| Owner | Filings | Most Recent |
|---|---|---|
| ROCKLYN ASSET | 37 | 07/08/2026 |
| RESURRECTION ASCENSION CHURCH | 5 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MADRIAGA ENGINEERING P.C. | 3 | 01/10/2024 |
| DVL CONSULTING ENGINEERS, INC | 6 | 05/09/2023 |
| 360 ENGINEERING P.C. | 1 | 08/10/2022 |
| SALAM & GIACALONE ARCHITECTS PC | 2 | 07/21/2022 |
| NEW YORK ENGINEERING ASSOC., P.C. | 1 | 06/02/2022 |
| SYED ENGINEERING, P.C. | 1 | 04/27/2022 |
| ANDREW ROBERT LEVENBAUM P.E. | 1 | 02/15/2022 |
| BRAD E. COHEN, PE | 1 | 10/06/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| PRECISION 3SIXTY NYC, INC | 16 | 03/21/2026 |
| ARCHETYPE CONSULTANTS | 2 | 03/21/2026 |
| JMV ASSOCIATES LLC | 1 | 03/21/2026 |
| NEW YORK ENGINEERING | 1 | 03/21/2026 |
| TAREK M ZEID P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CONSOLIDATED SCAFFOLDING | General Contractor | 12 | 03/21/2026 |
| KG CONSTRUCTION SERVICES | General Contractor | 5 | 07/08/2026 |
| JOY GREE LLC | General Contractor | 3 | 03/21/2026 |
| PARISH PROPERTY MANAGEMENT | General Contractor | 3 | 07/08/2026 |
| AMERICAN VENTILATION SERV | General Contractor | 2 | 03/21/2026 |
| MAR-SAL PLBG & HTG, INC | Plumbing | 1 | 07/08/2026 |
| FSM ELECTRICAL CORPORATIO | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 3 | 01/10/2024 |
| UNIVERSAL TESTING AND INS | 400 | 7 | 05/09/2023 |
| NEW YORK ENGINEERING ASSO | 851 | 1 | 06/02/2022 |
| C.M. TESTING LABORATORY, | 1352 | 1 | 02/15/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | JOY GREE LLC | 11/03/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 05/05/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 04/05/2023 |
| DOB NOW | Plumbing | Signed-off | MAR-SAL PLBG & HTG, INC | 10/07/2022 |
| DOB NOW | General Construction | Signed-off | PARISH PROPERTY MANAGEMEN | 09/29/2022 |
| DOB NOW | Mechanical Systems | Signed-off | STALCO | 09/08/2022 |
| DOB NOW | Construction Fence | Signed-off | STALCO | 08/11/2022 |
| DOB NOW | General Construction | Signed-off | STALCO | 08/10/2022 |
| DOB NOW | General Construction | Signed-off | AMERICAN VENTILATION SERV | 06/07/2022 |
| DOB NOW | General Construction | Signed-off | PARISH PROPERTY MANAGEMEN | 05/04/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 04/27/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 04/27/2022 |
| DOB NOW | Boiler Equipment | Signed-off | RANSHAW PLBG & HTG LLC | 10/22/2020 |
| BIS | — | ISSUED | OUR LADY OF ANGELUS | 06/08/2020 |
| BIS | FB | ISSUED | S.J. FUEL CO., INC | 09/29/2006 |
| BIS | BL | ISSUED | NEAL M. RUDIKOFF | 08/18/1995 |
| BIS | PL | ISSUED | AL HAAG & SON PLBG & HTG | 08/18/1995 |
| BIS | PL | ISSUED | M.VASCELLARO INC | 10/07/1993 |
| BIS | OT | ISSUED | FRANK CORIGLIANO CONTRACTOR, INC | 10/07/1993 |
| BIS | — | ISSUED | V & A ELECTRIC | 09/06/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/19/2022 | Permit Issued | PJZ MAINTENANCE CORP. | — |
| 07/05/2022 | Complete | RODEL ELEC'L CONTR'S, IN | General Wiring |
| 04/24/2022 | Permit Issued | V. VASS ELECTRIC CORP | — |
| 09/09/2020 | Complete | FSM ELECTRICAL CORPORATIO | General Wiring |
| 09/09/2020 | Complete | FSM ELECTRICAL CORPORATIO | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/21/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/24/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/23/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/04/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 02/03/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/05/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/12/2024 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 01/12/2024 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 01/12/2024 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 01/12/2024 | Final | Robert Truskosky | progress |
| 01/12/2024 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 01/12/2024 | Mechanical Systems | Robert Truskosky | special |
| 01/12/2024 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 01/07/2024 | Mechanical Systems | Robert Truskosky | special |
| 01/07/2024 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 01/07/2024 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 01/07/2024 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 01/07/2024 | Final | Robert Truskosky | progress |
| 01/07/2024 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 01/07/2024 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 12/27/2023 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 12/27/2023 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 12/27/2023 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 12/27/2023 | Mechanical Systems | Robert Truskosky | special |
| 12/27/2023 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 12/27/2023 | Final | Robert Truskosky | progress |
| 12/27/2023 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 05/09/2023 | Lighting controls | NELSON LOPEZ | energy_progress |
| 05/09/2023 | HVAC-R and service water heating system controls | NELSON LOPEZ | energy_progress |
| 05/09/2023 | HVAC-R and service water piping design and insulation | NELSON LOPEZ | energy_progress |
| 05/09/2023 | HVAC-R and service water heating equipment | NELSON LOPEZ | energy_progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Our Lady Of The Angelus | Education | Cellar, Floors 1, 2 | Project Q00644834 |