← Back
BuildNYC
Three families
916 PRESIDENT STREET
BROOKLYN · Park Slope · BIN 3024805
💬 Discuss this project
1899Year Built
4Stories
C0Building Class
R7BZoning
4,529 sfGross Floor Area
3Units
Three families · 2,000 sf lot · 2.26 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire Protection
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofRoof mounted photovoltaic system installationUnder Construction3p · 2 filings · 20 docs
Floor 4Under Construction35p · 1 filing · 20 docs
Floor 3Under Construction36p · 1 filing · 20 docs
Floor 2Under Construction36p · 1 filing · 20 docs
Floor 1Under Construction38p · 1 filing · 20 docs
CellarRoof mounted photovoltaic system installationUnder Construction36p · 2 filings · 20 docs
BasementUnder Construction40p · 1 filing · 20 docs
Site & exteriorUnder Construction1 filing
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/12/2024$5.3M—Private party → Private party$1,170/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
All City Engineering511/16/2026
Trevor O. Flowers110/26/2026
Celmer Architecture609/22/2026
Silman303/24/2026
NY Building Associates111/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Brooklyn Solarworks103/21/2026
Commercial Capital USA1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Davaro ContractingGeneral Contractor1108/05/2026
Davaro Contractingspecialty_contractor408/05/2026
Big Apple Sewer & Drain IPlumbing207/08/2026
HF Group Plumbing & SpnklerFire Protection208/16/2026
Steel ConstructionScaffold110/28/2026
Brooklyn Solarworksspecialty_contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AG Engineering88991111/16/2026
Mohammad Ahead - Professi9286403/24/2026
NKM Engineering6244111/06/2025
SGM Engineering2366108/16/2024
Building Lifecycle
11/16/2026
Filed — Alteration CO
Plumbing fit out work for 2 family.
B01079036-P9
10/27/2026
Permit issued — Supported Scaffold
B01480069-I1-SF
10/26/2026
Filed — Alteration
B01480069-I1
10/05/2026
Filed — Alteration CO
Plumbing fit out work for 2 family.
B01079036-P8
09/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ARIEL GOLSHAN
81 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupported ScaffoldPermit IssuedSteel Construction10/27/2026
DOB NOWSprinklersPermit IssuedHF Group Plumbing & Spnkler08/14/2026
DOB NOWStructuralPermit IssuedDavaro Contracting08/04/2026
DOB NOWMechanical SystemsPermit IssuedDavaro Contracting08/04/2026
DOB NOWGeneral ConstructionPermit IssuedDavaro Contracting08/04/2026
DOB NOWStructuralPermit IssuedDavaro Contracting04/10/2026
DOB NOWGeneral ConstructionPermit IssuedDavaro Contracting04/10/2026
DOB NOWMechanical SystemsPermit IssuedDavaro Contracting04/07/2026
DOB NOWPlumbingPermit IssuedBig Apple Sewer & Drain I01/20/2026
DOB NOWSolarSigned-offBrooklyn Solarworks11/06/2025
DOB NOWGeneral ConstructionPermit IssuedDavaro Contracting03/31/2025
DOB NOWMechanical SystemsPermit IssuedDavaro Contracting03/27/2025
DOB NOWStructuralPermit IssuedDavaro Contracting03/27/2025
DOB NOWSprinklersPermit IssuedHF Group Plumbing & Spnkler02/18/2025
DOB NOWPlumbingPermit IssuedBig Apple Sewer & Drain I02/14/2025
DOB NOWMechanical SystemsPermit IssuedDavaro Contracting10/30/2024
DOB NOWStructuralPermit IssuedDavaro Contracting10/29/2024
DOB NOWGeneral ConstructionPermit IssuedDavaro Contracting10/29/2024
1 project · most recent 11/16/2026
Sprinkler System
FiledStatusContractorScope
11/16/2026Permit IssuedHF Group Plumbing & SpnklerSprinkler System
1 project · most recent 11/16/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
11/16/2026Permit IssuedBig Apple Sewer & Drain IGas, Storm, Water/Sanitary
2 projects · most recent 10/21/2025
General Wiring
FiledStatusContractorScope
10/21/2025CompleteBrookyln Solarworks—
03/27/2025Permit IssuedJP & Son ElectricGeneral Wiring
1 project · most recent 11/16/2026
Steel Concrete Wood
FiledStatusContractorScope
11/16/2026Permit IssuedSmart Plumbing & HeatingSteel, Concrete, Wood
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
08/12/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/01/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/01/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/23/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 65
DateRequirementInspectorRole
09/29/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
09/17/2026Energy Code Compliance InspectionsARIEL GOLSHANprogress
09/17/2026Fire-Resistance Rated ConstructionARIEL GOLSHANprogress
09/17/2026Chimneys and ventsARIEL GOLSHANspecial
09/17/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
09/17/2026Structural Stability – Alterations of existing buildingsARIEL GOLSHANspecial
08/03/2026Fire-Resistance Rated ConstructionARIEL GOLSHANprogress
08/03/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
08/03/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
08/03/2026Structural Stability – Alterations of existing buildingsARIEL GOLSHANspecial
08/03/2026Chimneys and ventsARIEL GOLSHANspecial
08/03/2026Energy Code Compliance InspectionsARIEL GOLSHANprogress
07/06/2026Chimneys and ventsARIEL GOLSHANspecial
07/06/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
07/06/2026Fire-Resistance Rated ConstructionARIEL GOLSHANprogress
07/06/2026Structural Stability – Alterations of existing buildingsARIEL GOLSHANspecial
07/06/2026Energy Code Compliance InspectionsARIEL GOLSHANprogress
07/02/2026Fire-Resistant Penetrations and JointsARIEL GOLSHANspecial
04/13/2026Concrete - Cast-In-PlaceMOHAMMAD AHEADspecial
04/13/2026FinalARIEL GOLSHANprogress
04/13/2026Structural Wood FrameMOHAMMAD AHEADprogress
04/13/2026Structural Steel - WeldingMOHAMMAD AHEADspecial
04/13/2026Structural Steel - DetailsMOHAMMAD AHEADspecial
04/13/2026Post-installed AnchorsMOHAMMAD AHEADspecial
04/13/2026Structural Stability – Alterations of existing buildingsMOHAMMAD AHEADspecial
Latest 25 of 65.