← Back
BuildNYC
Elevator apt, miscellaneous
Fischer Senior Apartments
97 WEST 169TH STREET · BIN 2130622
💬 Discuss this project
2024Year Built
9Stories
D9Building Class
R7-1Zoning
75,563 sfGross Floor Area
106Units
0 Active Violations
Elevator apt, miscellaneous · Owner of record: Fischer Senior Apartments Housing Develo Pment Fund · 15,121 sf lot · 5 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsSprinkler/standpipe system installation5 filings
RoofTemporary sidewalk shed installation2p · 2 filings
BasementFisher Senior Apartment solar energy system1p · 1 filing · 20 docs
Site & exteriorHVAC-R and service water heating system6 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC Department of Housing Preservation and Development2407/08/2026
Wsfssh603/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Skyline1207/09/2025
De Nardis Engineering405/29/2025
Synergic Design Architects307/29/2024
Tohfaz Uddin PE503/15/2024
Bitopi Consultants112/27/2023
Titan Engineers108/22/2023
AKRF208/18/2023
Hansen Engineering106/21/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM Zoning1603/21/2026
A1 Expediting Service403/21/2026
Milrose Consultants403/21/2026
Spring Scaffolding603/21/2026
AK Consulting Services203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Spring ScaffoldingScaffold1707/08/2026
Procida ConstructionGeneral Contractor807/08/2026
Miller Plumbing & HeatingFire Protection707/08/2026
Northeast Masonry & RestorationScaffold707/08/2026
Total Electric SolutionsGeneral Contractor403/22/2026
Accord PowerGeneral Contractor403/21/2026
Procida ConstructionScaffold307/08/2026
AKRFGeneral Contractor303/22/2026
Miller Plumbing & HeatingPlumbing307/08/2026
Xtreme ElectricGeneral Contractor203/22/2026
Xtreme ElectricElectrical203/22/2026
Xtreme ElectricElectrical203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Concrete Solutions Lab Co53441707/09/2025
Synergic Design8561307/29/2024
Bitopi Consultants7036112/27/2023
Building Lifecycle
All (215)Filed (29)Permit Issued (33)Signed Off (14)Violation (12)Inspection (17)Objection (80)Special Inspection (30)
12/16/2025
Signed off — Alteration
Mechanical work as per plans filed.
X00466957-I1
11/07/2025
Signed off — Alteration
Installation of 32.98 kw solar energy system on roof. No change of occupancy, use or egress.
X01032712-I1
10/06/2025
Signed off — Alteration
Plumbing work as per plans filed.
X00467349-I1
08/19/2025
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
MINA HANNA
08/05/2025
Objection resolved — Addressed
08/05/2025
Objection resolved — Addressed
08/04/2025
Signed off — Alteration
Install temporary standpipe system as per plans filed. No change to use, egress oroccupancy. Filed in conjunction with NB#210182309
X00498184-I1
08/04/2025
Signed off — Alteration
Install combined sprinkler/standpipe system as per plans filed. No change to use, egress oroccupancy. Filed in conjunction with NB# 210182309
X00482209-I1
07/31/2025
Objection raised — Other
07/31/2025
Objection raised — Other
07/14/2025
Signed off — Alteration
X00890384-I1
07/11/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
07/09/2025
Signed off — Alteration
Structural work as per plans filed.
X00463742-I1
07/09/2025
Filed — Alteration
Plumbing work as per plans filed.
