← Back
Two family brick
939 PACIFIC STREET
BROOKLYN · BIN 3027531
💬 Discuss this project
1920Year Built
2Stories
B1Building Class
R6BZoning
1,890 sfGross Floor Area
2Units
Rent Stabilized16 Open Violations ▸FDNY Report ↗
Two family brick · Owner of record: 939 PACIFIC LLC · 1,875 sf lot · 1.01 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
Roof4p · 2 filings · 19 docs
Bulkhead2p · 1 filing · 11 docs
Floor 2Under Construction3p · 1 filing · 13 docs
Floor 1Under Construction5p · 2 filings · 20 docs
CellarUnder Construction15p · 3 filings · 20 docs
Basement1p · 1 filing · 8 docs
Sub-BasementUnder Construction2p · 1 filing · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MNB DEVELOPERS109/01/2026
939 PACIFIC LLC103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/21/2024$1.5M—— → —$794/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
THOMAS C. TUNG, P.E.106/23/2026
AARON MCDONALD ARCHITECT209/25/2025
NIC 88 CORP103/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BASIC GROUPS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CUBE BUILDERS GROUP NYGeneral Contractor404/10/2026
PIPESTYLISTS, INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AARON MCDONALD ARCHITECT5118109/25/2025
NIC 88 CORP8371203/05/2025
Building Lifecycle
All (91)Filed (4)Permit Issued (3)Violation (17)Objection (37)Special Inspection (30)
08/04/2026
Objection resolved — Resolved
07/20/2026
Objection raised — Scope
07/17/2026
Objection raised — Scope
07/17/2026
Objection raised — Scope
07/17/2026
Objection raised — Scope
07/17/2026
Objection raised — Scope
07/17/2026
Objection raised — Scope
07/15/2026
Objection raised — Scope
07/15/2026
Objection raised — Other
06/23/2026
Filed — Alteration CO
PROPOSED HORIZONTAL ENLARGEMENT ON EXISTING TWO(2) STORY WITH BASEMENT & CELLAR CONVERTING TWO(2) FAMILY INTO ONE(1) FAMILY.OBTAIN NEW CERTIFICATE OF OCCUPANCY AS ONE(1) FAMILY RESIDENTIAL.
B01419645-I1
02/24/2026
Objection resolved — Addressed
02/20/2026
Objection raised — Cost
12/18/2025
Objection resolved — Addressed
12/18/2025
Objection resolved — Addressed
12/05/2025
Objection raised — Admin
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/26/2025
Objection resolved — Addressed
11/25/2025
Objection resolved — Addressed
11/12/2025
Objection raised — Energy
11/12/2025
Objection raised — Fire_Protection
11/12/2025
Objection raised — Fire_Protection
11/12/2025
Objection raised — Energy
11/12/2025
Objection raised — Cost
11/12/2025
Objection raised — Zoning
11/12/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
11/04/2025
Special inspection requirement — Concrete - Cast-In-Place
11/04/2025
Special inspection requirement — Air barrier - visual inspection
11/04/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
11/04/2025
Special inspection requirement — Interior lighting power
11/04/2025
Special inspection requirement — Insulation placement and R values
11/04/2025
Special inspection requirement — Fenestration areas
11/04/2025
Special inspection requirement — Fenestration air leakage
11/04/2025
Special inspection requirement — Fire-Resistance Rated Construction
11/04/2025
Special inspection requirement — Energy Code Compliance Inspections
11/04/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
11/04/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
11/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Aaron McDonald
10/06/2025
Objection raised — Structural
10/06/2025
Objection raised — Zoning
10/06/2025
Objection raised — Admin
10/06/2025
Objection raised — Admin
10/06/2025
Objection raised — Fire_Protection
10/06/2025
Objection raised — Scope
10/06/2025
Objection raised — Scope
10/06/2025
Objection raised — Scope
09/25/2025
Filed — Alteration
PROPOSED HOLIZOTAL & VERTICAL EXTENSION @ BASEMENT, 1ST & 2ND FLOOR. AS PER PLANS OF 3 STORY EXISTING BUILDING. CONSTRUCTION WORK AS PARTITION, FLOORING AND PAINTING WORKS AS PER PLAN. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01265942-I1
09/05/2025
Special inspection requirement — Structural Steel - Details
09/05/2025
Special inspection requirement — Structural Cold-Formed Steel
08/04/2025
Special inspection requirement — Footing and Foundation
08/04/2025
Special inspection requirement — Final
03/20/2025
Permit issued — Mechanical Systems
B01189215-I1-GC-CX
03/10/2025
Permit issued — Plumbing
B01189215-S1-PL
