1925Year Built
2Stories
A9Building Class
R4-1Zoning
1,588 sfGross Floor Area
1Units
Miscellaneous one family · 2,250 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Architecture
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 2Relocated windows and stucco finish, 2nd floor1p · 1 filing · 7 docs
Floor 1
Site & exteriorRelocated windows and stucco finish, 2nd floor1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Sebastian M D'Alessandro110/10/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
John Evan ContractingGeneral Contractor107/08/2026
Building Lifecycle
12/17/2024
Signed off — Alteration
Obtain work permit for two (2) relocated windows at 2nd Floor as per DOB request for corrective action. New stucco finish at 2nd Floor front facade. Also replace existing masonry steps with new at front. No change in egress, use or occupancy.
B01122819-I1
10/18/2024
Permit issued — General Construction
B01122819-I1-GC
10/10/2024
Filed — Alteration
Obtain work permit for two (2) relocated windows at 2nd Floor as per DOB request for corrective action. New stucco finish at 2nd Floor front facade. Also replace existing masonry steps with new at front. No change in egress, use or occupancy.
B01122819-I1
10/10/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Sebastian D'Alessandro
10/10/2024
Special inspection requirement — Energy Code Compliance Inspections
Sebastian D'Alessandro
9 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offJohn Evan Contracting10/18/2024
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
10/10/2024Exterior Insulation and Finish Systems (EIFS)Sebastian D'Alessandrospecial
10/10/2024Energy Code Compliance InspectionsSebastian D'Alessandroprogress
10/07/2024FinalSebastian D'Alessandroprogress
10/07/2024Fenestration and door U-factor and product ratingsSebastian D'Alessandroenergy_progress
10/07/2024Fenestration areasSebastian D'Alessandroenergy_progress
10/07/2024Fenestration air leakageSebastian D'Alessandroenergy_progress