Two family converted from one family
95-27 97 AVENUE
QUEENS · Ozone Park (North) · BIN 4187755
💬 Discuss this project
1925Year Built
2Stories
B3Building Class
R4-1Zoning
1,152 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family converted from one family · 1,534 sf lot · 0.75 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof5p · 1 filing · 12 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC207/25/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYS ESSENTIAL POWER INCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854207/25/2024
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Violation (3)Special Inspection (5)
07/26/2024
Signed off — Alteration
Installation of PV System on existing rooftop. No changes to Egress or use of occupancy.
Q01071653-I1
07/25/2024
Filed — Alteration
Installation of PV System on existing rooftop. No changes to Egress or use of occupancy.
Q01071653-P1
07/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
07/25/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
07/25/2024
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
07/25/2024
Special inspection requirement — Final
TOM PETERSEN
07/25/2024
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
07/02/2024
Permit issued — Solar
Q01071653-I1-SL
06/25/2024
Filed — Alteration
Installation of PV System on existing rooftop. No changes to Egress or use of occupancy.
Q01071653-I1
11/28/2007
Violation issued (ECB, closed)
Construction
08/29/2002
Violation issued (ECB, closed)
Quality of Life
08/29/2002
Violation issued (ECB, open)
Quality of Life
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYS ESSENTIAL POWER INC07/02/2024
2 projects · most recent 06/25/2024
FiledStatusContractorScope
06/25/2024CompleteAMBER ELECTL CONTNG INC1 meters
06/18/2024CompleteAMBER ELECTL CONTNG INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/25/2024Fire-Resistant Penetrations and JointsTOM PETERSENspecial
07/25/2024Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
07/25/2024Energy Code Compliance InspectionsTOM PETERSENprogress
07/25/2024FinalTOM PETERSENprogress
07/25/2024Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026Q01071653-I1Request digital key ↗
08/22/2026Q01071653-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/31/2026Q01071653-P1Open ↗
08/31/2026Q01071653-P1Open ↗
08/31/2026Q01071653-P1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/22/2026Q01071653-I1Open ↗
08/13/2026Q01071653-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026Q01071653-P1Open ↗
08/31/2026Q01071653-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/22/2026Q01071653-I1Open ↗
08/13/2026Q01071653-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01071653-I1Open ↗