X00467349-P5
07/02/2025
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
MINA HANNA
06/16/2025
Special inspection requirement — Heating Systems
MINA HANNA
06/16/2025
Special inspection requirement — Interior lighting power
MINA HANNA
06/16/2025
Special inspection requirement — Final
MINA HANNA
06/16/2025
Special inspection requirement — Mechanical Systems
MINA HANNA
06/16/2025
Special inspection requirement — Lighting in dwelling units
MINA HANNA
06/16/2025
Special inspection requirement — Maintenance information
MINA HANNA
06/16/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MINA HANNA
06/16/2025
Special inspection requirement — Electrical motors and elevators
MINA HANNA
06/16/2025
Special inspection requirement — Energy Code Compliance
MINA HANNA
06/16/2025
Special inspection requirement — Shutoff dampers
MINA HANNA
06/16/2025
Special inspection requirement — Exterior lighting power
MINA HANNA
06/16/2025
Special inspection requirement — Energy Code Compliance Inspections
MINA HANNA
06/16/2025
Special inspection requirement — Metering
MINA HANNA
06/16/2025
Special inspection requirement — HVAC-R and service water heating system controls
MINA HANNA
06/16/2025
Special inspection requirement — Lighting controls
MINA HANNA
06/16/2025
Special inspection requirement — HVAC-R and service water heating equipment
MINA HANNA
06/16/2025
Special inspection requirement — Emergency and Standby Power Systems (Generator)
MINA HANNA
06/13/2025
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLD FOR NEW BUILDING AT 97 WEST 169TH STREET, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
X00981571-I1
06/13/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/12/2025
Filed — Alteration
Mechanical work as per plans filed.
X00466957-P4
06/09/2025
Special inspection requirement — Final
MINA HANNA
06/09/2025
Special inspection requirement — Energy Code Compliance Inspections
MINA HANNA
06/09/2025
Special inspection requirement — Metering
MINA HANNA
06/09/2025
Special inspection requirement — Mechanical Systems
MINA HANNA
06/09/2025
Special inspection requirement — Energy Code Compliance
MINA HANNA
06/09/2025
Special inspection requirement — Maintenance information
MINA HANNA
06/09/2025
Special inspection requirement — Heating Systems
MINA HANNA
06/09/2025
Special inspection requirement — Emergency and Standby Power Systems (Generator)
MINA HANNA
06/09/2025
Special inspection requirement — HVAC-R and service water heating equipment
MINA HANNA
06/09/2025
Special inspection requirement — Lighting controls
MINA HANNA
06/09/2025
Special inspection requirement — Exterior lighting power
MINA HANNA
05/29/2025
Filed — Alteration
Structural work as per plans filed.
X00463742-P4
05/22/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
05/20/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
05/16/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
X00956036-I1
05/16/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
X00956036-S1
05/09/2025
Permit issued — Construction Fence
X00890384-I1-FN
05/02/2025
Filed — Alteration
Plumbing work as per plans filed.
X00467349-P4
04/25/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
04/22/2025
Inspection — Certified StandPipe-Fire Pump (SD)-Fire Pump Test
Certified
View inspection ↗
04/18/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
03/11/2025
Signed off — Alteration
EQUIPMENT USE: SINGLE 7000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
X00985827-I1
03/05/2025
Permit issued — Supported Scaffold
X00981571-I1-SF
02/27/2025
Permit issued — Protection and Mechanical Methods
X00985827-I1-PMM
02/27/2025
Permit issued — Sidewalk Shed
X00956036-I1-SH
Latest 60 of 215 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offProcida Construction05/09/2025
DOB NOWSupported ScaffoldSigned-offNortheast Masonry & Restoration03/05/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding02/27/2025
DOB NOWSidewalk ShedSigned-offSpring Scaffolding02/27/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding02/27/2025
DOB NOWMechanical SystemsSigned-offProcida Construction02/10/2025
DOB NOWStructuralSigned-offProcida Construction02/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding01/06/2025
DOB NOWSidewalk ShedSigned-offSpring Scaffolding11/01/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding11/01/2024
DOB NOWStandpipeSigned-offMiller Plumbing & Heating09/04/2024
DOB NOWSprinklersSigned-offMiller Plumbing & Heating09/04/2024
DOB NOWPlumbingSigned-offMiller Plumbing & Heating09/03/2024
DOB NOWStandpipeSigned-offMiller Plumbing & Heating09/03/2024
