← Back
Church, synagogue, chapel
965 BEDFORD AVENUE
BROOKLYN · BIN 3048933
💬 Discuss this project
1931Year Built
1Stories
M1Building Class
R7AZoning
7,500 sfGross Floor Area
1Units
2 Open Violations 1 unresolved · 1 paperwork only ▸FDNY Report ↗
Church, synagogue, chapel · 5,000 sf lot · 1.5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire Protection
Roof3p · 1 filing · 20 docs
Penthouse2p · 1 filing · 20 docs
Floor 64p · 1 filing · 20 docs
Floor 54p · 1 filing · 20 docs
Floor 41p · 1 filing · 20 docs
Floor 3
Floor 21p · 1 filing · 20 docs
Floor 1
Cellar3p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
965 BEDFORD AVE103/22/2026
HOMELAND PROPERTY GROUP1803/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
INFOCUS DESIGN AND PLANNING PC709/28/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
XH&RC PLUMBING AND HEATING INC803/21/2026
INFOCUS DESIGN AND PLANNING PC603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOHN JR MARIElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
INFOCUS DESIGN & PLANNING932109/14/2022
Building Lifecycle
All (68)Filed (7)Violation (5)Objection (26)Special Inspection (30)
12/22/2022
Objection raised — Fire_Protection
12/22/2022
Objection resolved — Addressed
12/22/2022
Objection raised — Fire_Protection
12/22/2022
Objection resolved — Addressed
12/22/2022
Objection raised — Mechanical
12/22/2022
Objection resolved — Addressed
10/28/2022
Special inspection requirement — Preliminary
10/28/2022
Special inspection requirement — Fire-Resistance Rated Construction
09/30/2022
Objection raised — Structural
09/30/2022
Objection resolved — Addressed
09/30/2022
Objection raised — Structural
09/30/2022
Objection resolved — Addressed
09/30/2022
Objection raised — Mechanical
09/30/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Scope
09/29/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Scope
09/29/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Admin
09/29/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Scope
09/29/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Inspections
09/29/2022
Objection resolved — Addressed
09/29/2022
Objection raised — Scope
09/29/2022
Objection resolved — Addressed
09/28/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Convert existing 2 story Public building (Place of assembly) into mix use building (community, commercial and residential building), Vertical extension from 2 to 6 story building. Total 6 story building with penthouse and cellar mixed use building
B00583445-S2
09/28/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Convert existing 2 story Public building (Place of assembly) into mix use building (community, commercial and residential building), Vertical extension from 2 to 6 story building. Total 6 story building with penthouse and cellar mixed use building
B00583445-S1
09/28/2022
Objection raised — Other
09/28/2022
Objection resolved — Addressed
09/28/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
WU(WOODY) CHEN
09/26/2022
Special inspection requirement — Maintenance information
09/26/2022
Special inspection requirement — HVAC-R and service water heating system controls
09/26/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
09/26/2022
Special inspection requirement — HVAC-R and service water heating equipment
09/26/2022
Special inspection requirement — Metering
09/26/2022
Special inspection requirement — Shutoff dampers
09/26/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/26/2022
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
09/26/2022
Special inspection requirement — Metering
09/26/2022
Special inspection requirement — Maintenance information
09/26/2022
Special inspection requirement — HVAC-R and service water heating equipment
09/26/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
09/26/2022
Special inspection requirement — HVAC-R and service water heating system controls
09/14/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Convert existing 2 story Public building (Place of assembly) into mix use building (community, commercial and residential building), Vertical extension from 2 to 6 story building. Total 6 story building with penthouse and cellar mixed use building
B00583445-S5
09/14/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Convert existing 2 story Public building (Place of assembly) into mix use building (community, commercial and residential building), Vertical extension from 2 to 6 story building. Total 6 story building with penthouse and cellar mixed use building
B00583445-S3
09/14/2022
Filed — ALT-CO - New Building with Existing Elements to Remain
Convert existing 2 story Public building (Place of assembly) into mix use building (community, commercial and residential building), Vertical extension from 2 to 6 story building. Total 6 story building with penthouse and cellar mixed use building
B00583445-S4
09/13/2022
Special inspection requirement — Subgrade Inspections
09/13/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/08/2022
Special inspection requirement — Final
09/08/2022
Special inspection requirement — Masonry
