| Owner | Filings | Most Recent |
|---|---|---|
| CONSULTANTS LLC MOD | 2 | 03/22/2026 |
| JP REALTY | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/14/2026 | $2.0M | — | — → — | — not available |
| 03/04/2024 | $660K | — | — → — | — not available |
| 05/20/2021 | $400K | — | Private party → SK CAPITAL NYC LLC | — not available |
| 08/28/2014 | $210K | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 13 | 05/26/2026 |
| WJY ELECTRIC INC. | 2 | 10/14/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J. CALIENDO R.A., P.C. | 18 | 03/21/2026 |
| IBUILD CONSULTING | 4 | 03/21/2026 |
| RASPE CONSULTING ENGINEERS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MOD CONSULTANTS LLC | General Contractor | 12 | 07/08/2026 |
| CASE PLUMBING LLC | Fire Protection | 1 | 07/08/2026 |
| VMC PLUMBING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 12 | 05/26/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | MOD CONSULTANTS LLC | 10/14/2025 |
| DOB NOW | Curb Cut | Signed-off | MOD CONSULTANTS LLC | 10/01/2025 |
| DOB NOW | Sprinklers | Signed-off | S & L PLUMBING INC | 09/05/2025 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 11/06/2024 |
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 05/31/2024 |
| DOB NOW | Support of Excavation | Signed-off | MOD CONSULTANTS LLC | 03/22/2024 |
| DOB NOW | Earth Work | Signed-off | MOD CONSULTANTS LLC | 03/22/2024 |
| DOB NOW | Structural | Signed-off | MOD CONSULTANTS LLC | 03/21/2024 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 03/21/2024 |
| DOB NOW | Construction Fence | Signed-off | MOD CONSULTANTS LLC | 03/05/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/26/2026 | Signed-off | MOD CONSULTANTS LLC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2024 | Complete | RONEY ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/06/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 03/26/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/16/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 10/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/25/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/08/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/03/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/27/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/07/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/16/2026 | Fenestration air leakage | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Protection of exposed foundation insulation | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Maintenance information | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Air barrier — testing | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Metering | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Lighting controls | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Interior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Fenestration areas | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Exterior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Exterior Insulation and Finish Systems (EIFS) | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Concrete - Cast-In-Place | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Masonry | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Excavations - Sheeting, Shoring, and Bracing | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Subgrade Inspections | Rajasekhar Sakhamuri | special |
| 06/16/2026 | Fire-Resistance Rated Construction | Rajasekhar Sakhamuri | progress |
| 06/16/2026 | Energy Code Compliance Inspections | Rajasekhar Sakhamuri | progress |
| 06/16/2026 | Insulation placement and R values | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Fenestration and door U-factor and product ratings | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Lighting in dwelling units | Rajasekhar Sakhamuri | energy_progress |
| 06/16/2026 | Permanent certificate | Rajasekhar Sakhamuri | energy_progress |
| 05/20/2026 | Excavations - Sheeting, Shoring, and Bracing | Rajasekhar Sakhamuri | special |
| 05/20/2026 | Exterior lighting power | Rajasekhar Sakhamuri | energy_progress |