← Back
Large suburban residence
921 AVENUE P
BROOKLYN · BIN 3175160
💬 Discuss this project
1930Year Built
2.5Stories
A3Building Class
R5Zoning
3,607 sfGross Floor Area
1Units
Large suburban residence · 3,500 sf lot · 1.03 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Floor 316p · 1 filing · 20 docs
Floor 216p · 1 filing · 20 docs
Floor 117p · 1 filing · 20 docs
Cellar24p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/28/2022$1.9M—— → —$527/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AL FFRED ARCHITECTURE PLLC405/20/2024
RAHMAN CONSULTING312/28/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MISTER EXPEDITER703/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RHY CONSTRUCTION LLCGeneral Contractor1807/08/2026
TRI CITY MECHANICAL GROUP CORPPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. INT'L ENGINEERING PLLC3129605/20/2024
Building Lifecycle
All (71)Filed (7)Permit Issued (12)Signed Off (4)Inspection (5)Objection (14)Special Inspection (29)
01/03/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S1
12/17/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S2
11/21/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S4
11/21/2024
Signed off — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S3
08/26/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/19/2024
Permit issued — Plumbing
B07993512-S1-PL
08/19/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/21/2024
Permit issued — General Construction
B07993512-I1-GC
06/21/2024
Permit issued — Foundation
B07993512-S4-FO
06/21/2024
Permit issued — Structural
B07993512-S3-ST
06/21/2024
Permit issued — Support of Excavation
B07993512-S5-SE
05/24/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
05/24/2024
Special inspection requirement — HVAC-R and service water heating equipment
NANIK MASSAND
05/24/2024
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
05/24/2024
Special inspection requirement — HVAC-R and service water heating system controls
NANIK MASSAND
05/24/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
NANIK MASSAND
05/20/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-P1
06/27/2023
Permit issued — Foundation
B07993512-S4-FO
06/27/2023
Permit issued — General Construction
B07993512-I1-GC
06/22/2023
Permit issued — Construction Fence
B07993512-S2-FN
06/21/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/21/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/21/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/11/2023
Special inspection requirement — Electrical motors and elevators
NANIK MASSAND
04/27/2023
Permit issued — Plumbing
B07993512-S1-PL
01/25/2023
Permit issued — Support of Excavation
B07993512-S5-SE
01/23/2023
Permit issued — Structural
B07993512-S3-ST
01/19/2023
Permit issued — Construction Fence
B07993512-S2-FN
01/04/2023
Objection raised — Admin
01/04/2023
Objection resolved — Addressed
01/03/2023
Objection raised — Other
01/03/2023
Objection resolved — Addressed
01/03/2023
Objection raised — Structural
01/03/2023
Objection resolved — Addressed
01/03/2023
Objection raised — Admin
01/03/2023
Objection resolved — Addressed
01/03/2023
Objection raised — Structural
01/03/2023
Objection resolved — Addressed
01/03/2023
Objection raised — Energy
01/03/2023
Objection resolved — Addressed
12/28/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S4
12/28/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S5
12/23/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S3
12/12/2022
Special inspection requirement — Final
Feng Zhang
12/12/2022
Special inspection requirement — Structural Steel - Details
NANIK MASSAND
12/12/2022
Special inspection requirement — Structural Wood Frame
NANIK MASSAND
12/12/2022
Special inspection requirement — Structural Steel - High Strength Bolting
NANIK MASSAND
12/12/2022
Special inspection requirement — Structural Steel - Welding
NANIK MASSAND
12/12/2022
Special inspection requirement — Construction Operations Influencing Adjacent Structures
NANIK MASSAND
12/12/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
11/21/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S2
10/24/2022
Objection raised — Other
10/24/2022
Objection resolved — Addressed
10/21/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-S1
09/13/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Creating foundation design for 3 story horizontal extension wood framing building. Foundation work in conjunction with GC B07993512-I1. No underpinning required under this application. No dewatering required for this application.
