| Owner | Filings | Most Recent |
|---|---|---|
| ELITE CONCRETE | 2 | 09/01/2026 |
| J G CONSTRUCTION SRVCS | 2 | 07/17/2026 |
| NELSON CAPITAL ASSOCIATES LLC | 26 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/01/2025 | $830K | — | — → — | $347/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LOMBARDO PROFESSIONAL ENGINEERING | 1 | 08/10/2026 |
| ALWAYS FAST SERVICES CORP | 2 | 07/16/2026 |
| AG ENGINEERING PLLC | 3 | 07/09/2026 |
| MJE PROFESSIONAL SERVICES | 1 | 02/18/2026 |
| VASILIOS ARTEMIOU PE | 2 | 01/07/2026 |
| STRUCTURE 22 ENGINEERING | 2 | 11/13/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 13 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 8 | 08/11/2026 |
| SAFETY PLMBG & HTG LLC | Plumbing | 4 | 03/22/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 2 | 07/17/2026 |
| YOSEF BLAU | Electrical | 1 | 03/21/2026 |
| STAR COMPANIESS LLC | General Contractor | 1 | 04/09/2026 |
| A. M. PLUMBING COMPANY | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 6 | 07/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Signed-off | STAR COMPANIESS LLC | 03/16/2026 |
| BIS | PL | ISSUED | SAFETY PLMBG & HTG LLC | 12/01/2017 |
| BIS | OT | ISSUED | CONSTRUCTIVE PRO INC | 11/22/2017 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/10/2026 | Permit Issued | MJH CONSTRUCTION CORP | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | A. M. PLUMBING COMPANY | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | A. M. PLUMBING COMPANY | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2026 | Permit Issued | J & G CONSTRUCTION SVCS | Scaffold |
| 07/16/2026 | Permit Issued | J & G CONSTRUCTION SVCS | Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | A. M. PLUMBING COMPANY | Earthwork |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2026 | Exterior Insulation and Finish Systems (EIFS) | SHAHRIAR QUAYYUM | special |
| 07/07/2026 | Protection of exposed foundation insulation | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Exterior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Lighting in dwelling units | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Air barrier — testing | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Electrical motors and elevators | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Lighting controls | SHAHRIAR QUAYYUM | energy_progress |
| 07/07/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 07/07/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 07/07/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 11/26/2025 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 11/26/2025 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 11/26/2025 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 11/26/2025 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 11/26/2025 | Shutoff dampers | SHAHRIAR QUAYYUM | energy_progress |
| 11/26/2025 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 11/26/2025 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |