← Back
Public elementary, junior or senior high
P.S. 64 Joseph P. Addabbo
97-16 83 STREET · BIN 4188214
💬 Discuss this project
1939Year Built
4Stories
W1Building Class
R4-1Zoning
53,230 sfGross Floor Area
1Units
LL97 Covered5 Open Violations 1 unresolved · 4 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF PARKS AND RECREATION · 89,000 sf lot · 0.6 FAR built · Flood zone X
Locations of Work
StructuralMechanicalPlumbing
Floor 32p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
1 job · most recent 10/27/2025
Refrigeration Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/27/2025——Refrigeration Systems, Ventilation Systems
Ventilation
Magic-Aire MAUVF5 1,500 CFM · Vav Box ×4
Refrigeration
Airedale ACCM-030-A-A-G-2-1 720,000 BTU · Chiller ×1
1 job · most recent 10/27/2025
Storm Water/Sanitary
FiledStatusContractorScope
10/27/2025——Storm, Water/Sanitary
15 jobs · most recent 08/18/2026
General Wiring Lighting Boiler Controls
FiledStatusContractorScope
08/18/2026Permit IssuedSTANCO SYSTEM ELEC'L CONT—
04/19/2026Permit IssuedCORE ELECTRIC MEP INDS LLGeneral Wiring
03/23/2026CompleteA & S ELECTRIC INC.—
01/29/2026CompleteA & S ELECTRIC INC.—
11/20/2025CompleteCHARAN ELEC'L ENTERP'S IN—
05/06/2024CompleteWILLDAN ELECTRICAL OF NYGeneral Wiring
02/08/2023CompleteMILAD CONTRACTING CORP.General Wiring, Lighting
01/21/2020CompleteCHARAN ELEC'L ENTERP'S IN—
10/15/2019CompleteFALCON ELEC'L CONTR'G CORBoiler Controls
04/25/2019CompleteCHARAN ELEC'L ENTERP'S IN—
04/15/2019CompleteCHARAN ELEC'L ENTERP'S IN—
04/01/2019CompleteCHARAN ELEC'L ENTERP'S IN—
09/11/2018CompleteCHARAN ELEC'L ENTERP'S IN—
08/08/2018CompleteCHARAN ELEC'L ENTERP'S IN—
05/10/2018Permit IssuedCHARAN ELEC'L ENTERP'S IN—
1 job · most recent 10/27/2025
Steel Concrete Masonry
FiledStatusContractorScope
10/27/2025——Steel, Concrete, Masonry
3 jobs · most recent 07/22/2026
Fence Scaffold Sidewalk Shed
FiledStatusContractorScope
07/22/2026Permit IssuedARMY CONSTRUCTION LLCFence
07/19/2026——Scaffold
07/19/2026——Sidewalk Shed
Building Lifecycle
All (112)Filed (8)Permit Issued (2)Violation (60)Objection (12)Special Inspection (30)
08/14/2026
Permit issued — Protection and Mechanical Methods
Q01431668-I1-PMM
08/14/2026
Permit issued — Construction Fence
Q01431666-I1-FN
07/31/2026
Objection resolved — Addressed
07/31/2026
Objection resolved — Addressed
07/31/2026
Objection resolved — Addressed
07/28/2026
Objection raised — Other
07/28/2026
Objection raised — Other
07/28/2026
Objection raised — Other
07/22/2026
Filed — Alteration
Installation of temporary fence in conjunction with Q01307227
Q01431666-I1
07/19/2026
Filed — Alteration
Installation of pipe scaffolding in conjunction with Q01307227
Q01431658-I1
07/19/2026
Filed — Alteration
Installation of chute in conjunction with Q01307227
Q01431668-I1
07/19/2026
Filed — Alteration
Installation of sidewalk shed in conjunction with Q01307227
Q01431663-I1
07/19/2026
Special inspection requirement — Post-installed Anchors
04/07/2026
Violation issued (FDNY_ORDER, closed)
04/07/2026
Violation issued (FDNY_ORDER, closed)
03/13/2026
Objection resolved — Addressed
03/13/2026
Objection resolved — Addressed
03/13/2026
Objection resolved — Addressed
02/27/2026
Violation issued (ECB, open)
Construction
02/25/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
NELSON LOPEZ
11/25/2025
Special inspection requirement — Exterior lighting power
NELSON LOPEZ
11/25/2025
Special inspection requirement — Lighting controls
NELSON LOPEZ
11/25/2025
Special inspection requirement — Maintenance information
NELSON LOPEZ
11/25/2025
Special inspection requirement — Interior lighting power
NELSON LOPEZ
11/25/2025
Special inspection requirement — HVAC-R and service water heating equipment
NELSON LOPEZ
11/25/2025
Special inspection requirement — Electrical motors and elevators
