| Owner | Filings | Most Recent |
|---|---|---|
| J BUILDERS | 26 | 09/01/2026 |
| BG CONSTRUCTION NY | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/25/2023 | $975K | — | Private party → Private party | $285/sf building |
| 10/10/2016 | $150K | — | — → — | $44/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AL FFRED ARCHITECTURE PLLC | 5 | 08/25/2026 |
| MARK WEINBERGER ARCHITECT PLLC | 6 | 02/25/2026 |
| NANIK MASSAND | 1 | 06/07/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EMPIRE EXPEDITING | 22 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BG CONSTRUCTION NY INC | General Contractor | 14 | 07/08/2026 |
| M&D FIRE SPRINKLER INC | Fire Protection | 2 | 07/08/2026 |
| AL PLUMBING & CONT. INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 7 | 08/25/2026 |
| AURORA BUILDING CONSULTAN | 9710 | 5 | 02/25/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Support of Excavation | Signed-off | BG CONSTRUCTION NY INC | 03/19/2026 |
| DOB NOW | Plumbing | Permit Issued | AL PLUMBING & CONT. INC | 09/19/2025 |
| DOB NOW | Construction Fence | Signed-off | BG CONSTRUCTION NY INC | 09/10/2025 |
| DOB NOW | General Construction | Permit Issued | BG CONSTRUCTION NY INC | 09/09/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | BG CONSTRUCTION NY INC | 07/31/2025 |
| DOB NOW | Sprinklers | Permit Issued | M&D FIRE SPRINKLER INC | 07/30/2025 |
| DOB NOW | Sprinklers | Permit Issued | M&D FIRE SPRINKLER INC | 07/15/2025 |
| DOB NOW | Foundation | Permit Issued | BG CONSTRUCTION NY INC | 04/30/2025 |
| DOB NOW | Support of Excavation | Signed-off | BG CONSTRUCTION NY INC | 04/10/2025 |
| DOB NOW | Structural | Signed-off | BG CONSTRUCTION NY INC | 02/26/2025 |
| DOB NOW | General Construction | Permit Issued | BG CONSTRUCTION NY INC | 10/02/2024 |
| DOB NOW | Construction Fence | Signed-off | BG CONSTRUCTION NY INC | 08/16/2024 |
| DOB NOW | General Construction | Permit Issued | BG CONSTRUCTION NY INC | 08/09/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/25/2026 | Signed-off | BG CONSTRUCTION NY INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PEFY-P54NMAU-E3 60,000 BTU · Vrf Indoor ×4 PUHY-EP72TNU-A1 80,000 BTU · Vrf Outdoor ×3 MSZ-GL18NA 21,600 BTU · Fan Coil Indoor ×4 MSZ-GL09NA 10,900 BTU · Fan Coil Indoor ×2 MUZ-GX12NL 14,400 BTU · Ahu ×1 MXZ-SM42NAMHZ2-U1 48,000 BTU · Vrf Outdoor ×1 MXZ-SM60NAM2-U1 66,000 BTU · Ahu ×5 PUZ-A24NHA7 54,000 BTU · Fan Coil Indoor ×4 MUZ-GL09NA 9,000 BTU · Fan Coil Indoor ×1 MXZ-SM36NAM2-U1 36,000 BTU · Fan Coil Indoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2026 | Permit Issued | M&D FIRE SPRINKLER INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2025 | Permit Issued | KINGS ELECTRIC CO., INC. | General Wiring |
| 09/04/2025 | Permit Issued | ENERCHARGE ELECTRIC CONT | General Wiring |
| 04/09/2025 | Permit Issued | KINGS ELECTRIC CO., INC. | 6 meters, 6 new_meters |
| 02/25/2025 | Complete | KINGS ELECTRIC CO., INC. | — |
| 11/25/2024 | Complete | KINGS ELECTRIC CO., INC. | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/13/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/17/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/13/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/06/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Maintenance information | LESLIE GOOD | energy_progress |
| 08/18/2026 | HVAC-R and service water heating equipment | LESLIE GOOD | energy_progress |
| 08/18/2026 | HVAC-R and service water heating system controls | LESLIE GOOD | energy_progress |
| 08/18/2026 | Shutoff dampers | LESLIE GOOD | energy_progress |
| 08/18/2026 | HVAC-R and service water piping design and insulation | LESLIE GOOD | energy_progress |
| 08/18/2026 | Mechanical Systems | Shahrish Shuvo | special |
| 08/18/2026 | Smoke Control Systems Testing | Shahrish Shuvo | special |
| 08/18/2026 | Structural Stability – Alterations of existing buildings | Shahrish Shuvo | special |
| 08/18/2026 | Energy Code Compliance Inspections | LESLIE GOOD | progress |
| 08/18/2026 | Final | NOEL WONG | progress |
| 08/18/2026 | Fire-Resistance Rated Construction | LESLIE GOOD | progress |
| 08/18/2026 | Duct leakage testing, insulation and design | LESLIE GOOD | energy_progress |
| 01/27/2026 | Energy Code Compliance Inspections | NOEL WONG | progress |
| 01/27/2026 | Fire-Resistant Penetrations and Joints | NOEL WONG | special |
| 02/25/2025 | Excavations - Sheeting, Shoring, and Bracing | Shahrish Shuvo | special |
| 01/15/2025 | Post-installed Anchors | Shahrish Shuvo | special |
| 01/10/2025 | Subgrade Inspections | Shahrish Shuvo | special |
| 01/10/2025 | Subsurface Investigations (Borings/Test Pits) | SOORJBALLY HARILALL | special |
| 01/10/2025 | Concrete - Cast-In-Place | Shahrish Shuvo | special |
| 01/02/2025 | Final | NOEL WONG | progress |
| 01/02/2025 | Footing and Foundation | NOEL WONG | progress |
| 08/16/2024 | Energy Code Compliance Inspections | LESLIE GOOD | progress |
| 08/16/2024 | Fire-Resistant Penetrations and Joints | NOEL WONG | special |
| 08/16/2024 | Structural Stability – Alterations of existing buildings | NOEL WONG | special |
| 08/16/2024 | Fire-Resistance Rated Construction | LESLIE GOOD | progress |