| Owner | Filings | Most Recent |
|---|---|---|
| WP CONTRACTING | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RAAD | 10 | 01/12/2026 |
| WORLD DESIGN ARCHITECTURE,PLLC | 1 | 07/22/2024 |
| WARREN MEISTER ARCHITECTS, PC | 4 | 05/20/2024 |
| BGM ENGINEERING | 3 | 12/01/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDIA BUILDING SOLUTION | 17 | 03/21/2026 |
| KC EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WP CONTRACTING INC | General Contractor | 37 | 07/08/2026 |
| J SYNERGY GREEN INC | General Contractor | 2 | 03/21/2026 |
| SIGNORE & SONS PLBG CORP | Plumbing | 2 | 07/08/2026 |
| DEPENDABLE MECHANICAL COR | Fire Protection | 1 | 06/28/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| WATER WORKS PIPING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STRUCTURAL ENGINEERING & | 5699 | 15 | 01/12/2026 |
| WORLD DESIGN ARCHITECTURE | 9323 | 1 | 07/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 09/10/2025 |
| DOB NOW | Sprinklers | Permit Issued | DEPENDABLE MECHANICAL COR | 09/08/2025 |
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 08/19/2025 |
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 08/12/2025 |
| DOB NOW | Mechanical Systems | Signed-off | WP CONTRACTING INC | 08/12/2025 |
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 08/08/2025 |
| DOB NOW | Solar | Signed-off | J SYNERGY GREEN | 06/27/2025 |
| DOB NOW | Construction Fence | Signed-off | WP CONTRACTING INC | 05/29/2025 |
| DOB NOW | Plumbing | Permit Issued | SUPERIOR PIPING&MECH CORP | 11/20/2024 |
| DOB NOW | Earth Work | Signed-off | WP CONTRACTING INC | 10/22/2024 |
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 10/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | WP CONTRACTING INC | 08/23/2024 |
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 08/23/2024 |
| DOB NOW | Construction Fence | Signed-off | WP CONTRACTING INC | 05/21/2024 |
| DOB NOW | Plumbing | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 03/06/2024 |
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 07/26/2023 |
| DOB NOW | Earth Work | Signed-off | WP CONTRACTING INC | 07/26/2023 |
| DOB NOW | Support of Excavation | Signed-off | WP CONTRACTING INC | 07/26/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WP CONTRACTING INC | 07/26/2023 |
| DOB NOW | Structural | Signed-off | WP CONTRACTING INC | 07/26/2023 |
| DOB NOW | Support of Excavation | Signed-off | WP CONTRACTING INC | 05/05/2023 |
| DOB NOW | Foundation | Signed-off | WP CONTRACTING INC | 05/05/2023 |
| DOB NOW | Structural | Signed-off | WP CONTRACTING INC | 02/24/2023 |
| DOB NOW | Construction Fence | Permit Issued | WP CONTRACTING INC | 02/24/2023 |
| DOB NOW | General Construction | Permit Issued | WP CONTRACTING INC | 02/21/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WP CONTRACTING INC | 02/21/2023 |
| DOB NOW | Construction Fence | Permit Issued | WP CONTRACTING INC | 12/30/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/08/2025 | Signed-off | WP CONTRACTING INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM60NAM2 60,000 BTU · Vrf Outdoor ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/12/2026 | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 159 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/12/2026 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2024 | Complete | GREEN LIGHT ELECL & MECH | — |
| 01/25/2024 | Permit Issued | TESTA ELECTRIC CO., INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2024 | Permit Issued | WP CONTRACTING INC | Fence |
| 09/22/2022 | Permit Issued | WP CONTRACTING INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/10/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 01/30/2026 | Fail-Final SP - Up to 3 Requested Floors | Fail | View ↗ |
| 01/22/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 06/10/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/22/2024 | Pass-Final House Connection | Pass | View ↗ |
| 10/02/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/24/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/13/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/14/2026 | Sprinkler Systems | ROBERT SIQECA | special |
| 01/05/2026 | Sprinkler Systems | ROBERT SIQECA | special |
| 12/11/2025 | HVAC-R and service water piping design and insulation | NICHOLAS AZADIAN | energy_progress |
| 12/11/2025 | Mechanical Systems | ROBERT SIQECA | special |
| 12/11/2025 | Final | ROBERT SIQECA | progress |
| 12/11/2025 | Energy Code Compliance Inspections | ROBERT SIQECA | progress |
| 12/11/2025 | HVAC-R and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 12/11/2025 | HVAC-R and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 12/08/2025 | Mechanical Systems | ROBERT SIQECA | special |
| 12/08/2025 | Energy Code Compliance Inspections | ROBERT SIQECA | progress |
| 12/08/2025 | Final | ROBERT SIQECA | progress |
| 12/08/2025 | HVAC-R and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 12/08/2025 | HVAC-R and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 12/08/2025 | HVAC-R and service water piping design and insulation | NICHOLAS AZADIAN | energy_progress |
| 11/28/2025 | Energy Code Compliance Inspections | ROBERT SIQECA | progress |
| 11/28/2025 | HVAC-R and service water heating equipment | ROBERT SIQECA | energy_progress |
| 11/28/2025 | Fire-Resistant Penetrations and Joints | ROBERT SIQECA | special |
| 11/28/2025 | HVAC-R and service water piping design and insulation | ROBERT SIQECA | energy_progress |
| 11/28/2025 | HVAC-R and service water heating system controls | ROBERT SIQECA | energy_progress |
| 11/25/2025 | HVAC-R and service water heating equipment | ROBERT SIQECA | energy_progress |
| 11/25/2025 | HVAC-R and service water piping design and insulation | ROBERT SIQECA | energy_progress |
| 11/25/2025 | HVAC-R and service water heating system controls | ROBERT SIQECA | energy_progress |
| 11/25/2025 | Energy Code Compliance Inspections | ROBERT SIQECA | progress |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | ROBERT SIQECA | special |
| 07/16/2024 | HVAC-R and service water heating system controls | ROBERT SIQECA | energy_progress |