← Back
Two family frame
95-14 42 AVENUE
QUEENS · Elmhurst · BIN 4039911
💬 Discuss this project
1920Year Built
2Stories
B2Building Class
R5Zoning
2,356 sfGross Floor Area
2Units
Two family frame · 2,300 sf lot · 1.02 FAR built · Flood zone X
Locations of Work
Electrical
Roof3p · 1 filing · 18 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR201/20/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281201/20/2026
Building Lifecycle
All (17)Filed (2)Permit Issued (1)Special Inspection (14)
01/28/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
01/28/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/28/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/28/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
01/28/2026
Special inspection requirement — Final
Mina Makar
01/28/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/28/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
01/20/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 20 modules, 8.2 KW
Q01299499-P1
01/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/20/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
01/20/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
01/20/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/20/2026
Special inspection requirement — Final
Mina Makar
01/20/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
10/15/2025
Permit issued — Solar
Q01299499-I1-SL
10/08/2025
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 20 modules, 8.2 KW
Q01299499-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR10/15/2025
1 project · most recent 11/14/2025
FiledStatusContractorScope
11/14/2025CompleteISLAND ELECTRIC CORP—
1 project · most recent 01/20/2026
FiledStatusContractorScope
01/20/2026Permit IssuedMOMENTUM SOLAR80 panels, 32.8 kw, 352 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
01/28/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
01/28/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
01/28/2026Fire-Resistant Penetrations and JointsMina Makarspecial
01/28/2026Post-installed AnchorsMina Makarspecial
01/28/2026FinalMina Makarprogress
01/28/2026Energy Code Compliance InspectionsMina Makarprogress
01/28/2026Air barrier - visual inspectionMina Makarenergy_progress
01/20/2026Fire-Resistant Penetrations and JointsMina Makarspecial
01/20/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
01/20/2026Post-installed AnchorsMina Makarspecial
01/20/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
01/20/2026Energy Code Compliance InspectionsMina Makarprogress
01/20/2026FinalMina Makarprogress
01/20/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 18 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01299499-I1Request digital key ↗
08/17/2026Q01299499-P1Request digital key ↗
▸Seals & Professional Certifications14
▸DOB NOWSpecial Inspector Seal & Signature8
08/23/2026Q01299499-P1Open ↗
08/23/2026Q01299499-P1Open ↗
08/23/2026Q01299499-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/23/2026Q01299499-P1Open ↗
08/23/2026Q01299499-P1Open ↗
08/23/2026Q01299499-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01299499-I1Open ↗
08/17/2026Q01299499-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01299499-I1Open ↗
08/17/2026Q01299499-P1Open ↗