03/10/2025
Permit issued — Mechanical Systems
B01189215-I1-GC-CX
03/05/2025
Filed — Alteration
INTERIOR RENOVATION OF CELLAR, BASEMENT, 1ST, AND 2ND FL OF EXIST. 2 STORY BUILDING. DEMOLITION WORK AND CONSTRUCTION WORK AS PER PLAN. INSTALL NEW HVAC, PARTITION, FLOORING, CEILING AND PAINTING THROUGHOUT, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01189215-I1
03/05/2025
Filed — Alteration
INTERIOR RENOVATION OF CELLAR, BASEMENT, 1ST, AND 2ND FL OF EXIST. 2 STORY BUILDING. DEMOLITION WORK AND CONSTRUCTION WORK AS PER PLAN. INSTALL NEW HVAC, PARTITION, FLOORING, CEILING AND PAINTING THROUGHOUT, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01189215-S1
Latest 60 of 91 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedCUBE BUILDERS GROUP NY03/20/2025
DOB NOWPlumbingPermit IssuedT & T PLUMBING INC03/10/2025
DOB NOWMechanical SystemsPermit IssuedCUBE BUILDERS GROUP NY03/10/2025
1 project · most recent 03/05/2025
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
03/05/2025Permit IssuedCUBE BUILDERS GROUP NYAir Conditioning Systems
1 project · most recent 03/05/2025
Gas Water/Sanitary
FiledStatusContractorScope
03/05/2025Permit IssuedT & T PLUMBING INCGas, Water/Sanitary
2 projects · most recent 06/23/2026
Steel Wood
FiledStatusContractorScope
06/23/2026——Steel, Wood
09/25/2025——Steel, Wood
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
11/04/2025Concrete - Cast-In-Place—special
11/04/2025Air barrier - visual inspection—energy_progress
11/04/2025Fenestration and door U-factor and product ratings—energy_progress
11/04/2025Interior lighting power—energy_progress
11/04/2025Insulation placement and R values—energy_progress
11/04/2025Fenestration areas—energy_progress
11/04/2025Fenestration air leakage—energy_progress
11/04/2025Fire-Resistance Rated Construction—progress
11/04/2025Energy Code Compliance Inspections—progress
11/04/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
11/04/2025Structural Stability – Alterations of existing buildings—special
11/03/2025Fire-Resistant Penetrations and JointsAaron McDonaldspecial
09/05/2025Structural Steel - Details—special
09/05/2025Structural Cold-Formed Steel—special
08/04/2025Footing and Foundation—progress
08/04/2025Final—progress
03/04/2025HVAC-R and service water piping design and insulationEric Sunenergy_progress
03/04/2025Fire-Resistant Penetrations and JointsEric Sunspecial
03/04/2025Energy Code Compliance InspectionsEric Sunprogress
03/04/2025HVAC-R and service water heating equipmentEric Sunenergy_progress
03/04/2025HVAC-R and service water heating system controlsEric Sunenergy_progress
03/03/2025HVAC-R and service water heating equipmentEric Sunenergy_progress
03/03/2025Maintenance informationEric Sunenergy_progress
03/03/2025HVAC-R and service water piping design and insulationEric Sunenergy_progress
03/03/2025Air barrier - visual inspectionEric Sunenergy_progress
Latest 25 of 38.
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/22/2026B01189215-I1Request digital key ↗
08/22/2026B01189215-S1Request digital key ↗
08/16/2026B01419645-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/16/2026B01419645-I1Open ↗
08/13/2026B01265942-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/16/2026B01419645-I1Open ↗
08/13/2026B01265942-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/16/2026B01419645-I1Open ↗
▸Seals & Professional Certifications11
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/22/2026B01189215-I1Open ↗
08/20/2026B01265942-I1Open ↗
08/16/2026B01419645-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/02/2026B01189215-S1Open ↗
09/02/2026B01189215-S1Open ↗
08/26/2026B01189215-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/02/2026B01189215-S1Open ↗
08/26/2026B01189215-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/16/2026B01419645-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/16/2026B01419645-I1Open ↗
08/15/2026B01265942-I1Open ↗
08/13/2026B01189215-I1Open ↗
Showing 3 of 4 on file for this type
▸Other Documents7
▸DOB NOWSite Survey: Initial2
08/16/2026B01419645-I1Open ↗
08/13/2026B01265942-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/16/2026B01419645-I1Open ↗
08/13/2026B01265942-I1Open ↗
▸DOB NOWPlot Diagram2
08/16/2026B01419645-I1Open ↗
08/13/2026B01265942-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/16/2026B01419645-I1Open ↗