NELSON LOPEZ
11/25/2025
Special inspection requirement — HVAC-R and service water heating system controls
NELSON LOPEZ
11/25/2025
Special inspection requirement — Shutoff dampers
NELSON LOPEZ
11/18/2025
Special inspection requirement — Subgrade Inspections
NELSON LOPEZ
11/18/2025
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
NELSON LOPEZ
11/18/2025
Special inspection requirement — Structural Steel - High Strength Bolting
NELSON LOPEZ
11/07/2025
Objection raised — Other
11/07/2025
Objection raised — Other
11/07/2025
Objection raised — Other
10/27/2025
Filed — Alteration
Roof drain replacement, new rooftop chiller, new unit ventilators, new toilet room fan.
Q01307227-S3
10/27/2025
Filed — Alteration
Roof drain replacement, new rooftop chiller, new unit ventilators, new toilet room fan.
Q01307227-S1
10/27/2025
Filed — Alteration
Roof drain replacement, new rooftop chiller, new unit ventilators, new toilet room fan.
Q01307227-S2
10/27/2025
Violation issued (FDNY_ORDER, closed)
10/27/2025
Violation issued (FDNY_ORDER, closed)
10/24/2025
Filed — Alteration
Roof drain replacement, new rooftop chiller, new unit ventilators, new toilet room fan.
Q01307227-I1
10/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
NELSON LOPEZ
10/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
10/24/2025
Special inspection requirement — Final
NELSON LOPEZ
10/24/2025
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
10/24/2025
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
10/24/2025
Special inspection requirement — Maintenance information
NELSON LOPEZ
10/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
10/24/2025
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
10/24/2025
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
10/24/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
NELSON LOPEZ
10/24/2025
Special inspection requirement — Maintenance information
NELSON LOPEZ
10/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NELSON LOPEZ
10/24/2025
Special inspection requirement — Structural Steel - Details
NELSON LOPEZ
10/24/2025
Special inspection requirement — Concrete - Cast-In-Place
NELSON LOPEZ
10/24/2025
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
10/24/2025
Special inspection requirement — Structural Steel - Welding
NELSON LOPEZ
10/23/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
NELSON LOPEZ
05/13/2025
Violation issued (FDNY_NOV, closed)
05/06/2025
Violation issued (ECB, open)
Construction
04/24/2025
Violation issued (FDNY_ORDER, closed)
Latest 60 of 112 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION809/01/2026
NYC DEPARTMENT OF PARKS AND RECREATION103/22/2026
DOE 040303/22/2026
DEPARTMENT OF EDUCATION 0103/22/2026
NYC DOE 0103/22/2026
DEPT OF EDUCATION PS 64603/22/2026
DEPARTMENT OF EDUCATION103/22/2026
CENTRAL MECHANICAL SYSTEM103/22/2026
DEPT. OF EDUCATION 0103/22/2026
P.S.64 D.O.E. 0403/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AME SERVICES INC407/22/2026
ROBERT E. IKES, III210/27/2025
SHENOY ENGINEERING, PC210/27/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
H2M ARCHITECTS + ENGINEERS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CHARAN ELEC'L ENTERP'S INElectrical203/22/2026
MARTINEZ, FAUSTOElectrical203/21/2026
MILAD, MONETElectrical203/21/2026
ARMY CONSTRUCTION LLCGeneral Contractor208/16/2026
FRANCIS RICHARDSElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
UNIVERSAL TESTING AND INS400410/27/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsPermit IssuedARMY CONSTRUCTION LLC08/14/2026
DOB NOWConstruction FencePermit IssuedARMY CONSTRUCTION LLC08/14/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/12/2026
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/11/2026
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/11/2026
