← Back
Miscellaneous warehouse
92-10 182 PLACE
QUEENS · BIN 4442258
💬 Discuss this project
1928Year Built
2Stories
E9Building Class
M2-3AZoning
1,080 sfGross Floor Area
1Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
Miscellaneous warehouse · Owner of record: GOTHAM REALTY 2 LLC · 28,500 sf lot · 0.04 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof1p · 2 filings · 11 docs
Floor 317p · 3 filings · 20 docs
Floor 213p · 1 filing · 20 docs
Floor 12p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GOTHAM REALTY 2 LLC303/22/2026
SILVERCUPSCAFFOLDING103/22/2026
PARSONS CONSTRUCTION203/21/2026
FRED STARK ESTATE303/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/29/2021$4.5M—92 182ND PLACE LLC → GOTHAM REALTY 2 LLC$4,167/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STRACAR ENGINEERING, P.C.1308/19/2025
FL&M ENGINEERING DESIGN &INSPECTION102/25/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STRACAR ENGINEERING P C2603/21/2026
GREEN STUDIO203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
YATZIV CORPGeneral Contractor407/08/2026
CARMINE'S MECHANICAL INCPlumbing307/08/2026
CARMINE'S MECHANICAL INCGeneral Contractor307/08/2026
MANHATTAN D ENTERPRISESGeneral Contractor303/21/2026
PRIME ELECTRICAL CORPElectrical103/22/2026
DAVID MONGUILLOTElectrical103/21/2026
V. VASS ELECTRIC CORPElectrical103/22/2026
A & E MECHANICAL CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519308/19/2025
STRACAR SPECIAL INSPECTIO229605/06/2024
Building Lifecycle
All (88)Filed (14)Permit Issued (9)Signed Off (6)Violation (17)Inspection (12)Special Inspection (30)
10/07/2025
Violation issued (ECB, open)
Construction
10/07/2025
Violation issued (ECB, open)
Construction
09/12/2025
Special inspection requirement — Footing and Foundation
Younes Abouyaala
09/12/2025
Special inspection requirement — Interior lighting power
Younes Abouyaala
09/12/2025
Special inspection requirement — Exterior lighting power
Younes Abouyaala
09/12/2025
Special inspection requirement — Final
NAVEEN KUMAR
09/12/2025
Special inspection requirement — Lighting controls
Younes Abouyaala
09/12/2025
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
09/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
09/12/2025
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
09/12/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Younes Abouyaala
09/12/2025
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
08/19/2025
Filed — Alteration CO
PARTIAL DEMO OF 2 STORY SECTION BUILDING AND STRUCTURAL WORK TO ERECT PORTABLE CONCRETE BATCH PLANT FOR MIXING BUILDING MATERIALS.
Q00721212-P3
08/18/2025
Special inspection requirement — Final
NAVEEN KUMAR
08/18/2025
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
08/18/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Younes Abouyaala
08/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
08/18/2025
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
08/18/2025
Special inspection requirement — Subgrade Inspections
Younes Abouyaala
08/18/2025
Special inspection requirement — Footing and Foundation
Younes Abouyaala
08/18/2025
Special inspection requirement — Exterior lighting power
Younes Abouyaala
08/18/2025
Special inspection requirement — Interior lighting power
Younes Abouyaala
08/18/2025
Special inspection requirement — Lighting controls
Younes Abouyaala
06/26/2025
Signed off — Alteration
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS.
Q00890565-I1
06/24/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/09/2025
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
05/09/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
05/02/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/01/2025
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
04/09/2025
Signed off — Alteration
PLUMBING WORK ON FLOORS 1-3, OPEN SPACE AND ROOF.
Q00737005-I1
03/21/2025
Permit issued — Plumbing
Q00890565-I1-EW-SP
11/25/2024
Permit issued — Sprinklers
Q00890565-I1-PL
05/09/2024
Signed off — Alteration
Q01037123-I1
05/09/2024
Signed off — Alteration
INTERIOR ALTERATION ON FLOORS 1-3 PER PLANS.
