← Back
Two family frame
964 EAST 95 STREET
BROOKLYN · BIN 3228941
💬 Discuss this project
1925Year Built
2Stories
B2Building Class
R4-1Zoning
2,088 sfGross Floor Area
2Units
Two family frame · 2,708 sf lot · 0.77 FAR built · Flood zone X
Locations of Work
Architecture
Roof3p · 1 filing · 15 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/28/2024$1.2M—718 PARTNERS NY LLC → Private party$575/sf building
06/15/2023$675K—— → —$323/sf building
12/15/2022$381K—— → —$182/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC201/13/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854201/13/2026
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
05/05/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.
B01326996-I1
01/27/2026
Permit issued — Solar
B01326996-I1-SL
01/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
01/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
01/26/2026
Special inspection requirement — Final
TOM PETERSEN
01/26/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
01/26/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
01/13/2026
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.
B01326996-P1
01/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
01/13/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
01/13/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
01/13/2026
Special inspection requirement — Final
TOM PETERSEN
01/13/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
12/22/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.
B01326996-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC01/27/2026
1 project · most recent 12/02/2025
FiledStatusContractorScope
12/02/2025CompleteSOLAR ELEC CONTRACTNG LLC—
1 project · most recent 01/13/2026
FiledStatusContractorScope
01/13/2026Signed-offSOLAR CONTRACTING LLC32 panels, 13.76 kw, 1,039.26 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
01/26/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
01/26/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
01/26/2026FinalTOM PETERSENprogress
01/26/2026Energy Code Compliance InspectionsTOM PETERSENprogress
01/26/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
01/13/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
01/13/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
01/13/2026Energy Code Compliance InspectionsTOM PETERSENprogress
01/13/2026FinalTOM PETERSENprogress
01/13/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026B01326996-P1Request digital key ↗
08/19/2026B01326996-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026B01326996-I1Open ↗
09/01/2026B01326996-I1Open ↗
09/01/2026B01326996-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026B01326996-I1Open ↗
08/13/2026B01326996-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026B01326996-I1Open ↗
09/01/2026B01326996-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/19/2026B01326996-I1Open ↗
08/13/2026B01326996-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/19/2026B01326996-I1Open ↗