Permit Issued — active, not yet Signed-off
RoofUnder Construction76p · 3 filings · 20 docs
PenthouseUnder Construction82p · 5 filings · 20 docs
Floor 1Under Construction65p · 1 filing · 20 docs
CellarUnder Construction76p · 5 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KAWS3707/08/2026
COLT 93 NORTH 9TH ST303/22/2026
F & S CONTRACTING GROUP I303/22/2026
CONTRACTING GROUP INC F&S203/22/2026
TO THE OWNER OF 93 NORTH203/22/2026
THOR 93 NORTH 9TH STREET LLC1803/21/2026
NORTH NINE STREET REALTY LLC903/21/2026
NORTH 9TH STREET REALTY1203/21/2026
93 NORTH 9TH REALTY303/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/13/2019$17.0M—COLT 93 NORTH 9TH STREET LLC → NEW FICTION LLC$1,506/sf building
01/09/2015$8.3M—— → —$740/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HOWARD I SHAPIRO ASSOCIATES203/21/2026
JM ZONING, LLC.2203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
F&S CONTRACTING GROUP INCGeneral Contractor3807/08/2026
TATRA RENOVATION INCGeneral Contractor308/08/2026
JOSEPH WEINSTEIN ELECTRICElectrical203/22/2026
SPEEDWAY PLUMBING CORPPlumbing207/08/2026
WNW & SONS PLUMBING & HTGFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CROSSCHECK INSPECTION SER5441909/25/2025
CHRISTIAN L. MARTOS ENGIN5965801/19/2024
Building Lifecycle
All (209)Filed (27)Permit Issued (24)Signed Off (10)Violation (19)Inspection (19)Objection (80)Special Inspection (30)
08/07/2026
Permit issued — General Construction
B00797659-I1-GC
06/08/2026
Signed off — Alteration
MH WORK AS PER PLANS RELATED TO ALT CO PROJECT B00797659.
B00752960-I1
03/24/2026
Signed off — Alteration
Mechanical equipment use for the renovation of 1-story building, as per plans filed herewith. Filed in conjunction with B00797659, B00770340, B00752949.
B00859912-I1
03/05/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
02/10/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/13/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/17/2025
Violation issued (ECB, closed)
Construction
10/02/2025
Special inspection requirement — Ventilation and air distribution system
EUGENE BIFULCO
10/02/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
10/02/2025
Special inspection requirement — Duct leakage testing, insulation and design
EUGENE BIFULCO
10/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
EUGENE BIFULCO
10/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
10/02/2025
Special inspection requirement — Final
EUGENE BIFULCO
10/02/2025
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
09/25/2025
Filed — Alteration
MH WORK AS PER PLANS RELATED TO ALT CO PROJECT B00797659.
B00752960-P2
09/22/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
09/22/2025
Special inspection requirement — Duct leakage testing, insulation and design
EUGENE BIFULCO
09/22/2025
Special inspection requirement — Ventilation and air distribution system
EUGENE BIFULCO
09/22/2025
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
09/22/2025
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
09/22/2025
Special inspection requirement — HVAC-R and service water heating equipment
EUGENE BIFULCO
09/22/2025
Special inspection requirement — Final
EUGENE BIFULCO
09/17/2025
Permit issued — General Construction
B00797659-I1-GC
09/11/2025
Signed off — Alteration
FILING HEREWITH FOR CURB CUT WORK ON THE EAST SIDE AS PER PLANS. NO CHANGE TO USE EGRESS OR OCCUPANCY ON THIS APPLICATION.
B08000845-I1
09/08/2025
Objection resolved — Resolved
08/29/2025
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
08/22/2025
Permit issued — Mechanical Systems
B00752960-I1-MS
08/15/2025
Signed off — Alteration
PL WORK AS PER PLANS RELATED TO ALT CO PROJECT B00797659.
B00752972-I1
08/13/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
08/05/2025
Objection raised — Other
07/23/2025
Filed — Alteration CO
FILING HEREWITH FOR RENOVATIONS CHANGE OF USE AND OCCUPANCY FROM "OFFICE AND VETERINARIAN CLINIC" UG6 TO "ART STUDIOS" UG9A, AND PENTHOUSE ADDITION TO COMMERCIAL BUILDING INCLUDING NEW PANTRY AREAS, TOILETS, ACCESSORY PARKING and LOADING BERTH.
B00797659-P5
07/21/2025
Special inspection requirement — Fenestration air leakage
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Energy Code Compliance Inspections
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Interior lighting power
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Sprayed fire-resistant materials
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Lighting controls
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Exterior lighting power
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Fire-Resistance Rated Construction
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Insulation placement and R values
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Fenestration areas
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
07/21/2025
Special inspection requirement — Air barrier - visual inspection
EUGENE BIFULCO
07/16/2025
Permit issued — Curb Cut
B08000845-I1-CC
07/02/2025
Signed off — Alteration
INSTALLATION OF CONSTRUCTION FENCE AS PER DRAWING.