Q00736917-I1
05/08/2024
Permit issued — Mechanical Systems
Q01037123-I1-MS
05/08/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/07/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/06/2024
Filed — Alteration
Q01037123-I1
03/29/2024
Signed off — Alteration
INSTALLATION OF NEW HVAC SYSTEMS AS PER PLAN.
Q08038777-I1
03/27/2024
Special inspection requirement — Final
MIRO Stracar
03/27/2024
Special inspection requirement — Mechanical Systems
MIRO Stracar
03/27/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIRO Stracar
03/15/2024
Filed — Alteration
INSTALLATION OF NEW HVAC SYSTEMS AS PER PLAN.
Q08038777-P1
02/07/2024
Permit issued — General Construction
Q00736917-I1-GC
01/18/2024
Special inspection requirement — Interior lighting power
MIRO Stracar
01/18/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MIRO Stracar
01/18/2024
Special inspection requirement — Final
MIRO Stracar
01/17/2024
Filed — Alteration
INTERIOR ALTERATION ON FLOORS 1-3 PER PLANS.
Q00736917-P1
01/17/2024
Special inspection requirement — Interior lighting power
11/27/2023
Special inspection requirement — Sprinkler Systems
MIRO Stracar
11/21/2023
Filed — Alteration
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS.
Q00890565-P1
10/19/2023
Permit issued — Structural
Q00721212-I1-GC-CX
08/31/2023
Permit issued — Sprinklers
Q00890565-I1-PL
08/30/2023
Special inspection requirement — Sprinkler Systems
MIRO Stracar
07/21/2023
Filed — Alteration
INSTALLATION OF NEW SPRINKLER SYSTEM AS PER PLANS.
Q00890565-I1
05/22/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/04/2023
Filed — Alteration
PLUMBING WORK ON FLOORS 1-3, OPEN SPACE AND ROOF.
Q00737005-P2
04/17/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/13/2023
Permit issued — Mechanical Systems
Q08038777-I1-MS
02/20/2023
Filed — Alteration
INSTALLATION OF NEW HVAC SYSTEMS AS PER PLAN.
Q08038777-I1
Latest 60 of 88 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offA&E MECHANICAL CORP03/21/2025
DOB NOWSprinklersSigned-offCARMINE'S MECHANICAL INC11/25/2024
DOB NOWMechanical SystemsSigned-offCARMINE'S MECHANICAL INC05/08/2024
DOB NOWGeneral ConstructionSigned-offYATZIV CORP02/07/2024
DOB NOWStructuralPermit IssuedYATZIV CORP10/19/2023
DOB NOWSprinklersSigned-offCARMINE'S MECHANICAL INC08/31/2023
DOB NOWMechanical SystemsSigned-offCARMINE'S MECHANICAL INC04/13/2023
DOB NOWPlumbingSigned-offCARMINE'S MECHANICAL INC06/21/2022
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES02/28/2022
BISEQISSUEDFHA CONTRACTING CORP04/24/2017
BISOTISSUEDFHA CONTRACTING CORP04/24/2017
BISEQISSUEDPARSONS CONSTRUCTION INC11/23/2016
3 projects · most recent 12/04/2025
General Wiring
FiledStatusContractorScope
12/04/2025CompleteKOPP ELECTRIC CORPGeneral Wiring
03/28/2024CompletePRIME ELECTRICAL CORPGeneral Wiring
02/22/2022CompleteV. VASS ELECTRIC CORP—
1 project · most recent 08/19/2025
Steel Concrete
FiledStatusContractorScope
08/19/2025Permit IssuedYATZIV CORPSteel, Concrete
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
06/24/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/09/2025Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
05/09/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
05/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/01/2025Pass-Final SP - Up to 9 Requested FloorsPassView ↗
05/08/2024Pass-Final CND-Occupancy InspectionPassView ↗
05/07/2024Pass-Final CND-Occupancy InspectionPassView ↗
05/22/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/17/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/02/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/02/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/28/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
09/12/2025Footing and FoundationYounes Abouyaalaprogress
09/12/2025Interior lighting powerYounes Abouyaalaenergy_progress
09/12/2025Exterior lighting powerYounes Abouyaalaenergy_progress
09/12/2025FinalNAVEEN KUMARprogress
09/12/2025Lighting controlsYounes Abouyaalaenergy_progress
09/12/2025Structural Steel - DetailsYounes Abouyaalaspecial
09/12/2025Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
09/12/2025Concrete - Cast-In-PlaceYounes Abouyaalaspecial
