk Shed Fence
FiledStatusContractorScope
09/10/2026Permit IssuedJ & G CONSTRUCTION SVCSSidewalk Shed
08/12/2026Permit IssuedMJH CONSTRUCTION CORPFence
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
01/04/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 93
DateRequirementInspectorRole
07/29/2026Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
07/29/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
07/29/2026Lighting in dwelling unitsFAHAD FATEHenergy_progress
07/29/2026Protection of exposed foundation insulationFAHAD FATEHenergy_progress
07/29/2026MeteringFAHAD FATEHenergy_progress
07/29/2026Fenestration air leakageFAHAD FATEHenergy_progress
07/29/2026Maintenance informationFAHAD FATEHenergy_progress
07/29/2026Electrical motors and elevatorsFAHAD FATEHenergy_progress
07/29/2026Interior lighting powerFAHAD FATEHenergy_progress
07/29/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
07/29/2026Insulation placement and R valuesFAHAD FATEHenergy_progress
07/29/2026Lighting controlsFAHAD FATEHenergy_progress
07/29/2026Exterior lighting powerFAHAD FATEHenergy_progress
07/29/2026Air barrier — testing FAHAD FATEHenergy_progress
07/29/2026Fenestration areasFAHAD FATEHenergy_progress
07/29/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
07/29/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
07/29/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
05/02/2024Maintenance information—energy_progress
05/02/2024HVAC-R and service water piping design and insulation—energy_progress
05/02/2024Maintenance information—energy_progress
05/02/2024Metering—energy_progress
05/02/2024HVAC-R and service water heating system controls—energy_progress
05/02/2024HVAC-R and service water heating equipment—energy_progress
05/02/2024Seismic Isolation Systems—special
Latest 25 of 93.
▾Documents — 168 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch19
09/15/2026B01327889-I1Request digital key ↗
08/27/2026B00893989-I1Request digital key ↗
08/27/2026B00920985-I1Request digital key ↗
Showing 3 of 19 on file for this type
▸Applications & Permits34
▸BISPLAN / WORK APPROVAL APPLICATION17
02/29/2024340892467Open ↗
02/20/2024340892467Open ↗
08/18/2023321782950Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION10
03/08/2023321782950Open ↗
02/10/2023321782950Open ↗
02/09/2023321782950Open ↗
Showing 3 of 10 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
07/05/2023321782950Open ↗
10/31/2018321782950Open ↗
10/31/2018321782950Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
05/08/2024340892467Open ↗
04/03/2024340892467Open ↗
▸BISSIDEWALK SHED APPLICATION & PERMIT1
05/12/2022321782950Open ↗
▸BISTEMPORARY FENCE APPLICATION & PERMIT1
05/12/2022321782950Open ↗
▸Zoning, Tax Lot & Property Records8
▸BISZONING DIAGRAM2
07/24/2023321782950Open ↗
11/02/2018321782950Open ↗
▸DOB NOWZD1: DOB Zoning Diagram2
08/22/2026B00977949-P1Open ↗
08/13/2026B00977949-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/22/2026B00977949-P1Open ↗
08/13/2026B00977949-I1Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
10/16/2018321782950Open ↗
▸BISZONING EXHIBIT II: CERTIFICATION1
10/16/2018321782950Open ↗
▸Seals & Professional Certifications37
▸DOB NOWDPL-1: Design Professional Seal & Signature19
09/11/2026B01327889-I1Open ↗
08/27/2026B00852647-I1Open ↗
08/27/2026B00893989-I1Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/05/2026B00977949-S2Open ↗
09/01/2026B00977949-S7Open ↗
08/29/2026B01008674-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/05/2026B00977949-S2Open ↗
09/01/2026B00977949-S7Open ↗
08/25/2026B00977949-S1Open ↗
Showing 3 of 6 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
07/03/2023340892467Open ↗
10/26/2018340638787Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
11/09/2018321782950Open ↗
11/09/2018321782950Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/03/2023340892467Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/02/2018321782950Open ↗
▸BISFIRE ALARM SYSTEM FILING NUMBER1
05/12/2022321782950Open ↗
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B00977949-I1Open ↗
▸Safety & Tenant Protection9
▸BISSTREET TREE CHECKLIST2
04/03/2024340892467Open ↗
03/02/2018321782950Open ↗
▸DOB NOWStreet Tree Checklist2
08/22/2026B00977949-P1Open ↗
08/15/2026B00977949-I1Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
11/09/2018321782950Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
11/09/2018321782950Open ↗
▸BISBPP: STREET TREES SITE PLAN1
05/08/2024340892467Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
11/09/2018321782950Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00977949-I1Open ↗
▸Environmental & Asbestos4
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
10/25/2018321782950Open ↗
10/25/2018321782950Open ↗
03/02/2018321782950Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/25/2026B01008674-I1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
05/12/2022321782950Open ↗
▸Inspections & Test Reports7
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
05/12/2022321782950Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
05/12/2022321782950Open ↗
▸BISBORINGS / TEST PITS (TR-4) 27-7201
11/23/2018321782950Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
11/09/2018321782950Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
05/12/2022321782950Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026B00920985-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00920985-I1Open ↗
▸Approvals, Objections & Sign-offs6
▸BISSCHEDULE A - OCCUPANCY / USE4
03/24/2023321782950Open ↗
03/20/2023321782950Open ↗
11/16/2018321782950Open ↗
Showing 3 of 4 on file for this type
▸BISHOUSE CONNECTION SIGNOFF1
05/11/2023321782950Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
01/18/2019321782950Open ↗
▸Cost, Insurance & Ownership7
▸BISPROJECT-SPECIFIC GL INSURANCE4
02/10/2023321782950Open ↗
02/09/2023321782950Open ↗
02/02/2023321782950Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT2
10/25/2018321782950Open ↗
03/02/2018321782950Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE1
01/27/2023321782950Open ↗
▸Filing & Intake Forms14
▸BISADDITIONAL INFORMATION5
08/23/2023321782950Open ↗
07/24/2023321782950Open ↗
02/02/2023321782950Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM4
02/10/2023321782950Open ↗
02/09/2023321782950Open ↗
02/02/2023321782950Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
07/03/2023340892467Open ↗
10/26/2018340638787Open ↗
▸BISEFILING COVER SHEET2
10/25/2018321782950Open ↗
03/02/2018321782950Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
05/08/2024340892467Open ↗
▸Other Documents19
▸BISBPP - SUPPORTING DOCUMENTATION6
05/08/2024340892467Open ↗
05/08/2024340892467Open ↗
04/03/2024340892467Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProperty Ownership Certification4
08/25/2026B01008674-I1Open ↗
08/22/2026B00977949-P1Open ↗
08/15/2026B00977949-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial2
08/22/2026B00977949-P1Open ↗
08/13/2026B00977949-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/22/2026B00977949-P1Open ↗
08/13/2026B00977949-I1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00977949-S1Open ↗
08/13/2026B00977949-S4Open ↗
▸BISPLOT DIAGRAM1
03/02/2018321782950Open ↗
▸BISSD 1 & 21
05/12/2022321782950Open ↗
▸DOB NOWStructure Photographs1
08/13/2026B01008674-I1Open ↗