| Firm | Filings | Most Recent |
|---|---|---|
| CHRIS PONISI, ARCHITECT | 4 | 02/16/2024 |
| REAL CREATIVE MOTION ENGINEERING SE | 2 | 11/21/2023 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 01/12/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CHRIS PONISI ARCHITECT | 4 | 03/21/2026 |
| DAWN PONISI | 4 | 03/21/2026 |
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TREDENT CONTRACTING SERVI | General Contractor | 7 | 07/08/2026 |
| DNA PLUMBING CONTR. INC | Plumbing | 5 | 07/08/2026 |
| MCCLEARY ELEC CONT INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 5 | 02/16/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | TREDENT CONTRACTING SERVI | 08/28/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | TREDENT CONTRACTING SERVI | 08/28/2024 |
| DOB NOW | Plumbing | Permit Issued | DNA PLUMBING CONTR. INC | 03/14/2024 |
| DOB NOW | Plumbing | Permit Issued | DNA PLUMBING CONTR. INC | 03/06/2024 |
| DOB NOW | Plumbing | Permit Issued | DNA PLUMBING CONTR. INC | 01/03/2024 |
| DOB NOW | Plumbing | Permit Issued | DNA PLUMBING CONTR. INC | 01/30/2023 |
| DOB NOW | Plumbing | Permit Issued | DNA PLUMBING CONTR. INC | 01/30/2023 |
| DOB NOW | General Construction | Permit Issued | TREDENT CONTRACTING SERVI | 01/20/2023 |
| BIS | PL | ISSUED | CASTELUCCI PL. & HEATING | 02/16/1994 |
| BIS | — | ISSUED | NORTH SHORE CONCRETE & CONST. CO | 10/02/1992 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/21/2023 | Permit Issued | TREDENT CONTRACTING SERVI | Heating and Air Conditioning Systems, Heating Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAM 48,000 BTU · Heat Pump Outdoor ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/16/2024 | Permit Issued | DNA PLUMBING CONTR. INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/20/2023 | Complete | MCCLEARY ELEC CONT INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/16/2024 | Permit Issued | TREDENT CONTRACTING SERVI | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/11/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 04/08/2024 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 03/12/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/05/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/07/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/26/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/05/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/21/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/20/2024 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 02/20/2024 | Maintenance information | anthony santoro | energy_progress |
| 02/20/2024 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 02/20/2024 | Permanent certificate | anthony santoro | energy_progress |
| 02/20/2024 | Metering | anthony santoro | energy_progress |
| 02/20/2024 | Energy Code Compliance Inspections | anthony santoro | progress |
| 12/12/2023 | Final | anthony santoro | progress |
| 12/12/2023 | Energy Code Compliance Inspections | anthony santoro | progress |
| 12/12/2023 | Mechanical Systems | anthony santoro | special |
| 12/12/2023 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 12/12/2023 | Heating Systems | anthony santoro | special |
| 12/08/2023 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 12/08/2023 | Energy Code Compliance Inspections | anthony santoro | progress |
| 12/08/2023 | Metering | anthony santoro | energy_progress |
| 12/08/2023 | Maintenance information | anthony santoro | energy_progress |
| 12/08/2023 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 12/08/2023 | Permanent certificate | anthony santoro | energy_progress |
| 11/21/2023 | Heating Systems | — | special |
| 11/21/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 11/21/2023 | Final | — | progress |
| 11/21/2023 | Energy Code Compliance Inspections | — | progress |
| 11/21/2023 | Mechanical Systems | — | special |
| 12/14/2022 | Permanent certificate | anthony santoro | energy_progress |
| 12/14/2022 | Maintenance information | anthony santoro | energy_progress |
| 12/14/2022 | Structural Stability – Alterations of existing buildings | anthony santoro | special |