09/08/2022
Special inspection requirement — Structural Cold-Formed Steel
09/08/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/08/2022
Special inspection requirement — Structural Steel - Details
09/08/2022
Special inspection requirement — Concrete - Cast-In-Place
09/08/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/08/2022
Special inspection requirement — Concrete - Cast-In-Place
09/08/2022
Special inspection requirement — Subgrade Inspections
09/08/2022
Special inspection requirement — Final
09/08/2022
Special inspection requirement — Footing and Foundation
Latest 60 of 68 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISPLISSUEDMARATHON MECHANICAL LLC05/07/2008
BIS—ISSUED512 MAPLE STREET CORP.01/25/2008
BISEQISSUED514 MAPLE STREET CORP.01/24/2008
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.12/28/2007
BISEQISSUEDS&E BRIDGE & SCAFFOLD LLC.07/24/2007
BISEQISSUED512 MAPLE STREET CORP.01/08/2007
BIS—ISSUED512 MAPLE STREET CORP.01/08/2007
BISEQISSUEDUNIVERSAL OUTREACH MINISTRY08/14/2003
BIS—ISSUEDUNIVERSAL OUTREACH MINISTRY08/14/2003
1 project · most recent 09/28/2022
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
09/28/2022——Heating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric mitsubish mxz-4c36na2 35 BTU · Heat Pump Outdoor ×20
1 project · most recent 09/28/2022
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/28/2022——Gas, Storm, Water/Sanitary
1 project · most recent 09/28/2022
FiledStatusContractorScope
09/28/2022——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 52
DateRequirementInspectorRole
10/28/2022Preliminary—progress
10/28/2022Fire-Resistance Rated Construction—progress
09/28/2022Fire-Resistant Penetrations and JointsWU(WOODY) CHENspecial
09/26/2022Maintenance information—energy_progress
09/26/2022HVAC-R and service water heating system controls—energy_progress
09/26/2022HVAC-R and service water piping design and insulation—energy_progress
09/26/2022HVAC-R and service water heating equipment—energy_progress
09/26/2022Metering—energy_progress
09/26/2022Shutoff dampers—energy_progress
09/26/2022Fire-Resistant Penetrations and Joints—special
09/26/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
09/26/2022Metering—energy_progress
09/26/2022Maintenance information—energy_progress
09/26/2022HVAC-R and service water heating equipment—energy_progress
09/26/2022HVAC-R and service water piping design and insulation—energy_progress
09/26/2022HVAC-R and service water heating system controls—energy_progress
09/13/2022Subgrade Inspections—special
09/13/2022Structural Stability – Alterations of existing buildings—special
09/08/2022Final—progress
09/08/2022Masonry—special
09/08/2022Structural Cold-Formed Steel—special
09/08/2022Structural Stability – Alterations of existing buildings—special
09/08/2022Structural Steel - Details—special
09/08/2022Concrete - Cast-In-Place—special
09/08/2022Structural Stability – Alterations of existing buildings—special
Latest 25 of 52.
▾Documents — 61 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
09/01/2026B00588855-I1Request digital key ↗
08/29/2026B00583445-S3Request digital key ↗
08/29/2026B00583445-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
05/10/2023340861650Open ↗
09/27/2018321844055Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
05/10/2023340861650Open ↗
▸BISPLACE OF ASSEMBLY1
02/23/2009310299067Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00583445-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/01/2026B00588855-I1Open ↗
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-S5Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
09/27/2018321844055Open ↗
02/23/2009310299067Open ↗
05/07/2009310299067Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/17/2023340861650Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
05/10/2023340861650Open ↗
03/17/2023340861650Open ↗
▸BISBPP: STREET TREES SITE PLAN1
05/10/2023340861650Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00583445-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00583445-I1Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-S3Open ↗
08/13/2026B00583445-P1Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
05/10/2023340861650Open ↗
03/17/2023340861650Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
09/27/2018321844055Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00583445-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026B00583445-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
02/23/2009310299067Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
09/27/2018321844055Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET1
09/27/2018321844055Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/17/2023340861650Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
03/17/2023340861650Open ↗
▸Other Documents6
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/29/2026B00583445-I1Open ↗
08/13/2026B00583445-P1Open ↗
▸BISBPP-PARKS: PLANT NEW TREE1
05/10/2023340861650Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
05/10/2023340861650Open ↗