| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/13/2025 | $1.2M | — | LOVE PROPERTIES LLC → Private party | $609/sf building |
| 04/04/2018 | $760K | — | JAPJEE HOLDINGS II LLC → 222-40 LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| SUNG HO SHIN ARCHITECT, PC | 10 | 08/04/2025 |
| PARKER AND WEST ENGINEERING, PLLC | 1 | 04/15/2025 |
| SOUTHERN CONSULTING ENGINEERING PC | 1 | 04/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| UNITED GENERAL CONTRA COR | General Contractor | 4 | 07/08/2026 |
| SINGH LANDSCAPING & LAWN | General Contractor | 3 | 03/21/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| M & M PIPING AND HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHONG ENGINEERING P.C. | 7411 | 10 | 08/04/2025 |
| PARKER AND WEST ENGINEERI | 5272 | 1 | 04/15/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 04/18/2025 |
| DOB NOW | Plumbing | Signed-off | M & M PIPING AND HEATING | 06/17/2024 |
| DOB NOW | Curb Cut | Signed-off | SINGH LANDSCAPING & LAWN | 05/23/2024 |
| DOB NOW | General Construction | Permit Issued | UNITED GENERAL CONTRA COR | 04/30/2024 |
| DOB NOW | Support of Excavation | Signed-off | UNITED GENERAL CONTRA COR | 04/29/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 09/24/2024 | Complete | METROPOLITAN ELEC OF NY I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2025 | Permit Issued | UNITED GENERAL CONTRA COR | Concrete, Masonry, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2025 | Permit Issued | UNITED GENERAL CONTRA COR | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/16/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/20/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/27/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/27/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/27/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/27/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/27/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/04/2025 | Excavations - Sheeting, Shoring, and Bracing | Tae Chong | special |
| 09/04/2025 | Metering | Tae Chong | energy_progress |
| 09/04/2025 | Interior lighting power | Tae Chong | energy_progress |
| 09/04/2025 | Permanent certificate | Tae Chong | energy_progress |
| 09/04/2025 | Insulation placement and R values | Tae Chong | energy_progress |
| 09/04/2025 | Fenestration areas | Tae Chong | energy_progress |
| 09/04/2025 | Structural Wood Frame | Tae Chong | progress |
| 09/04/2025 | Energy Code Compliance Inspections | Tae Chong | progress |
| 09/04/2025 | Fire-Resistance Rated Construction | Tae Chong | progress |
| 09/04/2025 | Footing and Foundation | Tae Chong | progress |
| 09/04/2025 | Final | Tae Chong | progress |
| 09/04/2025 | Concrete - Cast-In-Place | Tae Chong | special |
| 09/04/2025 | Subgrade Inspections | Tae Chong | special |
| 09/04/2025 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 09/04/2025 | Structural Steel - High Strength Bolting | Tae Chong | special |
| 09/04/2025 | Construction Utilizing CLT or SCL, Type IV | Tae Chong | special |
| 09/04/2025 | Protection of exposed foundation insulation | Tae Chong | energy_progress |
| 09/04/2025 | Fenestration air leakage | Tae Chong | energy_progress |
| 09/04/2025 | Air barrier — testing | Tae Chong | energy_progress |
| 09/04/2025 | Air barrier - visual inspection | Tae Chong | energy_progress |
| 09/04/2025 | Fenestration and door U-factor and product ratings | Tae Chong | energy_progress |
| 09/04/2025 | Structural Steel - Welding | Tae Chong | special |
| 09/04/2025 | Subsurface Investigations (Borings/Test Pits) | BRIAN FLYNN | special |
| 09/04/2025 | Masonry | Tae Chong | special |
| 08/01/2025 | Subgrade Inspections | Tae Chong | special |