← Back
Public elementary, junior or senior high
P.S. 127 Aerospace Science Magnet School
98-01 25 AVENUE · BIN 4024487
💬 Discuss this project
1937Year Built
4Stories
W1Building Class
PARKZoning
129,600 sfGross Floor Area
0Units
LL97 Covered5 Open Violations 0 unresolved · 5 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF PARKS AND RECREATION · 227,750 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Basement2p · 1 filing · 20 docs
Sub-Basement8p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY1707/08/2026
NYC DEPARTMENT OF PARKS AND RECREATION103/22/2026
DOE PS 127 040103/22/2026
PS 127 DOE1803/22/2026
DEPARTMENT OF EDUCATION 0103/22/2026
DOE P.S. 127503/22/2026
DEPT. OF EDUCATION 0203/22/2026
DEPT OF EDUCATION P.S.127103/22/2026
DEPARTMENT OF EDUCATION203/22/2026
DEPT OF EDU 1103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYC DEPT OF PARKS & RECREATION108/24/2026
STV INCORPORATED304/14/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STV603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARORA CONSTRUCTION INCGeneral Contractor407/08/2026
BOYD MECHANICAL LLCPlumbing307/08/2026
CHARAN ELEC'L ENTERP'S INElectrical103/22/2026
HEXAGON CONST & ELECL GRPElectrical103/22/2026
YOLAND CONSTRUCTION & METGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
UNIVERSAL TESTING AND INS400304/14/2025
Building Lifecycle
All (95)Filed (4)Permit Issued (6)Violation (60)Special Inspection (25)
08/24/2026
Filed — Alteration
REPLACE EXISTING SITE STORMWATER DRAINAGE SYSTEM ANDINSTALL NEW DRAINAGE SYSTEM FOR ATHLETIC FIELD, BUT NOT LIMITED TO, NEWCATCH BASINS, MANHOLES, DRAINAGE PIPES, AND UNDERGROUND STORMWATER GALLERY SYSTEM.
Q01445968-I1
08/21/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
08/21/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
04/16/2026
Permit issued — Plumbing
Q00612517-I1-PL
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
09/22/2025
Violation issued (FDNY_NOV, closed)
09/08/2025
Violation issued (FDNY_ORDER, closed)
09/08/2025
Violation issued (FDNY_ORDER, closed)
09/08/2025
Violation issued (FDNY_ORDER, closed)
09/08/2025
Violation issued (FDNY_ORDER, closed)
04/21/2025
Violation issued (ECB, closed)
Construction
04/21/2025
Violation issued (ECB, open)
Construction
04/21/2025
Violation issued (ECB, open)
Construction
04/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
04/15/2025
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
04/15/2025
Special inspection requirement — Final
NELSON LOPEZ
04/15/2025
Special inspection requirement — Chimneys and vents
NELSON LOPEZ
04/15/2025
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
04/15/2025
Special inspection requirement — Metering
NELSON LOPEZ
04/15/2025
Special inspection requirement — Electrical motors and elevators
NELSON LOPEZ
04/15/2025
Special inspection requirement — Shutoff dampers
NELSON LOPEZ
04/14/2025
Filed — Alteration
Q127_Remove and replace motorized damper, fire damper, and concrete pad. Provide new stainless steel piping for new gas-fired HWH, barometric damper, vent hood, drain pipe and p-trap.
Q00612517-P1
10/29/2024
Violation issued (FDNY_ORDER, closed)
08/29/2024
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
08/29/2024
Special inspection requirement — Chimneys and vents
NELSON LOPEZ
08/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
08/29/2024
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
08/29/2024
Special inspection requirement — Final
NELSON LOPEZ
08/29/2024
Special inspection requirement — Shutoff dampers
NELSON LOPEZ
08/29/2024
Special inspection requirement — Metering
NELSON LOPEZ
08/29/2024
Special inspection requirement — Electrical motors and elevators
NELSON LOPEZ
04/30/2024
Violation issued (ECB, open)
Construction
04/30/2024
Violation issued (ECB, open)
Construction
04/30/2024
Violation issued (ECB, open)
Construction
04/03/2024
Violation issued (ECB, closed)
Construction
02/01/2024
Permit issued — Mechanical Systems
Q00612517-S1-MS
12/27/2023
Permit issued — Mechanical Systems
Q00612517-S1-GC
11/03/2023
Permit issued — Plumbing
Q00612517-I1-PL
06/26/2023
Permit issued — Plumbing
Q00612517-I1-PL
05/24/2023
Permit issued — Mechanical Systems
Q00612517-S1-GC
04/27/2023
Violation issued (FDNY_ORDER, closed)
04/29/2022
Violation issued (ECB, closed)
Construction
10/21/2021
Filed — Alteration
Q127_Remove and replace motorized damper, fire damper, and concrete pad. Provide new stainless steel piping for new gas-fired HWH, barometric damper, vent hood, drain pipe and p-trap.
