| Owner | Filings | Most Recent |
|---|---|---|
| KAWS | 37 | 07/08/2026 |
| COLT 93 NORTH 9TH ST | 3 | 03/22/2026 |
| F & S CONTRACTING GROUP I | 3 | 03/22/2026 |
| CONTRACTING GROUP INC F&S | 2 | 03/22/2026 |
| TO THE OWNER OF 93 NORTH | 2 | 03/22/2026 |
| THOR 93 NORTH 9TH STREET LLC | 18 | 03/21/2026 |
| NORTH NINE STREET REALTY LLC | 9 | 03/21/2026 |
| NORTH 9TH STREET REALTY | 12 | 03/21/2026 |
| 93 NORTH 9TH REALTY | 3 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/13/2019 | $17.0M | — | COLT 93 NORTH 9TH STREET LLC → NEW FICTION LLC | $1,506/sf building |
| 01/09/2015 | $8.3M | — | — → — | $740/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MQ CONSULTING | 7 | 09/25/2025 |
| MCALPINE ASSOCIATES ARCHITECTS PC | 10 | 07/23/2025 |
| MARTOS ENGINEERING | 8 | 01/19/2024 |
| HOWARD I. SHAPIRO & ASSOCIATES, P.C | 1 | 05/08/2023 |
| THE H ARCHITECTS LLC | 1 | 04/28/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| HOWARD I SHAPIRO ASSOCIATES | 2 | 03/21/2026 |
| JM ZONING, LLC. | 22 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| F&S CONTRACTING GROUP INC | General Contractor | 38 | 07/08/2026 |
| TATRA RENOVATION INC | General Contractor | 3 | 08/08/2026 |
| JOSEPH WEINSTEIN ELECTRIC | Electrical | 2 | 03/22/2026 |
| SPEEDWAY PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| WNW & SONS PLUMBING & HTG | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CROSSCHECK INSPECTION SER | 544 | 19 | 09/25/2025 |
| CHRISTIAN L. MARTOS ENGIN | 5965 | 8 | 01/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | TATRA RENOVATION INC | 08/07/2026 |
| DOB NOW | General Construction | Permit Issued | TATRA RENOVATION INC | 09/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | TATRA RENOVATION INC | 08/22/2025 |
| DOB NOW | Curb Cut | Signed-off | F&S CONTRACTING GROUP INC | 07/16/2025 |
| DOB NOW | Construction Fence | Signed-off | F&S CONTRACTING GROUP INC | 06/13/2025 |
| DOB NOW | General Construction | Permit Issued | F&S CONTRACTING GROUP INC | 12/12/2024 |
| DOB NOW | Plumbing | Signed-off | SPEEDWAY PLUMBING CORP | 11/27/2024 |
| DOB NOW | Sprinklers | Signed-off | WNW & SONS PLUMBING & HTG | 08/30/2024 |
| DOB NOW | Construction Fence | Signed-off | F&S CONTRACTING GROUP INC | 06/12/2024 |
| DOB NOW | Foundation | Signed-off | F&S CONTRACTING GROUP INC | 04/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | F&S CONTRACTING GROUP INC | 04/26/2024 |
| DOB NOW | Structural | Signed-off | F&S CONTRACTING GROUP INC | 04/26/2024 |
| DOB NOW | Construction Fence | Signed-off | F&S CONTRACTING GROUP INC | 04/26/2024 |
| DOB NOW | Plumbing | Signed-off | SPEEDWAY PLUMBING CORP | 12/14/2023 |
| DOB NOW | General Construction | Permit Issued | F&S CONTRACTING GROUP INC | 12/12/2023 |
| DOB NOW | General Construction | Permit Issued | F&S CONTRACTING GROUP INC | 06/17/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | F&S CONTRACTING GROUP INC | 06/01/2023 |
| DOB NOW | Construction Fence | Signed-off | F&S CONTRACTING GROUP INC | 05/15/2023 |
| DOB NOW | General Construction | Signed-off | F&S CONTRACTING GROUP INC | 05/11/2023 |
| DOB NOW | Structural | Signed-off | F&S CONTRACTING GROUP INC | 05/08/2023 |
| DOB NOW | Curb Cut | Permit Issued | F&S CONTRACTING GROUP INC | 04/27/2023 |
| DOB NOW | Foundation | Signed-off | F&S CONTRACTING GROUP INC | 04/27/2023 |
| DOB NOW | Support of Excavation | Signed-off | F&S CONTRACTING GROUP INC | 04/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | F&S CONTRACTING GROUP INC | 04/27/2023 |
| BIS | PL | ISSUED | JEFFREY VULPIS PLMBNG LLC | 09/20/2019 |
| BIS | SP | ISSUED | VULPIS & VULPIS PLBG INC | 09/20/2019 |
| BIS | OT | ISSUED | SPECTRUM.WIDE PRODUCTIONS | 02/15/2018 |
| BIS | OT | ISSUED | MELITO CONSTRUCTION CORP | 01/09/2017 |
| BIS | OT | ISSUED | MELITO CONSTRUCTION CORP | 01/14/2016 |
| BIS | PL | ISSUED | JEFFREY VULPIS PLMBNG LLC | 08/21/2015 |
| BIS | SP | ISSUED | INTERCITY PLBG & HTG CORP | 06/17/2015 |
