| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/18/2023 | $660K | — | — → — | $522/sf building |
| 06/14/2022 | $400K | — | — → — | $316/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 08/21/2025 |
| HAMMOND ARCHITECTURE | 2 | 07/28/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| TIFFANY ANN HAMMOND | 1 | 03/21/2026 |
| TIFFANY HAMMOND | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J&J DESIGNS INC | General Contractor | 1 | 07/08/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 08/21/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 08/26/2025 |
| DOB NOW | Plumbing | Signed-off | HORBRIDGE PLUMBING & HEAT | 08/03/2022 |
| DOB NOW | General Construction | Signed-off | J&J DESIGNS INC | 08/02/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| 09/05/2025 | Complete | CUNNINGHAM ELECTRIC CORP | General Wiring |
| 09/08/2022 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/21/2025 | Signed-off | SUNRUN INSTALLATION SVC | 26 panels, 10.66 kw, 273.39 roof_area_sqft |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/19/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/08/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/29/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/29/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2025 | Final | Walid Abdulla | progress |
| 08/19/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 08/19/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 08/19/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 08/19/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 07/28/2022 | Lighting in dwelling units | Patrick Hammond | energy_progress |
| 07/20/2022 | Final | Patrick Hammond | progress |