| Owner | Filings | Most Recent |
|---|---|---|
| LEFKO CAPITAL GROUP | 11 | 07/08/2026 |
| 951 SHERMAN LLC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/28/2023 | $1.2M | — | — → — | $262/sf building |
| 02/24/2023 | $855K | — | — → — | $179/sf building |
| 07/15/2022 | $550K | — | — → — | $115/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ADB ASSOCIATES | 6 | 08/14/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC DESIGN FILE | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MABE GROUP INC | General Contractor | 2 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| MPI PLUMBING CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 5 | 08/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | AB BUILDERS NY | 07/05/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 06/08/2023 |
| DOB NOW | Plumbing | Signed-off | YG SERVICES INC | 04/19/2023 |
| DOB NOW | General Construction | Permit Issued | AB BUILDERS NY | 03/24/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/15/2023 | Complete | FRIED ELECTRIC CO. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/06/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/27/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/22/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/12/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/09/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/17/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/17/2023 | Post-installed Anchors | FAHAD FATEH | special |
| 02/06/2023 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 02/06/2023 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 02/06/2023 | Heating Systems | FAHAD FATEH | special |
| 02/06/2023 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 01/09/2023 | Final | FAHAD FATEH | progress |
| 01/09/2023 | Mechanical Systems | FAHAD FATEH | special |
| 01/09/2023 | Sprinkler Systems | FAHAD FATEH | special |