| Owner | Filings | Most Recent |
|---|---|---|
| MORELL BUILDERS | 2 | 03/22/2026 |
| BUYERS 516 849 3151 LLC | 1 | 03/22/2026 |
| PARK SLOPE ASSOCIATES | 3 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/05/2021 | $1.4M | — | — → — | $614/sf building |
| 02/26/2018 | $830K | — | Private party → BUYERS 516 849 3151 LLC | $377/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHARLES DIEHL ARCHITECT LLC | 7 | 12/15/2022 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GALA DESIGNS CORP | General Contractor | 8 | 03/22/2026 |
| CHARLES DIEHL | Electrical | 2 | 03/21/2026 |
| PROTO P & H SERVICES CORP | Plumbing | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RLC HVAC CONTROLS LLC | 5082 | 7 | 12/15/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | GALA DESIGNS CORP | 06/06/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | GALA DESIGNS CORP | 01/31/2022 |
| BIS | OT | ISSUED | MORELL BUILDERS INC | 06/27/2019 |
| BIS | OT | ISSUED | MORELL BUILDERS INC | 02/07/2019 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/15/2022 | Permit Issued | GALA DESIGNS CORP | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2022 | — | — | Gas, Plumbing-Sprinkler, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/03/2022 | Complete | KET ELECTRIC LLC | General Wiring |
| 07/20/2021 | Complete | ALL WAYS ELECTRIC CORP.W | — |
| 08/20/2018 | Complete | ROYAL ELEC'L CONTR'G CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/08/2022 | Fire-Resistant Penetrations and Joints | MICHAEL LI | special |
| 11/08/2022 | HVAC-R and service water heating equipment | MICHAEL LI | energy_progress |
| 11/08/2022 | HVAC-R and service water piping design and insulation | MICHAEL LI | energy_progress |
| 11/08/2022 | HVAC-R and service water heating system controls | MICHAEL LI | energy_progress |
| 10/28/2022 | HVAC-R and service water heating equipment | MICHAEL LI | energy_progress |
| 10/28/2022 | HVAC-R and service water heating system controls | MICHAEL LI | energy_progress |
| 10/28/2022 | Fire-Resistant Penetrations and Joints | MICHAEL LI | special |
| 10/28/2022 | HVAC-R and service water piping design and insulation | MICHAEL LI | energy_progress |
| 10/04/2022 | HVAC-R and service water piping design and insulation | MICHAEL LI | energy_progress |
| 10/04/2022 | Fire-Resistant Penetrations and Joints | MICHAEL LI | special |
| 10/04/2022 | HVAC-R and service water heating equipment | MICHAEL LI | energy_progress |
| 10/04/2022 | HVAC-R and service water heating system controls | MICHAEL LI | energy_progress |
| 10/04/2022 | Concrete - Cast-In-Place | MICHAEL LI | special |
| 10/04/2022 | Excavations - Sheeting, Shoring, and Bracing | MICHAEL LI | special |
| 10/04/2022 | Fire-Resistant Penetrations and Joints | MICHAEL LI | special |
| 10/04/2022 | Mechanical Systems | MICHAEL LI | special |
| 10/04/2022 | Structural Stability – Alterations of existing buildings | MICHAEL LI | special |
| 10/04/2022 | Energy Code Compliance Inspections | MICHAEL LI | progress |
| 10/04/2022 | Final | MICHAEL LI | progress |
| 10/04/2022 | Fire-Resistance Rated Construction | MICHAEL LI | progress |
| 10/04/2022 | Lighting in dwelling units | MICHAEL LI | energy_progress |
| 10/04/2022 | Shutoff dampers | MICHAEL LI | energy_progress |
| 10/04/2022 | Fenestration air leakage | MICHAEL LI | energy_progress |
| 10/04/2022 | HVAC-R and service water piping design and insulation | MICHAEL LI | energy_progress |
| 10/04/2022 | HVAC-R and service water heating equipment | MICHAEL LI | energy_progress |