B00865870-I1
06/13/2025
Permit issued — Construction Fence
B00865870-I1-FN
06/05/2025
Special inspection requirement — Sprayed fire-resistant materials
EUGENE BIFULCO
06/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
EUGENE BIFULCO
06/05/2025
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
EUGENE BIFULCO
05/21/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/02/2025
Signed off — Alteration
SP WORK AS PER PLANS RELATED TO ALT CO PROJECT B00797659.
B00752992-I1
03/14/2025
Signed off — Alteration
ST WORK AS PER PLANS RELATED TO ALT CO PROJECT B00797659.
B00752949-I1
03/10/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/05/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/05/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/06/2025
Objection resolved — Addressed
02/06/2025
Objection resolved — Addressed
12/13/2024
Objection resolved — Addressed
Latest 60 of 209 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedTATRA RENOVATION INC08/07/2026
DOB NOWGeneral ConstructionPermit IssuedTATRA RENOVATION INC09/17/2025
DOB NOWMechanical SystemsSigned-offTATRA RENOVATION INC08/22/2025
DOB NOWCurb CutSigned-offF&S CONTRACTING GROUP INC07/16/2025
DOB NOWConstruction FenceSigned-offF&S CONTRACTING GROUP INC06/13/2025
DOB NOWGeneral ConstructionPermit IssuedF&S CONTRACTING GROUP INC12/12/2024
DOB NOWPlumbingSigned-offSPEEDWAY PLUMBING CORP11/27/2024
DOB NOWSprinklersSigned-offWNW & SONS PLUMBING & HTG08/30/2024
DOB NOWConstruction FenceSigned-offF&S CONTRACTING GROUP INC06/12/2024
DOB NOWFoundationSigned-offF&S CONTRACTING GROUP INC04/29/2024
DOB NOWMechanical SystemsSigned-offF&S CONTRACTING GROUP INC04/26/2024
DOB NOWStructuralSigned-offF&S CONTRACTING GROUP INC04/26/2024
DOB NOWConstruction FenceSigned-offF&S CONTRACTING GROUP INC04/26/2024
DOB NOWPlumbingSigned-offSPEEDWAY PLUMBING CORP12/14/2023
DOB NOWGeneral ConstructionPermit IssuedF&S CONTRACTING GROUP INC12/12/2023
DOB NOWGeneral ConstructionPermit IssuedF&S CONTRACTING GROUP INC06/17/2023
DOB NOWProtection and Mechanical MethodsSigned-offF&S CONTRACTING GROUP INC06/01/2023
DOB NOWConstruction FenceSigned-offF&S CONTRACTING GROUP INC05/15/2023
DOB NOWGeneral ConstructionSigned-offF&S CONTRACTING GROUP INC05/11/2023
DOB NOWStructuralSigned-offF&S CONTRACTING GROUP INC05/08/2023
DOB NOWCurb CutPermit IssuedF&S CONTRACTING GROUP INC04/27/2023
DOB NOWFoundationSigned-offF&S CONTRACTING GROUP INC04/27/2023
DOB NOWSupport of ExcavationSigned-offF&S CONTRACTING GROUP INC04/27/2023
DOB NOWMechanical SystemsSigned-offF&S CONTRACTING GROUP INC04/27/2023
BISPLISSUEDJEFFREY VULPIS PLMBNG LLC09/20/2019
BISSPISSUEDVULPIS & VULPIS PLBG INC09/20/2019
BISOTISSUEDSPECTRUM.WIDE PRODUCTIONS02/15/2018
BISOTISSUEDMELITO CONSTRUCTION CORP01/09/2017
BISOTISSUEDMELITO CONSTRUCTION CORP01/14/2016
BISPLISSUEDJEFFREY VULPIS PLMBNG LLC08/21/2015
BISSPISSUEDINTERCITY PLBG & HTG CORP06/17/2015
BISOTISSUEDVANQUISH CONTRACTING CORP04/27/2015
BISOTISSUEDVANQUISH CONTRACTING CORP01/16/2015
BISPLISSUEDPARKSET PLMBG CO.,INC03/18/2008
BIS—ISSUEDD. EDGAR INC03/06/2008
BIS—ISSUEDN/A01/18/2008
BISSPISSUEDPARKSET PLBG CO INC09/17/2007
BISPLISSUEDPARKSET PLMBG CO.,INC06/14/2007
BISMHISSUEDD. EDGAR INC06/11/2007
BISSPISSUEDPARKSET PLBG CO INC04/03/2006
+ 13 more permits on file
1 project · most recent 09/25/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/25/2025Signed-offTATRA RENOVATION INCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric PURY-EP432TSNU-A 432,000 BTU · Vrf Outdoor ×1
PURY-EP216TNU-A1 216,000 BTU · Vrf Outdoor ×2
PURY-EP216TNU-AI 216,000 BTU · Vrf Outdoor ×2
Ventilation
Greenback N/A 100,000 BTU · Makeup Air ×2
2 projects · most recent 10/07/2025
General Wiring
FiledStatusContractorScope
10/07/2025CompleteJOSEPH WEINSTEIN ELECTRICGeneral Wiring
05/09/2023CancelledELECTL CONTG SOLUTIONS COGeneral Wiring
▾Field Inspections (DOB CAP) — 19
DateTypeResultReport
03/05/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/10/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/13/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/29/2025Fail-Final Curb Cut Non-Directive 14FailView ↗
08/13/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
05/21/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/10/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/05/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/05/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/03/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/03/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/16/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/24/2024Fail-Final PL - UndergroundFailView ↗
