← Back
Miscellaneous two family
952 EAST 220 STREET
BRONX · Williamsbridge-Olinville · BIN 2059079
💬 Discuss this project
1960Year Built
3Stories
B9Building Class
R4Zoning
2,140 sfGross Floor Area
2Units
Miscellaneous two family · 2,178 sf lot · 0.98 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof4p · 1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/30/2024$957K—— → —$447/sf building
04/15/2024$280K—Private party → BX 952 LLC$131/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
UNISOLAR104/21/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BERGER QUALITY ELEC'L CONElectrical103/22/2026
CENTURION SOLAR ENERGYGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CENTURION SOLAR ENERGY LL9475104/21/2025
Building Lifecycle
All (14)Filed (1)Permit Issued (1)Signed Off (1)Objection (6)Special Inspection (5)
05/15/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01212261-I1
05/20/2025
Permit issued — Solar
X01212261-I1-SL
04/29/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/29/2025
Objection resolved — Addressed
04/24/2025
Objection raised — Mechanical
04/24/2025
Objection raised — Structural
04/24/2025
Objection raised — Electrical
04/21/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
X01212261-I1
04/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Andres Arias Londono
04/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Andres Arias Londono
04/17/2025
Special inspection requirement — Energy Code Compliance Inspections
Andres Arias Londono
04/17/2025
Special inspection requirement — Final
Andres Arias Londono
04/17/2025
Special inspection requirement — Air barrier - visual inspection
Andres Arias Londono
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY05/20/2025
2 projects · most recent 12/05/2025
General Wiring
FiledStatusContractorScope
12/05/2025CompleteVILLAGE ELECTL CONTRS INCGeneral Wiring
04/19/2025CompleteBERGER QUALITY ELEC'L CON—
1 project · most recent 04/21/2025
FiledStatusContractorScope
04/21/2025Signed-offCENTURION SOLAR ENERGY11 panels, 4.67 kw, 231.22 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/17/2025Fire-Resistant Penetrations and JointsAndres Arias Londonospecial
04/17/2025Structural Stability – Alterations of existing buildingsAndres Arias Londonospecial
04/17/2025Energy Code Compliance InspectionsAndres Arias Londonoprogress
04/17/2025FinalAndres Arias Londonoprogress
04/17/2025Air barrier - visual inspectionAndres Arias Londonoenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026X01212261-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026X01212261-I1Open ↗
08/24/2026X01212261-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026X01212261-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026X01212261-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01212261-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/19/2026X01212261-I1Open ↗