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/11/2026
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/11/2026
BISPLISSUEDVARSITY PLBG AND HTG INC06/16/2025
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/27/2025
BISPLISSUEDVARSITY PLBG AND HTG INC05/16/2024
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC04/01/2024
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/31/2023
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/31/2023
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/31/2023
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/31/2023
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISOTISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISMHISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
BISEQISSUEDCENTRAL MECHANICAL SYSTEMS INC03/17/2023
+ 12 more permits on file
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
07/19/2026Post-installed Anchors—special
02/25/2026Excavations - Sheeting, Shoring, and BracingNELSON LOPEZspecial
11/25/2025Exterior lighting powerNELSON LOPEZenergy_progress
11/25/2025Lighting controlsNELSON LOPEZenergy_progress
11/25/2025Maintenance informationNELSON LOPEZenergy_progress
11/25/2025Interior lighting powerNELSON LOPEZenergy_progress
11/25/2025HVAC-R and service water heating equipmentNELSON LOPEZenergy_progress
11/25/2025Electrical motors and elevatorsNELSON LOPEZenergy_progress
11/25/2025HVAC-R and service water heating system controlsNELSON LOPEZenergy_progress
11/25/2025Shutoff dampersNELSON LOPEZenergy_progress
11/18/2025Subgrade InspectionsNELSON LOPEZspecial
11/18/2025Subsurface Conditions – Fill Placement & In-Place DensityNELSON LOPEZspecial
11/18/2025Structural Steel - High Strength BoltingNELSON LOPEZspecial
10/24/2025HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
10/24/2025Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
10/24/2025FinalNELSON LOPEZprogress
10/24/2025Energy Code Compliance InspectionsNELSON LOPEZprogress
10/24/2025Mechanical SystemsNELSON LOPEZspecial
10/24/2025Maintenance informationNELSON LOPEZenergy_progress
10/24/2025Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
10/24/2025Post-installed AnchorsNELSON LOPEZspecial
10/24/2025Energy Code Compliance InspectionsNELSON LOPEZprogress
10/24/2025HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
10/24/2025Maintenance informationNELSON LOPEZenergy_progress
10/24/2025Structural Stability – Alterations of existing buildingsNELSON LOPEZspecial
Latest 25 of 46.
▾Documents — 38 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/18/2026Q01307227-S3Request digital key ↗
08/18/2026Q01307227-S2Request digital key ↗
08/18/2026Q01307227-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature7
09/13/2026Q01307227-S3Open ↗
09/13/2026Q01307227-S3Open ↗
09/01/2026Q01307227-S1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/18/2026Q01307227-S3Open ↗
08/18/2026Q01307227-S1Open ↗
08/18/2026Q01307227-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/13/2026Q01307227-S3Open ↗
09/01/2026Q01307227-S1Open ↗
09/01/2026Q01307227-S2Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
08/17/2023421105529Open ↗
▸Safety & Tenant Protection1
▸DOB NOWNYCSCA - Approved Site Safety Plans1
08/15/2026Q01431666-I1Open ↗
▸Approvals, Objections & Sign-offs10
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
08/15/2026Q01431666-I1Open ↗
08/13/2026Q01307227-S1Open ↗
08/13/2026Q01307227-S3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
08/15/2026Q01431666-I1Open ↗
08/13/2026Q01307227-S1Open ↗
08/13/2026Q01307227-S2Open ↗
Showing 3 of 5 on file for this type
▸Other Documents5
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal5
08/15/2026Q01431666-I1Open ↗
08/13/2026Q01307227-I1Open ↗
08/13/2026Q01307227-S2Open ↗
Showing 3 of 5 on file for this type