| Owner | Filings | Most Recent |
|---|---|---|
| SE 936 OWNER | 16 | 07/08/2026 |
| 409 EDGECOMBE AVENUE HOUSING DEVELO | 4 | 07/08/2026 |
| 155 PERRY ST CONDOMINIUM | 4 | 07/08/2026 |
| 936 BROADWAY CONDO | 56 | 03/22/2026 |
| 936 BROADWAY ASSOC. | 2 | 03/22/2026 |
| 936 BWY CONDO | 12 | 03/22/2026 |
| 932 BROADWAY RLTY CO. | 4 | 03/22/2026 |
| TORANTO ASSOCIATES | 1 | 03/22/2026 |
| WELLS & GAZ SRTALIC ASSOC | 1 | 03/22/2026 |
| 936 BROADWAY PARTNERS | 2 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROBERT G. LYON & ASSOC | 2 | 05/28/2026 |
| KLH PROFESSIONAL ENGINEERS, PSC P.C | 5 | 05/27/2026 |
| GRM CONSULTANTS LLC | 5 | 10/12/2025 |
| STUDIOGREENER ARCHITECTURE PLLC | 3 | 01/06/2025 |
| THE ROCK BROOK CONSULTING GROUP, PA | 3 | 11/17/2023 |
| THE DEROSA GROUP, PC ARCHITECTS | 2 | 03/23/2023 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 2 | 11/01/2022 |
| SERMAN ENGINEERING | 1 | 01/26/2022 |
| ADG ARCHITECTURE AND DESIGN PC | 2 | 05/06/2021 |
| RICHARD WAINER ARCHITECT, PLLC | 1 | 09/08/2020 |
| UNISPACE | 1 | 06/14/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| LOUIS STRIAR | 10 | 03/21/2026 |
| ARCHETYPE CONSULTANTS | 8 | 03/21/2026 |
| JM ZONING, LLC. | 10 | 03/21/2026 |
| ADG ARCHITECTURE DESIGN | 4 | 03/21/2026 |
| D R BROWN | 2 | 03/21/2026 |
| EMPIRE CITY CONSULTANTS, INC. | 8 | 03/21/2026 |
| HLZAE | 4 | 03/21/2026 |
| M W EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROSELAND CONSTRUCTION COR | General Contractor | 6 | 07/08/2026 |
| STAN LYUBOMUDROV | Electrical | 4 | 03/21/2026 |
| SIGNSTAR NYC | Scaffold | 3 | 07/08/2026 |
| DONALD R BORG CONSTRUCT | General Contractor | 2 | 07/08/2026 |
| SHANNON CONTRACTING LLC | General Contractor | 2 | 07/08/2026 |
| ETNA CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| BEDROCK MECHANICAL INC | Fire Protection | 1 | 06/27/2026 |
| LEBO ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| A PLUS PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| BEDROCK PLBG. & HTG., INC | Plumbing | 1 | 07/08/2026 |
| NATIONAL MAINTENANCE | Scaffold | 1 | 07/08/2026 |
| EQUATORIAL RENOVATIONS CO | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HANSEN ENGINEERING PC | 8174 | 6 | 05/28/2026 |
| STUDIOGREENER ARCHITECTUR | 7455 | 3 | 01/06/2025 |
| SPECIAL TESTING & CONSULT | 1688 | 2 | 03/24/2023 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 2 | 11/01/2022 |
| SERMAN ENGINEERING | 4685 | 1 | 01/26/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 10/22/2025 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 09/29/2025 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 09/29/2025 |
| DOB NOW | Plumbing | Signed-off | BEDROCK PLBG. & HTG., INC | 07/29/2025 |
| DOB NOW | Sprinklers | Signed-off | BEDROCK MECHANICAL INC | 07/29/2025 |
| DOB NOW | General Construction | Signed-off | DONALD R BORG CONSTRUCT | 07/07/2025 |
| DOB NOW | Mechanical Systems | Signed-off | DONALD R BORG CONSTRUCT | 07/07/2025 |
| DOB NOW | General Construction | Signed-off | ROSELAND CONSTRUCTION COR | 08/13/2024 |
| DOB NOW | Structural | Signed-off | ROSELAND CONSTRUCTION COR | 08/12/2024 |
| DOB NOW | General Construction | Signed-off | ROSELAND CONSTRUCTION COR | 08/21/2023 |
| DOB NOW | Structural | Signed-off | ROSELAND CONSTRUCTION COR | 08/21/2023 |
| DOB NOW | General Construction | Permit Issued | SHANNON CONTRACTING LLC | 04/24/2023 |
| DOB NOW | Plumbing | Signed-off | A PLUS PLUMBING CORP | 04/24/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | SHANNON CONTRACTING LLC | 04/24/2023 |
| DOB NOW | General Construction | Signed-off | ETNA CONTRACTING INC | 02/26/2022 |
| DOB NOW | General Construction | Signed-off | EQUATORIAL RENOVATIONS | 03/08/2021 |
| DOB NOW | Sign | Signed-off | NATIONAL MAINTENANCE, INC | 09/09/2020 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 07/23/2019 |
| BIS | OT | ISSUED | BAYSIDE CONTRACTING INC | 05/20/2019 |
| BIS | OT | ISSUED | BENCHMARK BUILDERS LLC | 09/27/2018 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 09/14/2018 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 09/04/2018 |
| BIS | SP | ISSUED | NEW ERA MECH SERVICE INC | 07/03/2018 |
| BIS | PL | ISSUED | TRUE NORTH MECHANICAL LLC | 05/25/2018 |
