← Back
Two family converted from one family
92-26 176 STREET
QUEENS · Jamaica · BIN 4217579
💬 Discuss this project
1920Year Built
2Stories
B3Building Class
R5Zoning
1,216 sfGross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Two family converted from one family · 2,500 sf lot · 0.49 FAR built · Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC111/20/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272111/20/2024
Building Lifecycle
All (11)Filed (1)Permit Issued (1)Violation (4)Special Inspection (5)
11/27/2024
Permit issued — Solar
Q01141137-I1-SL
11/20/2024
Filed — Alteration
Q01141137-I1
11/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
11/12/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
11/12/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
11/12/2024
Special inspection requirement — Final
Walid Abdulla
11/12/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/09/2017
Violation issued (HPD, open)
C
02/08/2014
Violation issued (HPD, closed)
C
08/29/2011
Violation issued (ECB, closed)
Unknown
08/29/2011
Violation issued (ECB, closed)
Unknown
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC11/27/2024
1 project · most recent 11/20/2024
FiledStatusContractorScope
11/20/2024CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
11/12/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
11/12/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
11/12/2024Energy Code Compliance InspectionsWalid Abdullaprogress
11/12/2024FinalWalid Abdullaprogress
11/12/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026Q01141137-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/22/2026Q01141137-I1Open ↗
08/22/2026Q01141137-I1Open ↗
08/22/2026Q01141137-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/22/2026Q01141137-I1Open ↗
08/22/2026Q01141137-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/21/2026Q01141137-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026Q01141137-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01141137-I1Open ↗