04/16/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/13/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/25/2024Fail-Final PL - UndergroundFailView ↗
12/19/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/19/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 108
DateRequirementInspectorRole
10/02/2025Mechanical SystemsEUGENE BIFULCOspecial
10/02/2025HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
10/02/2025HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
10/02/2025HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
10/02/2025Duct leakage testing, insulation and designEUGENE BIFULCOenergy_progress
10/02/2025Ventilation and air distribution systemEUGENE BIFULCOenergy_progress
10/02/2025FinalEUGENE BIFULCOprogress
09/22/2025Mechanical SystemsEUGENE BIFULCOspecial
09/22/2025FinalEUGENE BIFULCOprogress
09/22/2025HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
09/22/2025HVAC-R and service water heating equipmentEUGENE BIFULCOenergy_progress
09/22/2025Ventilation and air distribution systemEUGENE BIFULCOenergy_progress
09/22/2025Duct leakage testing, insulation and designEUGENE BIFULCOenergy_progress
09/22/2025HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
07/21/2025Fenestration air leakageEUGENE BIFULCOenergy_progress
07/21/2025Fire-Resistance Rated ConstructionEUGENE BIFULCOprogress
07/21/2025Air barrier - visual inspectionEUGENE BIFULCOenergy_progress
07/21/2025Fenestration and door U-factor and product ratingsEUGENE BIFULCOenergy_progress
07/21/2025Insulation placement and R valuesEUGENE BIFULCOenergy_progress
07/21/2025Fenestration areasEUGENE BIFULCOenergy_progress
07/21/2025Exterior lighting powerEUGENE BIFULCOenergy_progress
07/21/2025Lighting controlsEUGENE BIFULCOenergy_progress
07/21/2025Fire-Resistant Penetrations and JointsEUGENE BIFULCOspecial
07/21/2025Mastic and Intumescent Fire-resistant CoatingsEUGENE BIFULCOspecial
07/21/2025Sprayed fire-resistant materialsEUGENE BIFULCOspecial
Latest 25 of 108.
▾Documents — 317 on file (BIS + DOB NOW)
▸Plans & Drawings27
▸DOB NOWPlans/Sketch27
08/29/2026B00752992-P1Request digital key ↗
08/29/2026B00752992-I1Request digital key ↗
08/29/2026B00752972-I1Request digital key ↗
Showing 3 of 27 on file for this type
▸Applications & Permits31
▸BISWORK PERMIT APPLICATION14
11/12/2019321972111Open ↗
09/20/2019321972111Open ↗
09/20/2019321972111Open ↗
Showing 3 of 14 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION13
02/18/2025340870427Open ↗
02/12/2025340870427Open ↗
01/24/2025340870427Open ↗
Showing 3 of 13 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
02/19/2025340870427Open ↗
▸BISBPP-DOT: SIDEWALK/CURB/ROAD WORK PERMITS1
11/28/2025340870427Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
02/20/2008310076912Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
12/02/2019321972111Open ↗
▸Zoning, Tax Lot & Property Records21
▸DOB NOWRestrictive Declaration/Easement 16
08/13/2026B00797659-I1Open ↗
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram6
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P2Open ↗
08/13/2026B00797659-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWRestrictive Declaration/Easement 26
08/13/2026B00797659-I1Open ↗
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P2Open ↗
Showing 3 of 6 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
01/30/2008310084618Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
01/30/2008310084618Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00797659-I1Open ↗
▸Seals & Professional Certifications104
▸DOB NOWDPL-1: Design Professional Seal & Signature27
08/29/2026B00752992-P1Open ↗
08/29/2026B00752992-I1Open ↗
08/29/2026B00752972-P1Open ↗
Showing 3 of 27 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature26
09/30/2026B00752949-I1Open ↗
09/30/2026B00752949-I1Open ↗
09/30/2026B00752949-I1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
09/30/2026B00752949-I1Open ↗
09/22/2026B00797659-P2Open ↗
09/22/2026B00797659-P2Open ↗
Showing 3 of 18 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
01/07/2020321972111Open ↗
12/05/2019321972111Open ↗
11/23/2019321972111Open ↗
Showing 3 of 17 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
06/28/2019321972111Open ↗
02/14/2018321779688Open ↗
11/20/2015321257037Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
06/28/2019321972111Open ↗