| BIS | OT | ISSUED | BAYSIDE CONTRACTING INC | 05/18/2018 |
| BIS | MH | ISSUED | QUALITY INSTALLATIONS NY | 04/12/2018 |
| BIS | OT | ISSUED | QUALITY INSTALLATIONS NY | 04/12/2018 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 09/14/2017 |
| BIS | SP | ISSUED | DEVO FIRE PROTECTION INC | 09/05/2017 |
| BIS | SD | ISSUED | DEVO FIRE PROTECTION INC | 08/31/2017 |
| BIS | EQ | ISSUED | DYNAMIC INSTALLATION CORP. | 08/24/2017 |
| BIS | OT | ISSUED | BAYSIDE CONTRACTING INC | 08/23/2017 |
| BIS | SP | ISSUED | DEVO FIRE PROTECTION INC | 04/07/2017 |
| BIS | PL | ISSUED | DEMAR PLUMBING CORP | 08/26/2016 |
| BIS | BL | ISSUED | DEMAR PLUMBING CORP | 08/01/2016 |
| BIS | — | ISSUED | COMJEM ASSOCIATES LTD | 06/10/2016 |
| BIS | SP | ISSUED | DEVO FIRE PROTECTION INC | 04/11/2016 |
| BIS | MH | ISSUED | BENCHMARK BUILDERS LLC | 08/14/2014 |
| BIS | OT | ISSUED | BENCHMARK BUILDERS LLC | 08/14/2014 |
| BIS | OT | ISSUED | BENCHMARK BUILDERS LLC | 08/14/2014 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/27/2026 | Signed-off | DONALD R BORG CONSTRUCT | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | Signed-off | BEDROCK MECHANICAL INC | 142 heads |
| — | — | — | 43 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | — | — | — |
| 11/17/2023 | Signed-off | A PLUS PLUMBING CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/19/2025 | Complete | PROFF ELECTRICAL LLC | — |
| 11/19/2025 | Complete | PROFF ELECTRICAL LLC | — |
| 11/19/2025 | Complete | PROFF ELECTRICAL LLC | — |
| 11/04/2025 | Complete | LEBO ELECTRIC LLC | General Wiring |
| 12/06/2024 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 04/29/2023 | Complete | S.E. ELECTL CONTNG CORP | General Wiring |
| 04/20/2021 | Complete | PATRIOT ELECTRIC CORP | — |
| 03/22/2021 | Complete | VILANOVA ELECL CONTS LLC | General Wiring |
| 02/15/2019 | Complete | FSM ELECTRICAL CORPORATIO | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | Signed-off | BEDROCK MECHANICAL INC | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/22/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/23/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/18/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/18/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/12/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 08/23/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/23/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/29/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 05/29/2026 | Final | Ryan Hansen | progress |
| 05/28/2026 | Shutoff dampers | Ryan Hansen | energy_progress |
| 05/28/2026 | Final | Ryan Hansen | progress |
| 05/28/2026 | Energy Code Compliance Inspections | Ryan Hansen | progress |
| 05/28/2026 | Lighting controls | Ryan Hansen | energy_progress |
| 05/28/2026 | HVAC-R and service water heating system controls | Ryan Hansen | energy_progress |
| 05/28/2026 | HVAC-R and service water piping design and insulation | Ryan Hansen | energy_progress |
| 05/28/2026 | HVAC-R and service water heating equipment | Ryan Hansen | energy_progress |
| 05/28/2026 | Interior lighting power | Ryan Hansen | energy_progress |
| 05/28/2026 | Maintenance information | Ryan Hansen | energy_progress |
| 05/28/2026 | Mechanical Systems | Ryan Hansen | special |
| 05/28/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 05/19/2026 | Sprinkler Systems | Ryan Hansen | special |
| 05/19/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 05/01/2026 | Final | Ryan Hansen | progress |
| 05/01/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 04/20/2026 | Interior lighting power | Ryan Hansen | energy_progress |
| 04/20/2026 | Fire-Resistant Penetrations and Joints | Ryan Hansen | special |
| 04/20/2026 | Mechanical Systems | Ryan Hansen | special |
| 04/20/2026 | Energy Code Compliance Inspections | Ryan Hansen | progress |
| 04/20/2026 | Final | Ryan Hansen | progress |
| 04/20/2026 | HVAC-R and service water heating system controls | Ryan Hansen | energy_progress |
| 04/20/2026 | HVAC-R and service water piping design and insulation | Ryan Hansen | energy_progress |
| 04/20/2026 | Shutoff dampers | Ryan Hansen | energy_progress |