12 Open Violations ▸FDNY Report ↗
Two stories - detached, small or mid-size · 2,018 sf lot · 0.56 FAR built · Flood zone X
Locations of Work
StructuralPlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction2 filings · 15 docs
Floor 1Under Construction2 filings · 15 docs
CellarUnder Construction2 filings · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
INGA CONSULTING ENGINEERS206/15/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LAVB DESIGN CONSULTANTS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MORELL BUILDERS INCGeneral Contractor303/21/2026
RKA PIPING AND HEATINGPlumbing107/02/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519106/15/2026
CL ENGINEERING P.C.6781104/26/2025
Building Lifecycle
All (47)Filed (2)Permit Issued (2)Violation (25)Inspection (3)Special Inspection (15)
09/10/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/29/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/30/2026
Permit issued — Plumbing
Q01241360-I1-PL
06/15/2026
Filed — Alteration
Q01241360-I1
06/13/2025
Special inspection requirement — Maintenance information
Andrew Inga
06/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Andrew Inga
06/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
06/13/2025
Special inspection requirement — Energy Code Compliance Inspections
Andrew Inga
06/13/2025
Special inspection requirement — HVAC-R and service water heating equipment
Andrew Inga
05/09/2025
Permit issued — Structural
Q01186583-I1-GC-CX
04/26/2025
Filed — Alteration
HEREWITH FILING TO REPAIR FIRE DAMAGED AT THE REAR OF THE BUILDING. REPAIR STRUCTURALLY AS PER ENGINEER'S REPORT AND FULLY RENOVATEDNEW PARTITION WALLS, FINISH FLOORING, NEW INTERIOR DOORS, NEW TILES AND NEW PLUMBING FIXTURES AS PER PLANS.
Q01186583-I1
03/19/2025
Special inspection requirement — Insulation placement and R values
Andrew Inga
03/19/2025
Special inspection requirement — Fenestration air leakage
Andrew Inga
03/19/2025
Special inspection requirement — Fenestration areas
Andrew Inga
03/19/2025
Special inspection requirement — Lighting in dwelling units
Andrew Inga
03/19/2025
Special inspection requirement — Energy Code Compliance Inspections
Andrew Inga
03/19/2025
Special inspection requirement — Structural Wood Frame
Andrew Inga
03/19/2025
Special inspection requirement — Air barrier - visual inspection
Andrew Inga
03/19/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Andrew Inga
02/25/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
CHRISTIAN LOZADA
02/25/2025
Special inspection requirement — Final
Andrew Inga
08/15/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/13/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/10/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/10/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/09/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/05/2012
Violation issued (ECB, closed)
Unknown
04/20/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/23/2011
Violation issued (ECB, closed)
Construction
03/09/2011
Violation issued (ECB, closed)
Construction
03/09/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/19/2011
Violation issued (ECB, closed)
Quality of Life
01/19/2011
Violation issued (ECB, closed)
Construction
01/13/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/14/2010
Violation issued (ECB, closed)
Construction
10/13/2010
Violation issued (ECB, closed)
Construction
10/13/2010
Violation issued (ECB, closed)
Quality of Life
10/13/2010
Violation issued (ECB, closed)
Construction
07/13/2010
Violation issued (HPD, open)
C
05/19/2010
Violation issued (HPD, open)
B
05/19/2010
Violation issued (HPD, open)
B
05/19/2010
Violation issued (HPD, open)
C
09/15/2009
Violation issued (HPD, open)
B
09/15/2009
Violation issued (HPD, open)
B
09/15/2009
Violation issued (HPD, open)
B
09/15/2009
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedRKA PIPING AND HEATING06/30/2026
DOB NOWStructuralPermit IssuedMORELL BUILDERS INC05/09/2025
1 project · most recent 03/12/2026
General Wiring
FiledStatusContractorScope
03/12/2026Permit IssuedRONEY ELECTRIC INCGeneral Wiring
1 project · most recent 04/26/2025
Wood
FiledStatusContractorScope
04/26/2025Permit IssuedMORELL BUILDERS INCWood
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
09/10/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/29/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
07/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
06/13/2025Maintenance informationAndrew Ingaenergy_progress
06/13/2025HVAC-R and service water piping design and insulationAndrew Ingaenergy_progress
06/13/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
06/13/2025Energy Code Compliance InspectionsAndrew Ingaprogress
06/13/2025HVAC-R and service water heating equipmentAndrew Ingaenergy_progress
03/19/2025Insulation placement and R valuesAndrew Ingaenergy_progress
03/19/2025Fenestration air leakageAndrew Ingaenergy_progress
03/19/2025Fenestration areasAndrew Ingaenergy_progress
03/19/2025Lighting in dwelling unitsAndrew Ingaenergy_progress
03/19/2025Energy Code Compliance InspectionsAndrew Ingaprogress
03/19/2025Structural Wood FrameAndrew Ingaprogress
03/19/2025Air barrier - visual inspectionAndrew Ingaenergy_progress
03/19/2025Fenestration and door U-factor and product ratingsAndrew Ingaenergy_progress
02/25/2025Structural Stability – Alterations of existing buildingsCHRISTIAN LOZADAspecial
02/25/2025FinalAndrew Ingaprogress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01186583-I1Request digital key ↗
08/16/2026Q01241360-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature6
08/24/2026Q01186583-I1Open ↗
08/24/2026Q01186583-I1Open ↗
08/24/2026Q01186583-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/16/2026Q01241360-I1Open ↗
08/13/2026Q01186583-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/24/2026Q01186583-I1Open ↗
08/23/2026Q01241360-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/16/2026Q01241360-I1Open ↗
08/13/2026Q01186583-I1Open ↗
▸Other Documents1
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01186583-I1Open ↗