| Owner | Filings | Most Recent |
|---|---|---|
| LW CONTRACTING | 6 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 3 | 08/15/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J. CALIENDO R.A., P.C. | 3 | 03/21/2026 |
| GERALD J CALIENDO R A P C | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LW CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| MAXWELL PLUMB MECH. CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOYUN KIM; RA | 7415 | 3 | 08/15/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | MAXWELL PLUMB MECH. CORP | 07/29/2023 |
| DOB NOW | General Construction | Permit Issued | LW CONTRACTING INC | 05/05/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/15/2023 | Signed-off | MAXWELL PLUMB MECH. CORP | Storm |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/26/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 12/24/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/23/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/23/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/31/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/29/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/11/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/09/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/26/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/23/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | DOYUN KIM | special |
| 08/23/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | DOYUN KIM | special |
| 08/14/2023 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | DOYUN KIM | special |
| 08/14/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 01/10/2023 | Subgrade Inspections | DOYUN KIM | special |
| 01/05/2023 | Lowest Floor Elevation | DOYUN KIM | progress |
| 01/05/2023 | Masonry | DOYUN KIM | special |
| 01/05/2023 | Subsurface Investigations (Borings/Test Pits) | FAHAD FATEH | special |
| 01/05/2023 | Concrete - Cast-In-Place | DOYUN KIM | special |