| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/19/2026 | Permit Issued | HIL GROUP LLC | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/19/2026 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| 10/28/2025 | Complete | RICHARD NEU | — |
| 07/10/2025 | Complete | HIVOLTS ELECTRICAL INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| 910 EAST 167 | 36 | 07/08/2026 |
| SAFELINE GROUP | 4 | 04/09/2026 |
| HIL GROUP | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/10/2024 | $820K | — | Private party → 910 EAST 167 LLC | $488/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BAOBAB ARCHITECTS P.C. | 13 | 03/19/2026 |
| MJE PROFESSIONAL SERVICES | 1 | 10/27/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ELLIPSES DESIGN | 10 | 03/21/2026 |
| SNR EXPEDITING DESIGN | 2 | 03/21/2026 |
| REDCUT EXPEDITING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIL GROUP LLC | General Contractor | 7 | 07/08/2026 |
| BRUCHE MECHANICAL NY LLC | Fire Protection | 1 | 07/08/2026 |
| SAFELINE GROUP INC | General Contractor | 1 | 04/09/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 11 | 03/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | HIL GROUP | 02/10/2026 |
| DOB NOW | Mechanical Systems | Signed-off | HIL GROUP | 12/19/2025 |
| DOB NOW | Sprinklers | Signed-off | BRUCHE MECHANICAL NY LLC | 11/28/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFELINE GROUP INC | 10/27/2025 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 10/06/2025 |
| DOB NOW | Structural | Signed-off | HIL GROUP | 08/27/2025 |
| DOB NOW | Foundation | Signed-off | HIL GROUP | 08/22/2025 |
| DOB NOW | Support of Excavation | Signed-off | HIL GROUP | 08/07/2025 |
| DOB NOW | General Construction | Permit Issued | HIL GROUP | 08/01/2025 |
| DOB NOW | Construction Fence | Signed-off | HIL GROUP | 07/23/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/06/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/17/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/17/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/26/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/26/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/26/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/16/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/16/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/12/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/12/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 03/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/03/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/23/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/20/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/13/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/03/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/02/2026 | Post-installed Anchors | Shahrish Shuvo | special |
| 04/02/2026 | Sprinkler Systems | Shahrish Shuvo | special |
| 04/02/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 03/24/2026 | Post-installed Anchors | Shahrish Shuvo | special |
| 03/24/2026 | Construction Operations Influencing Adjacent Structures | Shahrish Shuvo | special |
| 03/24/2026 | Concrete - Cast-In-Place | Shahrish Shuvo | special |
| 03/24/2026 | Structural Steel - High Strength Bolting | Shahrish Shuvo | special |
| 03/24/2026 | Structural Steel - Details | Shahrish Shuvo | special |
| 03/24/2026 | Raising and Moving of a Building | Shahrish Shuvo | special |
| 03/24/2026 | Structural Stability – Alterations of existing buildings | Shahrish Shuvo | special |
| 03/24/2026 | Structural Steel - Welding | Shahrish Shuvo | special |
| 03/24/2026 | Final | Shahrish Shuvo | progress |
| 03/23/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 03/23/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Shahrish Shuvo | special |
| 03/23/2026 | HVAC-R and service water heating system controls | Shahrish Shuvo | energy_progress |
| 03/23/2026 | Maintenance information | Shahrish Shuvo | energy_progress |
| 03/23/2026 | HVAC-R and service water piping design and insulation | Shahrish Shuvo | energy_progress |
| 03/23/2026 | HVAC-R and service water heating equipment | Shahrish Shuvo | energy_progress |
| 03/18/2026 | Maintenance information | Shahrish Shuvo | energy_progress |
| 03/18/2026 | HVAC-R and service water piping design and insulation | Shahrish Shuvo | energy_progress |
| 03/18/2026 | HVAC-R and service water heating equipment | Shahrish Shuvo | energy_progress |
| 03/18/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Shahrish Shuvo | special |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Shahrish Shuvo | special |
| 03/18/2026 | HVAC-R and service water heating system controls | Shahrish Shuvo | energy_progress |
| 09/22/2025 | Maintenance information | Shahrish Shuvo | energy_progress |