| BIS | OT | ISSUED | VANQUISH CONTRACTING CORP | 04/27/2015 |
| BIS | OT | ISSUED | VANQUISH CONTRACTING CORP | 01/16/2015 |
| BIS | PL | ISSUED | PARKSET PLMBG CO.,INC | 03/18/2008 |
| BIS | — | ISSUED | D. EDGAR INC | 03/06/2008 |
| BIS | — | ISSUED | N/A | 01/18/2008 |
| BIS | SP | ISSUED | PARKSET PLBG CO INC | 09/17/2007 |
| BIS | PL | ISSUED | PARKSET PLMBG CO.,INC | 06/14/2007 |
| BIS | MH | ISSUED | D. EDGAR INC | 06/11/2007 |
| BIS | SP | ISSUED | PARKSET PLBG CO INC | 04/03/2006 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/25/2025 | Signed-off | TATRA RENOVATION INC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PURY-EP432TSNU-A 432,000 BTU · Vrf Outdoor ×1 PURY-EP216TNU-A1 216,000 BTU · Vrf Outdoor ×2 PURY-EP216TNU-AI 216,000 BTU · Vrf Outdoor ×2 Ventilation Greenback N/A 100,000 BTU · Makeup Air ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2025 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 05/09/2023 | Cancelled | ELECTL CONTG SOLUTIONS CO | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/05/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/10/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/13/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/29/2025 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 08/13/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/10/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/05/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/03/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/03/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/16/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/24/2024 | Fail-Final PL - Underground | Fail | View ↗ |
| 04/16/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/13/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/25/2024 | Fail-Final PL - Underground | Fail | View ↗ |
| 12/19/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/19/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/02/2025 | Mechanical Systems | EUGENE BIFULCO | special |
| 10/02/2025 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 10/02/2025 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 10/02/2025 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 10/02/2025 | Duct leakage testing, insulation and design | EUGENE BIFULCO | energy_progress |
| 10/02/2025 | Ventilation and air distribution system | EUGENE BIFULCO | energy_progress |
| 10/02/2025 | Final | EUGENE BIFULCO | progress |
| 09/22/2025 | Mechanical Systems | EUGENE BIFULCO | special |
| 09/22/2025 | Final | EUGENE BIFULCO | progress |
| 09/22/2025 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 09/22/2025 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 09/22/2025 | Ventilation and air distribution system | EUGENE BIFULCO | energy_progress |
| 09/22/2025 | Duct leakage testing, insulation and design | EUGENE BIFULCO | energy_progress |
| 09/22/2025 | HVAC-R and service water piping design and insulation | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Fenestration air leakage | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Fire-Resistance Rated Construction | EUGENE BIFULCO | progress |
| 07/21/2025 | Air barrier - visual inspection | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Fenestration and door U-factor and product ratings | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Insulation placement and R values | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Fenestration areas | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Exterior lighting power | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Lighting controls | EUGENE BIFULCO | energy_progress |
| 07/21/2025 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 07/21/2025 | Mastic and Intumescent Fire-resistant Coatings | EUGENE BIFULCO | special |
| 07/21/2025 | Sprayed fire-resistant materials | EUGENE BIFULCO | special |