DOB NOWSolarSigned-offAccord Power09/03/2024
DOB NOWSupported ScaffoldSigned-offNortheast Masonry & Restoration08/01/2024
DOB NOWSolarSigned-offAccord Power07/31/2024
DOB NOWStandpipeSigned-offMiller Plumbing & Heating07/01/2024
DOB NOWConstruction FenceSigned-offProcida Construction05/24/2024
DOB NOWMechanical SystemsSigned-offProcida Construction02/15/2024
DOB NOWStructuralSigned-offProcida Construction02/08/2024
DOB NOWSprinklersSigned-offMiller Plumbing & Heating01/22/2024
DOB NOWStandpipeSigned-offMiller Plumbing & Heating01/22/2024
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding01/05/2024
DOB NOWSupported ScaffoldSigned-offNortheast Masonry & Restoration12/28/2023
DOB NOWProtection and Mechanical MethodsSigned-offSpring Scaffolding11/03/2023
DOB NOWSidewalk ShedSigned-offSpring Scaffolding11/03/2023
DOB NOWStructuralSigned-offProcida Construction10/02/2023
DOB NOWEarth WorkSigned-offProcida Construction09/19/2023
DOB NOWPlumbingSigned-offMiller Plumbing & Heating09/08/2023
DOB NOWPlumbingSigned-offMiller Plumbing & Heating08/22/2023
DOB NOWConstruction FenceSigned-offProcida Construction06/23/2023
DOB NOWStandpipeSigned-offMiller Plumbing & Heating06/13/2023
BIS—RE-ISSUEDProcida Construction04/25/2025
BIS—ISSUEDProcida Construction04/25/2025
BIS—ISSUEDProcida Construction04/30/2024
BIS—ISSUEDProcida Construction04/30/2024
BIS—ISSUEDProcida Construction07/19/2023
BIS—ISSUEDProcida Construction06/27/2023
9 projects · most recent 05/13/2026
General Wiring
FiledStatusContractorScope
05/13/2026CompleteJames Lewis Elect'lGeneral Wiring
11/03/2025CompleteXtreme ElectricGeneral Wiring
10/01/2025CompleteXtreme ElectricGeneral Wiring
08/14/2025CompleteTotal Electric SolutionsGeneral Wiring
07/30/2025CompleteXtreme ElectricGeneral Wiring
07/29/2025CompletePower Surge Electric115 meters, 1 new_meters
11/16/2023CompleteXtreme Electric—
10/30/2023CompleteTop Shelf Electric—
06/21/2023CompleteXtreme Electric1 meters, 1 new_meters
▾Field Inspections (DOB CAP) — 17
DateTypeResultReport
07/11/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/22/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
05/20/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/25/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
04/22/2025Certified StandPipe-Fire Pump (SD)-Fire Pump TestCertifiedView ↗
04/18/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
05/24/2024Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
05/24/2024Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
03/14/2024Pass-Final PL - UndergroundPassView ↗
03/08/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
11/13/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/13/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/06/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/06/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/20/2023Pass-Final PL - UndergroundPassView ↗
10/12/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 114
DateRequirementInspectorRole
08/19/2025Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesMINA HANNAspecial
07/02/2025Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesMINA HANNAspecial
06/16/2025Mechanical SystemsMINA HANNAspecial
06/16/2025Energy Code Compliance InspectionsMINA HANNAprogress
06/16/2025Energy Code ComplianceMINA HANNAprogress
06/16/2025FinalMINA HANNAprogress
06/16/2025Shutoff dampersMINA HANNAenergy_progress
06/16/2025HVAC-R and service water heating system controlsMINA HANNAenergy_progress
06/16/2025HVAC-R and service water piping design and insulationMINA HANNAenergy_progress
06/16/2025Electrical motors and elevatorsMINA HANNAenergy_progress
06/16/2025Interior lighting powerMINA HANNAenergy_progress
06/16/2025MeteringMINA HANNAenergy_progress
06/16/2025Exterior lighting powerMINA HANNAenergy_progress
06/16/2025Lighting in dwelling unitsMINA HANNAenergy_progress
06/16/2025HVAC-R and service water heating equipmentMINA HANNAenergy_progress
06/16/2025Lighting controlsMINA HANNAenergy_progress
06/16/2025Emergency and Standby Power Systems (Generator)MINA HANNAspecial
06/16/2025Maintenance informationMINA HANNAenergy_progress
06/16/2025Heating SystemsMINA HANNAspecial
06/09/2025Maintenance informationMINA HANNAenergy_progress
06/09/2025HVAC-R and service water heating system controlsMINA HANNAenergy_progress
06/09/2025Electrical motors and elevatorsMINA HANNAenergy_progress
06/09/2025Shutoff dampersMINA HANNAenergy_progress
06/09/2025HVAC-R and service water piping design and insulationMINA HANNAenergy_progress
06/09/2025Interior lighting powerMINA HANNAenergy_progress
Latest 25 of 114.
