| Owner | Filings | Most Recent |
|---|---|---|
| BROOKLYN B COMPANY GROUP | 5 | 07/08/2026 |
| 420 EAST 75 STREET | 9 | 07/08/2026 |
| 1310 MYRTLE | 4 | 04/09/2026 |
| OWNER OF 95 MONROE STREET | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/30/2026 | $2.8M | — | — → — | $1,404/sf building |
| 07/16/2024 | $1.3M | — | Private party → BEDSTUY GROUP CAPITAL LLC | $672/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CQ&J CORPORATION | 5 | 12/09/2025 |
| THOMAS C. TUNG, P.E. | 2 | 10/29/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| WM ARCH | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AB PLUS R CONSTRUCTION IN | General Contractor | 2 | 07/08/2026 |
| IK MGNT LLC | General Contractor | 1 | 04/09/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SIMON | 7555 | 1 | 12/09/2025 |
| D&E BUILD EVERGREEN I | 9342 | 2 | 10/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | IK MGNT LLC | 12/12/2025 |
| DOB NOW | Plumbing | Signed-off | ALL PRO PLBG & HTG INC | 02/14/2025 |
| DOB NOW | General Construction | Permit Issued | AB PLUS R CONSTRUCTION IN | 01/16/2025 |
| DOB NOW | Construction Fence | Signed-off | AB PLUS R CONSTRUCTION IN | 08/26/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/09/2025 | Signed-off | IK MGNT LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/09/2025 | Signed-off | ALL PRO PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Complete | POWER SURGE ELECTRIC, INC | 3 meters, 1 new_meters |
| 09/04/2024 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/30/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/31/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/29/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/28/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/08/2025 | HVAC-R and service water piping design and insulation | CALVIN TRAN | energy_progress |
| 12/08/2025 | Maintenance information | CALVIN TRAN | energy_progress |
| 12/08/2025 | HVAC-R and service water heating system controls | CALVIN TRAN | energy_progress |
| 12/08/2025 | HVAC-R and service water heating equipment | CALVIN TRAN | energy_progress |
| 11/12/2025 | Insulation placement and R values | THOMAS TUNG | energy_progress |
| 11/12/2025 | Metering | THOMAS TUNG | energy_progress |
| 11/12/2025 | Fenestration and door U-factor and product ratings | THOMAS TUNG | energy_progress |
| 11/12/2025 | Interior lighting power | THOMAS TUNG | energy_progress |
| 11/12/2025 | Fenestration areas | THOMAS TUNG | energy_progress |
| 11/12/2025 | Air barrier - visual inspection | THOMAS TUNG | energy_progress |
| 11/12/2025 | Permanent certificate | THOMAS TUNG | energy_progress |
| 11/12/2025 | Fenestration air leakage | THOMAS TUNG | energy_progress |
| 11/12/2025 | Fire-Resistant Penetrations and Joints | Danny Chen | special |
| 11/12/2025 | Structural Stability – Alterations of existing buildings | Danny Chen | special |
| 11/12/2025 | Fire-Resistance Rated Construction | THOMAS TUNG | progress |
| 11/12/2025 | Energy Code Compliance Inspections | THOMAS TUNG | progress |
| 10/15/2025 | Fenestration areas | THOMAS TUNG | energy_progress |
| 10/15/2025 | Permanent certificate | THOMAS TUNG | energy_progress |
| 10/15/2025 | Fenestration and door U-factor and product ratings | THOMAS TUNG | energy_progress |
| 10/15/2025 | Fenestration air leakage | THOMAS TUNG | energy_progress |
| 10/15/2025 | Insulation placement and R values | THOMAS TUNG | energy_progress |
| 10/15/2025 | Interior lighting power | THOMAS TUNG | energy_progress |
| 10/15/2025 | Metering | THOMAS TUNG | energy_progress |
| 10/15/2025 | Fire-Resistant Penetrations and Joints | Danny Chen | special |
| 10/15/2025 | Structural Stability – Alterations of existing buildings | Danny Chen | special |