| Owner | Filings | Most Recent |
|---|---|---|
| EAST 19TH ST REALTY CO IN | 6 | 03/22/2026 |
| E 19 ST REALTY CO INC | 2 | 03/22/2026 |
| EAST 19ST REALTY CO INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/09/2025 | $700K | — | EAST 19TH ST. REALTY CO., INC. → Private party | $312/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SOLANKI ENGINEERING, PC | 2 | 07/01/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KISHAN PLUMBING INC | General Contractor | 2 | 07/29/2026 |
| KISHAN PLUMBING INC | Plumbing | 1 | 07/31/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SOLANKI ENGINEERING, P.C. | 8451 | 2 | 07/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | KISHAN PLUMBING INC | 07/30/2026 |
| DOB NOW | General Construction | Permit Issued | KISHAN PLUMBING INC | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | KISHAN PLUMBING INC | 07/23/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/01/2026 | Permit Issued | KISHAN PLUMBING INC | Heating Systems | Heating Crown Boiler AWR105C 105,000 BTU · Boiler ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | KISHAN PLUMBING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | MARTINEZ ELECTRICAL CONT | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/12/2026 | Chimneys and vents | Ashray Solanki | special |
| 03/12/2026 | Fire-Resistant Penetrations and Joints | Ashray Solanki | special |
| 03/12/2026 | Heating Systems | Ashray Solanki | special |
| 03/12/2026 | Structural Stability – Alterations of existing buildings | Ashray Solanki | special |
| 03/12/2026 | Mechanical Systems | Ashray Solanki | special |
| 03/12/2026 | Final | Ashray Solanki | progress |
| 03/12/2026 | Energy Code Compliance Inspections | Ashray Solanki | progress |
| 03/12/2026 | Fire-Resistance Rated Construction | Ashray Solanki | progress |
| 03/12/2026 | HVAC-R and service water piping design and insulation | Ashray Solanki | energy_progress |
| 03/12/2026 | Air barrier - visual inspection | Ashray Solanki | energy_progress |
| 03/12/2026 | Insulation placement and R values | Ashray Solanki | energy_progress |
| 03/12/2026 | Fenestration air leakage | Ashray Solanki | energy_progress |
| 03/12/2026 | Interior lighting power | Ashray Solanki | energy_progress |
| 03/12/2026 | Fenestration and door U-factor and product ratings | Ashray Solanki | energy_progress |
| 03/12/2026 | Fenestration areas | Ashray Solanki | energy_progress |
| 03/12/2026 | Metering | Ashray Solanki | energy_progress |
| 03/12/2026 | HVAC-R and service water heating equipment | Ashray Solanki | energy_progress |
| 03/12/2026 | Maintenance information | Ashray Solanki | energy_progress |
| 03/12/2026 | Permanent certificate | Ashray Solanki | energy_progress |
| 03/12/2026 | HVAC-R and service water heating system controls | Ashray Solanki | energy_progress |
| 03/12/2026 | Shutoff dampers | Ashray Solanki | energy_progress |