▾Documents — 381 on file (BIS + DOB NOW)
▸Plans & Drawings29
▸DOB NOWPlans/Sketch16
08/23/2026X00890384-I1Request digital key ↗
08/22/2026X00906554-S1Request digital key ↗
08/22/2026X00906554-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Plumbing5
08/22/2026X00467349-I1Request digital key ↗
08/22/2026X00467349-P4Request digital key ↗
08/22/2026X00467349-P3Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems4
08/21/2026X00466957-I1Request digital key ↗
08/21/2026X00466957-P4Request digital key ↗
08/21/2026X00466957-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Structural4
08/22/2026X00463742-P1Request digital key ↗
08/22/2026X00463742-P4Request digital key ↗
08/15/2026X00463742-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits44
▸BISPLAN / WORK APPROVAL APPLICATION32
08/28/2025210182309Open ↗
08/21/2025210182309Open ↗
05/22/2025210182309Open ↗
Showing 3 of 32 on file for this type
▸BISWORK PERMIT APPLICATION9
05/01/2025210182309Open ↗
05/01/2025210182309Open ↗
05/01/2025210182309Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
01/10/2025210182309Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
04/13/2021240303186Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
01/14/2025210182309Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING DIAGRAM2
06/24/2024210182309Open ↗
11/10/2021210182309Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
04/09/2021210182309Open ↗
▸BISAPPROVED ACPE AI1-ZONING EXHIBIT DEFERRAL1
10/08/2021210182309Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
09/24/2021210182309Open ↗
▸Seals & Professional Certifications145
▸DOB NOWProgress Inspector Seal & Signature66
10/03/2026X00913285-I1Open ↗
09/18/2026X00906554-I1Open ↗
09/02/2026X01032712-I1Open ↗
Showing 3 of 66 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature48
10/04/2026X00467349-I1Open ↗
10/03/2026X00913285-I1Open ↗
10/03/2026X00913285-I1Open ↗
Showing 3 of 48 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature29
08/23/2026X00890384-I1Open ↗
08/22/2026X00913285-I1Open ↗
08/22/2026X00482209-P1Open ↗
Showing 3 of 29 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
04/13/2021240303186Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/13/2021240303186Open ↗
▸Trade Schedules & Equipment7
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)2
10/21/2025210182309Open ↗
10/06/2021210182309Open ↗
▸DOB NOWFDNY: Letter of No Objection2
08/13/2026X00482209-I1Open ↗
08/13/2026X00482209-P1Open ↗
▸BISDEP STORMWATER SEWER CERTIFICATION (HCP/SCP)1
05/12/2021210182309Open ↗
▸BISSTANDPIPE ALARM DRAWINGS & AI1 (OR AI1 PROOF)1
06/27/2023210182309Open ↗
▸BISSTANDPIPE WORK PERMIT1
06/27/2023210182309Open ↗
▸Safety & Tenant Protection8
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN2
08/11/2023240303186Open ↗
06/27/2023210182309Open ↗
▸BISSTREET TREE CHECKLIST2
10/08/2021210182309Open ↗
07/13/2021240303186Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING2
03/20/2024210182309Open ↗
06/27/2023210182309Open ↗
▸BISBPP: STREET TREES SITE PLAN1
07/13/2021240303186Open ↗
▸BISSTREET TREE SIGNOFF1
04/23/2025210182309Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/24/2021210182309Open ↗
05/12/2021210182309Open ↗
05/12/2021210182309Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
07/02/2025210182309Open ↗
▸BISFENESTRATION AREAS1
07/02/2025210182309Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
08/08/2025210182309Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
