1950Year Built
2Stories
B9Building Class
R4Zoning
1,602 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Miscellaneous two family · 1,967 sf lot · 0.81 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof3p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC101/18/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854101/18/2024
Building Lifecycle
All (18)Filed (1)Permit Issued (1)Signed Off (1)Violation (2)Objection (8)Special Inspection (5)
05/23/2024
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X00991858-I1
02/07/2024
Permit issued — Solar
X00991858-I1-SL
02/02/2024
Objection resolved — Addressed
01/29/2024
Objection resolved — Addressed
01/29/2024
Objection resolved — Addressed
01/29/2024
Objection resolved — Addressed
01/24/2024
Objection raised — Other
01/22/2024
Objection raised — Other
01/22/2024
Objection raised — Other
01/22/2024
Objection raised — Other
01/18/2024
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X00991858-I1
01/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
01/17/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
01/17/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
01/17/2024
Special inspection requirement — Final
TOM PETERSEN
01/17/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
02/22/2022
Violation issued (ECB, closed)
Construction
11/03/1994
Violation issued (DOB, closed)
V%*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY02/07/2024
2 projects · most recent 02/19/2024
FiledStatusContractorScope
02/19/2024CompleteBERGER QUALITY ELEC'L CON1 meters
01/27/2024CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/17/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
01/17/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
01/17/2024Energy Code Compliance InspectionsTOM PETERSENprogress
01/17/2024FinalTOM PETERSENprogress
01/17/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026X00991858-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/31/2026X00991858-I1Open ↗
08/31/2026X00991858-I1Open ↗
08/31/2026X00991858-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026X00991858-I1Open ↗
08/31/2026X00991858-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X00991858-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X00991858-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1