B07993512-I1
08/25/2022
Special inspection requirement — Permanent certificate
NANIK MASSAND
08/25/2022
Special inspection requirement — Fenestration areas
NANIK MASSAND
08/25/2022
Special inspection requirement — Fenestration air leakage
NANIK MASSAND
08/25/2022
Special inspection requirement — Air barrier - visual inspection
NANIK MASSAND
08/25/2022
Special inspection requirement — Concrete - Cast-In-Place
NANIK MASSAND
Latest 60 of 71 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP08/19/2024
DOB NOWGeneral ConstructionPermit IssuedRHY CONSTRUCTION LLC06/21/2024
DOB NOWFoundationPermit IssuedRHY CONSTRUCTION LLC06/21/2024
DOB NOWStructuralPermit IssuedRHY CONSTRUCTION LLC06/21/2024
DOB NOWSupport of ExcavationPermit IssuedRHY CONSTRUCTION LLC06/21/2024
DOB NOWFoundationPermit IssuedRHY CONSTRUCTION LLC06/27/2023
DOB NOWGeneral ConstructionPermit IssuedRHY CONSTRUCTION LLC06/27/2023
DOB NOWConstruction FenceSigned-offRHY CONSTRUCTION LLC06/22/2023
DOB NOWPlumbingSigned-offFLAVIO MECHANICAL CORP04/27/2023
DOB NOWSupport of ExcavationPermit IssuedRHY CONSTRUCTION LLC01/25/2023
DOB NOWStructuralPermit IssuedRHY CONSTRUCTION LLC01/23/2023
DOB NOWConstruction FenceSigned-offRHY CONSTRUCTION LLC01/19/2023
1 project · most recent 05/20/2024
Gas Water/Sanitary
FiledStatusContractorScope
05/20/2024Signed-offTRI CITY MECHANICAL GROUPGas, Water/Sanitary
1 project · most recent 07/16/2023
General Wiring
FiledStatusContractorScope
07/16/2023Permit IssuedACCURATE ELEC'L CORP.General Wiring
1 project · most recent 05/20/2024
Steel Wood
FiledStatusContractorScope
05/20/2024Signed-offTRI CITY MECHANICAL GROUPSteel, Wood
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
08/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/19/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/21/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/21/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
05/24/2024Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
05/24/2024HVAC-R and service water heating equipmentNANIK MASSANDenergy_progress
05/24/2024Energy Code Compliance InspectionsNANIK MASSANDprogress
05/24/2024HVAC-R and service water heating system controlsNANIK MASSANDenergy_progress
05/24/2024HVAC-R and service water piping design and insulationNANIK MASSANDenergy_progress
05/11/2023Electrical motors and elevatorsNANIK MASSANDenergy_progress
12/12/2022FinalFeng Zhangprogress
12/12/2022Structural Steel - DetailsNANIK MASSANDspecial
12/12/2022Structural Wood FrameNANIK MASSANDprogress
12/12/2022Structural Steel - High Strength BoltingNANIK MASSANDspecial
12/12/2022Structural Steel - WeldingNANIK MASSANDspecial
12/12/2022Construction Operations Influencing Adjacent StructuresNANIK MASSANDspecial
12/12/2022Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
08/25/2022Permanent certificateNANIK MASSANDenergy_progress
08/25/2022Fenestration areasNANIK MASSANDenergy_progress
08/25/2022Fenestration air leakageNANIK MASSANDenergy_progress
08/25/2022Air barrier - visual inspectionNANIK MASSANDenergy_progress
08/25/2022Concrete - Cast-In-PlaceNANIK MASSANDspecial
08/25/2022Excavations - Sheeting, Shoring, and BracingNANIK MASSANDspecial
08/25/2022Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
08/25/2022Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
08/25/2022Subsurface Investigations (Borings/Test Pits)INDARDEO PARBHUNATHspecial
08/25/2022Energy Code Compliance InspectionsNANIK MASSANDprogress
08/25/2022Fire-Resistance Rated ConstructionNANIK MASSANDprogress
08/25/2022Interior lighting powerNANIK MASSANDenergy_progress
Latest 25 of 29.
▾Documents — 63 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/28/2026B07993512-I1Request digital key ↗
08/28/2026B07993512-S2Request digital key ↗
08/28/2026B07993512-S3Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
10/17/2024340865727Open ↗
09/16/2022340865727Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
07/11/2023340865727Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B07993512-P3Open ↗
08/13/2026B07993512-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026B07993512-I1Open ↗
08/13/2026B07993512-P3Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B07993512-I1Open ↗
▸Seals & Professional Certifications19
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/28/2026B07993512-I1Open ↗
08/28/2026B07993512-S2Open ↗
08/28/2026B07993512-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026B07993512-S1Open ↗
09/01/2026B07993512-S1Open ↗
08/24/2026B07993512-S3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026B07993512-S1Open ↗
08/24/2026B07993512-S3Open ↗
08/22/2026B07993512-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/16/2022340865727Open ↗
▸Safety & Tenant Protection3
▸BISBPP: STREET TREES SITE PLAN1
07/11/2023340865727Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B07993512-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B07993512-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/28/2026B07993512-I1Open ↗
08/28/2026B07993512-S2Open ↗
08/28/2026B07993512-P3Open ↗
Showing 3 of 8 on file for this type
▸Inspections & Test Reports9
▸DOB NOWSOIL REPORT4
08/13/2026B07993512-P3Open ↗
08/13/2026B07993512-I1Open ↗
08/13/2026B07993512-S5Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram3
08/13/2026B07993512-I1Open ↗
08/13/2026B07993512-S5Open ↗
08/13/2026B07993512-S4Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026B07993512-S4Open ↗
08/13/2026B07993512-S5Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
09/16/2022340865727Open ↗
▸Other Documents7
▸DOB NOWSite Survey: Initial2
08/13/2026B07993512-I1Open ↗
08/13/2026B07993512-P3Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B07993512-I1Open ↗
08/13/2026B07993512-P3Open ↗
▸DOB NOWProperty Ownership Certification2
08/28/2026B07993512-I1Open ↗
08/28/2026B07993512-P3Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B07993512-S5Open ↗