07/02/2025210182309Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
08/08/2025210182309Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/02/2025210182309Open ↗
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION1
09/10/2025210182309Open ↗
▸BISFENESTRATION AIR LEAKAGE1
07/02/2025210182309Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00466957-I1Open ↗
▸Inspections & Test Reports28
▸BISTECHNICAL REPORT: RESPONSIBILITY13
04/30/2025210182309Open ↗
08/14/2024210182309Open ↗
08/05/2024210182309Open ↗
Showing 3 of 13 on file for this type
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS2
03/20/2024210182309Open ↗
06/27/2023210182309Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
06/26/2024240303186Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
08/08/2025210182309Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
07/02/2025210182309Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
03/12/2024210182309Open ↗
▸BISSPRAYED FIRE-RESISTANT MATERIALS1
08/15/2024210182309Open ↗
▸BISWALL PANELS, CURTAIN WALLS, AND VENEERS1
08/15/2024210182309Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
04/30/2025210182309Open ↗
▸BISSOIL REPORT1
05/12/2021210182309Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
06/27/2023210182309Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
05/12/2021210182309Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
06/27/2023210182309Open ↗
▸BISSUBSURFACE / SOILS-FILL PLACEMENT IN-PLACE DENSITY1
04/30/2025210182309Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
03/12/2024210182309Open ↗
▸Approvals, Objections & Sign-offs57
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter25
08/23/2026X00890384-I1Open ↗
08/22/2026X00467349-P4Open ↗
08/22/2026X00467349-P3Open ↗
Showing 3 of 25 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION16
07/14/2023210182309Open ↗
07/14/2023210182309Open ↗
06/27/2023210182309Open ↗
Showing 3 of 16 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE13
08/28/2025210182309Open ↗
08/21/2025210182309Open ↗
05/22/2025210182309Open ↗
Showing 3 of 13 on file for this type
▸BISDESIGN COMM. SIGNOFF: CITY-OWNED PROPERTY (EXTERIOR WORK)1
08/11/2023240303186Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
08/11/2023240303186Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026X01032712-I1Open ↗
▸Cost, Insurance & Ownership4
▸BISPROJECT-SPECIFIC GL INSURANCE3
05/01/2025210182309Open ↗
05/02/2024210182309Open ↗
06/27/2023210182309Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
06/27/2023210182309Open ↗
▸Filing & Intake Forms31
▸BISADDITIONAL INFORMATION26
06/23/2025210182309Open ↗
01/10/2025210182309Open ↗
08/14/2024210182309Open ↗
Showing 3 of 26 on file for this type
▸BISBOROUGH INTAKE FORM2
05/01/2025210182309Open ↗
06/08/2021210182309Open ↗
▸BISEFILING COVER SHEET2
04/28/2021210182309Open ↗
04/28/2021210182309Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/13/2021240303186Open ↗
▸Other Documents8
▸BISPLOT DIAGRAM2
09/24/2021210182309Open ↗
06/08/2021210182309Open ↗
▸BISAI APPROVED BY COMMISSIONER PAVAN - COURT COMPLIANCE DATED 05-20-20211
10/06/2021210182309Open ↗
▸BISVESTIBULES1
07/02/2025210182309Open ↗
▸BISPRE-CONSTRUCTION SURVEY1
06/27/2023210182309Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
02/11/2025210182309Open ↗
▸BISPRELIMINARY1
02/11/2025210182309Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X00906554-I1Open ↗