Q00612517-S1
10/19/2021
Filed — Alteration
Q127_Remove and replace motorized damper, fire damper, and concrete pad. Provide new stainless steel piping for new gas-fired HWH, barometric damper, vent hood, drain pipe and p-trap.
Q00612517-I1
10/19/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
10/19/2021
Special inspection requirement — HVAC-R and service water heating system controls
NELSON LOPEZ
10/19/2021
Special inspection requirement — Maintenance information
NELSON LOPEZ
10/19/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NELSON LOPEZ
10/19/2021
Special inspection requirement — HVAC-R and service water heating equipment
NELSON LOPEZ
10/19/2021
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
10/19/2021
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
10/10/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/27/2021
Violation issued (ECB, closed)
Boilers
05/27/2021
Violation issued (ECB, closed)
Boilers
04/06/2021
Violation issued (ECB, closed)
Construction
Latest 60 of 95 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedBOYD MECHANICAL LLC04/16/2026
DOB NOWMechanical SystemsPermit IssuedYOLAND CONSTRUCTION & MET02/01/2024
DOB NOWMechanical SystemsPermit IssuedARORA CONSTRUCTION INC12/27/2023
DOB NOWPlumbingPermit IssuedBOYD MECHANICAL LLC11/03/2023
DOB NOWPlumbingPermit IssuedBOYD MECHANICAL LLC06/26/2023
DOB NOWMechanical SystemsPermit IssuedARORA CONSTRUCTION INC05/24/2023
BISOTISSUEDPRO-METAL CONSTRUCTION05/10/2017
BISOTISSUEDPRO-METAL CONSTRUCTION05/05/2017
BISOTISSUEDPRO-METAL CONSTRUCTION05/09/2016
BISEQISSUEDPRO-METAL CONSTRUCTION05/09/2016
BISOTISSUEDPRO-METAL CONSTRUCTION05/02/2016
BISEQISSUEDPRO-METAL CONSTRUCTION05/02/2016
BISEQISSUEDROMA SCAFFOLDING INC04/28/2016
BISEQISSUEDROMA SCAFFOLDING INC04/25/2016
BISPLISSUEDVARSITY PLBG AND HTG INC04/08/2016
BISMHISSUEDCHAPMAN & EVANS INC12/16/2015
BISOTISSUEDPRO-METAL CONSTRUCTION05/06/2015
BISEQISSUEDPRO-METAL CONSTRUCTION05/06/2015
BISPLISSUEDVARSITY PLBG AND HTG INC04/07/2015
BISMHISSUEDCHAPMAN & EVANS INC04/07/2015
BISOTISSUEDPRO-METAL CONSTRUCTION04/07/2015
BISEQISSUEDROMA SCAFFOLDING INC04/03/2015
BISEQISSUEDROMA SCAFFOLDING INC04/03/2015
BISEQISSUEDPRO-METAL CONSTRUCTION03/24/2015
BISOTISSUEDEMPIRE CONTROL ABATEMENT08/27/2012
BISOTISSUEDCARNAK CONSTRUCTION INC09/01/2011
BISOTISSUEDCARNAK CONSTRUCTION INC08/31/2011
BISOTISSUEDEMPIRE CONTROL ABATEMENT06/28/2011
BISPLISSUEDW D F INC06/01/2011
BISOTISSUEDWDF INC06/01/2011
BISPLISSUEDW D F INC06/23/2010
BISOTISSUEDWDF INC06/23/2010
BISOTRE-ISSUEDCARNAK CONSTRUCTION INC06/18/2010
BISOTISSUEDWDF INC07/02/2009
BISPLISSUEDABSOLUTE MECH CO. INC03/31/2009
BISEQISSUEDPRESTIGE CONSTRUCTION SERVICES10/06/2008
BISEQISSUEDPRESTIGE CONSTRUCTION SERVICES10/06/2008
BISMHISSUEDWDF INCORPORATED07/31/2008
BISPLISSUEDWDF INCORPORATED08/06/2007
BISOTISSUEDWDF INCORPORATED08/06/2007
+ 16 more permits on file
2 projects · most recent 08/24/2026
Storm Gas Water/Sanitary
FiledStatusContractorScope
08/24/2026——Storm
04/14/2025Permit IssuedBOYD MECHANICAL LLCGas, Water/Sanitary
12 projects · most recent 08/17/2026
General Wiring
FiledStatusContractorScope
08/17/2026CompleteGEMINI ELECTRIC CO., INC.—
05/30/2025CompleteANCO ELECTL CONTCTNG INC—
03/13/2025CompleteADVANCE LIGHT & PWR ELECTGeneral Wiring
12/05/2024CompleteCHARAN ELEC'L ENTERP'S IN—
08/23/2023CompleteCHARAN ELEC'L ENTERP'S IN—
07/25/2023Permit IssuedDYNAMO ELECTRICAL CORPGeneral Wiring
07/05/2023CompleteGEMINI ELECTRIC CO., INC.—
08/10/2022CompleteCHARAN ELEC'L ENTERP'S IN—
08/30/2021CompleteCHARAN ELEC'L ENTERP'S IN—
02/05/2020CompleteHEXAGON CONST & ELECL GRPGeneral Wiring
02/18/2019CompleteCHARAN ELEC'L ENTERP'S INGeneral Wiring
12/03/2018CompleteCHARAN ELEC'L ENTERP'S IN—
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