09/12/2025Excavations - Sheeting, Shoring, and BracingYounes Abouyaalaspecial
09/12/2025Subgrade InspectionsYounes Abouyaalaspecial
08/18/2025FinalNAVEEN KUMARprogress
08/18/2025Concrete - Cast-In-PlaceYounes Abouyaalaspecial
08/18/2025Excavations - Sheeting, Shoring, and BracingYounes Abouyaalaspecial
08/18/2025Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
08/18/2025Structural Steel - DetailsYounes Abouyaalaspecial
08/18/2025Subgrade InspectionsYounes Abouyaalaspecial
08/18/2025Footing and FoundationYounes Abouyaalaprogress
08/18/2025Exterior lighting powerYounes Abouyaalaenergy_progress
08/18/2025Interior lighting powerYounes Abouyaalaenergy_progress
08/18/2025Lighting controlsYounes Abouyaalaenergy_progress
03/27/2024FinalMIRO Stracarprogress
03/27/2024Mechanical SystemsMIRO Stracarspecial
03/27/2024Fire-Resistant Penetrations and JointsMIRO Stracarspecial
01/18/2024Interior lighting powerMIRO Stracarenergy_progress
01/18/2024Fire-Resistant Penetrations and JointsMIRO Stracarspecial
Latest 25 of 41.
▾Documents — 105 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/26/2026Q00686708-I1Request digital key ↗
08/26/2026Q00736917-I1Request digital key ↗
08/26/2026Q00736917-P1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
06/26/2019421435600Open ↗
04/11/2017421435600Open ↗
11/22/2016440364749Open ↗
▸BISWORK PERMIT APPLICATION2
04/26/2017421435600Open ↗
11/22/2016440364749Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00721212-I1Open ↗
▸Seals & Professional Certifications48
▸DOB NOWProgress Inspector Seal & Signature14
09/02/2026Q00736917-I1Open ↗
09/02/2026Q00736917-I1Open ↗
08/27/2026Q08038777-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature14
09/03/2026Q00890565-I1Open ↗
09/02/2026Q00736917-I1Open ↗
08/27/2026Q08038777-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/26/2026Q00736917-P1Open ↗
08/26/2026Q00736917-I1Open ↗
08/23/2026Q08038777-I1Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
10/22/2019421435600Open ↗
05/15/2019440364749Open ↗
04/11/2017421435600Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
04/11/2017421435600Open ↗
11/22/2016440364749Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/22/2016440364749Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
04/11/2017421435600Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/22/2016440364749Open ↗
▸Trade Schedules & Equipment1
▸BISJAMAICA: DEP SEWER CONNECTION APPROVAL1
11/22/2016440364749Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist3
08/13/2026Q00721212-I1Open ↗
08/13/2026Q00721212-P1Open ↗
08/13/2026Q00721212-P3Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00721212-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00721212-I1Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/26/2026Q00736917-P1Open ↗
08/26/2026Q00736917-I1Open ↗
08/23/2026Q08038777-I1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
04/11/2017421435600Open ↗
▸Energy Compliance4
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026Q00736917-I1Open ↗
08/13/2026Q00721212-I1Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
04/11/2017421435600Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/22/2019421435600Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
11/23/2016440364749Open ↗
11/22/2016440364749Open ↗
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
10/22/2019421435600Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
10/24/2019421435600Open ↗
05/15/2019440364749Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
10/22/2019421435600Open ↗
04/11/2017421435600Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION2
10/03/2019421435600Open ↗
04/28/2017421435600Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/22/2016440364749Open ↗
▸BISEFILING COVER SHEET1
04/17/2017421435600Open ↗
▸Other Documents6
▸DOB NOWProperty Ownership Certification3
08/13/2026Q00721212-I1Open ↗
08/13/2026Q00721212-P1Open ↗
08/13/2026Q00721212-P3Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026Q00721212-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026Q00721212-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00721212-I1Open ↗