| Owner | Filings | Most Recent |
|---|---|---|
| 95-22 147th PL | 3 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/12/2017 | $400K | — | — → — | $97/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Leslie M. Good Architects | 4 | 10/15/2024 |
| Acv Design | 2 | 06/17/2024 |
| Aryeh Siegel Architect | 1 | 03/07/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Avalon Design | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Heartfelt Townhouse Builders | Scaffold | 2 | 03/21/2026 |
| Amm General Contracting | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Acv Design | 3864 | 2 | 06/17/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Amm General Contracting | 12/11/2023 |
| DOB NOW | Construction Fence | Signed-off | Heartfelt Townhouse Builders | 03/28/2022 |
| BIS | — | ISSUED | All Star 1 | 04/11/2022 |
| BIS | PL | ISSUED | L&J PLG & Heating Co of NY | 10/13/2017 |
| BIS | OT | ISSUED | H.P.N. Construction | 10/11/2017 |
| BIS | FP | ISSUED | Fire Command Co | 06/19/2015 |
| BIS | OT | ISSUED | Nobel Construction | 05/29/2015 |
| BIS | PL | ISSUED | Fernandez Heating & Mechanical | 07/23/2014 |
| BIS | OT | ISSUED | L J & A Construction | 07/08/2014 |
| BIS | OT | ISSUED | L J & A Construction | 06/26/2014 |
| BIS | OT | ISSUED | L J & A Construction | 06/20/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2024 | Signed-off | Amm General Contracting | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2023 | Permit Issued | Berardi Electrical Contracting | 6 meters, 1 new_meters |
| 08/02/2023 | Complete | Joseph Weinstein Electric | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/28/2024 | HVAC-R and service water piping design and insulation | LESLIE GOOD | energy_progress |
| 10/28/2024 | HVAC-R and service water heating equipment | LESLIE GOOD | energy_progress |
| 09/23/2024 | HVAC-R and service water heating equipment | LESLIE GOOD | energy_progress |
| 09/23/2024 | HVAC-R and service water piping design and insulation | LESLIE GOOD | energy_progress |
| 09/04/2024 | HVAC-R and service water piping design and insulation | LESLIE GOOD | energy_progress |
| 09/04/2024 | HVAC-R and service water heating equipment | LESLIE GOOD | energy_progress |
| 07/01/2024 | Fire-Resistance Rated Construction | ANTHONY VILLANO | progress |
| 07/01/2024 | Final | — | progress |
| 07/01/2024 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 06/17/2024 | HVAC-R and service water heating equipment | LESLIE GOOD | energy_progress |
| 06/17/2024 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 06/17/2024 | Final | — | progress |
| 06/17/2024 | Fire-Resistance Rated Construction | ANTHONY VILLANO | progress |
| 06/17/2024 | HVAC-R and service water piping design and insulation | LESLIE GOOD | energy_progress |