02/14/2018321779688Open ↗
11/20/2015321257037Open ↗
Showing 3 of 4 on file for this type
▸BISPC FULL REPORT2
01/30/2008310084618Open ↗
01/03/2008310076912Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
01/30/2008310084618Open ↗
01/03/2008310076912Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
01/24/2025340870427Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
01/24/2025340870427Open ↗
▸Trade Schedules & Equipment14
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P5Open ↗
08/13/2026B00797659-I1Open ↗
Showing 3 of 6 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
06/28/2019321972111Open ↗
06/28/2019321972111Open ↗
08/27/2015321062906Open ↗
Showing 3 of 5 on file for this type
▸BISSELF-CERT PLUMBING NOTICE1
08/13/2008310084618Open ↗
▸BISWATER METER PERMIT : DEP-METER1
08/18/2008310084618Open ↗
▸BISSEWER/HOUSE CON SIGNOFF: DEP HC 0211
06/19/2008310084618Open ↗
▸Safety & Tenant Protection11
▸DOB NOWStreet Tree Checklist6
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-I1Open ↗
08/13/2026B00797659-P5Open ↗
Showing 3 of 6 on file for this type
▸BISBPP: STREET TREES SITE PLAN1
02/11/2025340870427Open ↗
▸BISSTREET TREE SIGNOFF1
10/30/2025340870427Open ↗
▸DOB NOWStreet Trees Site Plan1
08/14/2026B00797659-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00797659-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00797659-I1Open ↗
▸Environmental & Asbestos19
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/29/2026B00752972-I1Open ↗
08/21/2026B00797659-P5Open ↗
08/21/2026B00797659-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/29/2026B00752992-I1Open ↗
08/28/2026B00770340-I1Open ↗
08/15/2026B00752949-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
06/28/2019321972111Open ↗
11/20/2015321257037Open ↗
01/23/2015321062906Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
01/30/2008310084618Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
01/03/2008310076912Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
01/07/2020321972111Open ↗
01/07/2020321972111Open ↗
06/28/2019321972111Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
01/07/2020321972111Open ↗
12/28/2015321062906Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/15/2026B00752960-I1Open ↗
08/13/2026B00797659-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/15/2026B00752960-I1Open ↗
▸Approvals, Objections & Sign-offs17
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
01/07/2020321972111Open ↗
10/07/2019321779688Open ↗
01/12/2018321257037Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
11/20/2015321257037Open ↗
01/23/2015321062906Open ↗
01/29/2008310084618Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
02/11/2025340870427Open ↗
01/23/2015321062906Open ↗
01/23/2015321062906Open ↗
▸BISSUPERSEDING LETTER1
11/12/2019321972111Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
11/28/2025340870427Open ↗
▸BISTAP LETTER - DOM SVC : DEP-DOM1
08/18/2008310084618Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT9
01/07/2020321972111Open ↗
06/28/2019321972111Open ↗
12/28/2015321062906Open ↗
Showing 3 of 9 on file for this type
▸BISBPP-11 - Affidavit as to Roadway Pavement And/Or Sidewalk and Curb Construction1
11/28/2025340870427Open ↗
▸Filing & Intake Forms14
▸BISEFILING COVER SHEET8
07/01/2019321972111Open ↗
07/01/2019321972111Open ↗
07/01/2019321972111Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM3
01/07/2020321972111Open ↗
10/07/2019321779688Open ↗
01/12/2018321257037Open ↗
▸BISADDITIONAL INFORMATION2
12/05/2019321972111Open ↗
05/22/2017321257037Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
01/24/2025340870427Open ↗
▸Other Documents39
▸DOB NOWPlot Diagram11
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-I1Open ↗
08/13/2026B00770340-P1Open ↗
Showing 3 of 11 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION7
11/28/2025340870427Open ↗
11/28/2025340870427Open ↗
11/28/2025340870427Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P4Open ↗
08/13/2026B00797659-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProperty Ownership Certification6
08/21/2026B00797659-P3Open ↗
08/21/2026B00797659-P2Open ↗
08/21/2026B00797659-P5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSite Survey: Initial6
08/13/2026B00797659-I1Open ↗
08/13/2026B00797659-P1Open ↗
08/13/2026B00797659-P2Open ↗
Showing 3 of 6 on file for this type
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
01/24/2025340870427Open ↗
▸BISBPP: SIDEWALK & ROADWAY THICKNESS CORES1
11/28/2025340870427Open ↗