08/21/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities—special
08/21/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
04/15/2025Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
04/15/2025Energy Code Compliance InspectionsNELSON LOPEZprogress
04/15/2025FinalNELSON LOPEZprogress
04/15/2025Chimneys and ventsNELSON LOPEZspecial
04/15/2025Mechanical SystemsNELSON LOPEZspecial
04/15/2025MeteringNELSON LOPEZenergy_progress
04/15/2025Electrical motors and elevatorsNELSON LOPEZenergy_progress
04/15/2025Shutoff dampersNELSON LOPEZenergy_progress
08/29/2024Energy Code Compliance InspectionsNELSON LOPEZprogress
08/29/2024Chimneys and ventsNELSON LOPEZspecial
08/29/2024Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
08/29/2024Mechanical SystemsNELSON LOPEZspecial
08/29/2024FinalNELSON LOPEZprogress
08/29/2024Shutoff dampersNELSON LOPEZenergy_progress
08/29/2024MeteringNELSON LOPEZenergy_progress
08/29/2024Electrical motors and elevatorsNELSON LOPEZenergy_progress
10/19/2021Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
10/19/2021HVAC-R and service water heating system controlsNELSON LOPEZenergy_progress
10/19/2021Maintenance informationNELSON LOPEZenergy_progress
10/19/2021HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
10/19/2021HVAC-R and service water heating equipmentNELSON LOPEZenergy_progress
10/19/2021Energy Code Compliance InspectionsNELSON LOPEZprogress
10/19/2021Post-installed AnchorsNELSON LOPEZspecial
▾Documents — 64 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/25/2026Q01445968-I1Request digital key ↗
08/20/2026Q00612517-P1Request digital key ↗
08/20/2026Q00612517-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
05/24/2018421315026Open ↗
01/03/2018421315026Open ↗
▸BISWORK PERMIT APPLICATION1
07/18/2019421315026Open ↗
▸Seals & Professional Certifications25
▸DOB NOWProgress Inspector Seal & Signature9
08/28/2026Q00612517-I1Open ↗
08/28/2026Q00612517-I1Open ↗
08/28/2026Q00612517-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
03/23/2020421315026Open ↗
02/26/2020421315026Open ↗
02/19/2020421315026Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026Q00612517-I1Open ↗
08/28/2026Q00612517-I1Open ↗
08/26/2026Q00612517-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/25/2026Q01445968-I1Open ↗
08/13/2026Q00612517-I1Open ↗
08/13/2026Q00612517-S1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/13/2026Q00612517-S1Open ↗
08/13/2026Q00612517-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/25/2018421315026Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
02/26/2020421315026Open ↗
04/10/2019421315026Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
04/10/2019421315026Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
05/25/2018421315026Open ↗
▸Approvals, Objections & Sign-offs15
▸BISLETTERS - SUPPORTING DOCUMENTATION4
05/25/2018421315026Open ↗
05/25/2018421315026Open ↗
05/25/2018421315026Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/25/2026Q01445968-I1Open ↗
08/13/2026Q00612517-I1Open ↗
08/13/2026Q00612517-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)4
08/25/2026Q01445968-I1Open ↗
08/13/2026Q00612517-I1Open ↗
08/13/2026Q00612517-S1Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
03/27/2020421315026Open ↗
03/23/2020421315026Open ↗
03/13/2020421315026Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
03/27/2020421315026Open ↗
03/13/2020421315026Open ↗
01/03/2018421315026Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
01/03/2018421315026Open ↗
▸BISBOROUGH INTAKE FORM1
03/13/2020421315026Open ↗
▸Other Documents5
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal3
08/13/2026Q00612517-P1Open ↗
08/13/2026Q00612517-I1Open ↗
08/13/2026Q00612517-S1Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
05/25/2018421315026Open ↗
01/03/2018421315026Open ↗