← Back
Two stories - detached, small or mid-size
912 AVENUE L
BROOKLYN · BIN 3171926
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R5Zoning
1,445 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 2,600 sf lot · 0.56 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Permit Issued — active, not yet Signed-off
Floor 2Under Construction8p · 2 filings · 20 docs
Floor 1Under Construction7p · 2 filings · 20 docs
CellarUnder Construction9p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/30/2020$1.4M—Private party → Private party$947/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GARFINKEL ARCHITECT, PLLC204/24/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
OVADIA CONSTRUCTION GROUPGeneral Contractor208/07/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AZ PROFESSIONAL ENGINEERI766204/24/2026
Building Lifecycle
All (50)Filed (2)Permit Issued (2)Objection (16)Special Inspection (30)
08/06/2026
Permit issued — Foundation
B01389971-I1-GC-CX
07/13/2026
Objection resolved — Resolved
07/08/2026
Objection raised — Scope
06/29/2026
Objection resolved — Addressed
06/16/2026
Objection resolved — Addressed
06/15/2026
Objection resolved — Addressed
06/15/2026
Objection resolved — Addressed
06/15/2026
Objection resolved — Addressed
06/15/2026
Objection resolved — Addressed
06/15/2026
Objection resolved — Addressed
05/06/2026
Objection raised — Other
05/06/2026
Objection raised — Other
05/06/2026
Objection raised — Other
05/06/2026
Objection raised — Other
04/30/2026
Objection raised — Scope
04/30/2026
Objection raised — Mechanical
04/30/2026
Objection raised — Scope
04/24/2026
Filed — Alteration
Extend first floor and second floor
B01389971-I1
04/22/2026
Special inspection requirement — Permanent certificate
VIJAY KUMAR
04/22/2026
Special inspection requirement — Subgrade Inspections
VIJAY KUMAR
04/22/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Bin Li
04/22/2026
Special inspection requirement — Energy Code Compliance Inspections
VIJAY KUMAR
04/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
VIJAY KUMAR
04/22/2026
Special inspection requirement — Fenestration air leakage
VIJAY KUMAR
04/22/2026
Special inspection requirement — Interior lighting power
VIJAY KUMAR
04/22/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
VIJAY KUMAR
04/22/2026
Special inspection requirement — Fenestration areas
VIJAY KUMAR
04/22/2026
Special inspection requirement — Maintenance information
VIJAY KUMAR
04/22/2026
Special inspection requirement — Insulation placement and R values
VIJAY KUMAR
04/22/2026
Special inspection requirement — Air barrier - visual inspection
VIJAY KUMAR
04/22/2026
Special inspection requirement — Protection of exposed foundation insulation
VIJAY KUMAR
04/22/2026
Special inspection requirement — Electric vehicle service equipment requirements
VIJAY KUMAR
04/22/2026
Special inspection requirement — Metering
VIJAY KUMAR
04/22/2026
Special inspection requirement — Concrete - Cast-In-Place
VIJAY KUMAR
04/22/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
VIJAY KUMAR
04/22/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
VIJAY KUMAR
04/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
VIJAY KUMAR
04/22/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
VIJAY KUMAR
04/21/2026
Permit issued — General Construction
B01376850-I1-GC
04/20/2026
Special inspection requirement — Footing and Foundation
VIJAY KUMAR
04/20/2026
Special inspection requirement — Final
VIJAY KUMAR
04/14/2026
Filed — Alteration
Partial interior renovation
B01376850-I1
03/26/2026
Special inspection requirement — Preliminary
VIJAY KUMAR
03/26/2026
Special inspection requirement — Metering
VIJAY KUMAR
03/26/2026
Special inspection requirement — Insulation placement and R values
VIJAY KUMAR
03/26/2026
Special inspection requirement — Air barrier - visual inspection
VIJAY KUMAR
03/26/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
VIJAY KUMAR
03/26/2026
Special inspection requirement — Interior lighting power
VIJAY KUMAR
03/26/2026
Special inspection requirement — Fenestration air leakage
VIJAY KUMAR
03/26/2026
Special inspection requirement — Fenestration areas
VIJAY KUMAR
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedOVADIA CONSTRUCTION GROUP08/06/2026
DOB NOWGeneral ConstructionPermit IssuedOVADIA CONSTRUCTION GROUP04/21/2026
1 project · most recent 04/24/2026
Wood
FiledStatusContractorScope
04/24/2026Permit IssuedOVADIA CONSTRUCTION GROUPWood
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
04/22/2026Permanent certificateVIJAY KUMARenergy_progress
04/22/2026Subgrade InspectionsVIJAY KUMARspecial
04/22/2026Subsurface Investigations (Borings/Test Pits)Bin Lispecial
04/22/2026Energy Code Compliance InspectionsVIJAY KUMARprogress
04/22/2026Fire-Resistance Rated ConstructionVIJAY KUMARprogress
04/22/2026Fenestration air leakageVIJAY KUMARenergy_progress
04/22/2026Interior lighting powerVIJAY KUMARenergy_progress
04/22/2026Fenestration and door U-factor and product ratingsVIJAY KUMARenergy_progress
04/22/2026Fenestration areasVIJAY KUMARenergy_progress
04/22/2026Maintenance informationVIJAY KUMARenergy_progress
04/22/2026Insulation placement and R valuesVIJAY KUMARenergy_progress
04/22/2026Air barrier - visual inspectionVIJAY KUMARenergy_progress
04/22/2026Protection of exposed foundation insulationVIJAY KUMARenergy_progress
04/22/2026Electric vehicle service equipment requirementsVIJAY KUMARenergy_progress
04/22/2026MeteringVIJAY KUMARenergy_progress
04/22/2026Concrete - Cast-In-PlaceVIJAY KUMARspecial
04/22/2026Excavations - Sheeting, Shoring, and BracingVIJAY KUMARspecial
04/22/2026Exterior Insulation and Finish Systems (EIFS)VIJAY KUMARspecial
04/22/2026Fire-Resistant Penetrations and JointsVIJAY KUMARspecial
04/22/2026Structural Stability – Alterations of existing buildingsVIJAY KUMARspecial
04/20/2026Footing and FoundationVIJAY KUMARprogress
04/20/2026FinalVIJAY KUMARprogress
03/26/2026PreliminaryVIJAY KUMARprogress
03/26/2026MeteringVIJAY KUMARenergy_progress
03/26/2026Insulation placement and R valuesVIJAY KUMARenergy_progress
Latest 25 of 34.
▾Documents — 24 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026B01376850-I1Request digital key ↗
08/15/2026B01389971-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZoning Exhibit form (1-5)1
08/15/2026B01389971-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026B01389971-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWSpecial Inspector Seal & Signature5
08/28/2026B01389971-I1Open ↗
08/28/2026B01389971-I1Open ↗
08/28/2026B01389971-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
08/28/2026B01389971-I1Open ↗
08/28/2026B01389971-I1Open ↗
08/28/2026B01389971-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026B01376850-I1Open ↗
08/17/2026B01389971-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026B01376850-I1Open ↗
08/15/2026B01389971-I1Open ↗
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT1
08/15/2026B01389971-I1Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/15/2026B01389971-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/15/2026B01389971-I1Open ↗
▸Other Documents3
▸DOB NOWSite Survey: Initial1
08/15/2026B01389971-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026B01389971-I1Open ↗
▸DOB NOWPlot Diagram1
08/15/2026B01389971-I1Open ↗