| Owner | Filings | Most Recent |
|---|---|---|
| 995 Fifth Avenue Owner | 18 | 03/22/2026 |
| Hyatt Hotels | 8 | 03/21/2026 |
| Epoch 5th | 6 | 03/21/2026 |
| WB Imico Lexington Fee | 6 | 03/21/2026 |
| Extell Development | 4 | 03/21/2026 |
| Candela Stanhope Holding Company | 3 | 03/21/2026 |
| 995 Fifth Condominium | 2 | 03/21/2026 |
| LBN 995 5th Avenue | 2 | 03/21/2026 |
| Imico Metro | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Munyc Architecture | 4 | 05/19/2026 |
| Hyke Engineering & Management | 6 | 07/08/2025 |
| Shalat Architects | 2 | 10/22/2024 |
| KZ Engineering | 3 | 12/05/2022 |
| Benazzi Engineering | 3 | 11/03/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| Synergy Building Consultants | 3 | 03/21/2026 |
| Janco Building Consultants | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Colgate Enterprise | Scaffold | 22 | 07/08/2026 |
| Accurate Electrical Contractors | Electrical | 5 | 03/21/2026 |
| CS Bridge | Scaffold | 4 | 03/21/2026 |
| Tatras Construction | General Contractor | 4 | 03/21/2026 |
| Marathon Mechanical | Plumbing | 2 | 07/08/2026 |
| J. Simon Associates | General Contractor | 2 | 07/08/2026 |
| MPC Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| A & S Electric | Electrical | 1 | 03/21/2026 |
| Zerega Contracting | Plumbing | 1 | 07/08/2026 |
| J. G. Installations | Electrical | 1 | 03/21/2026 |
| New Century Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Power Full Electric | Electrical | 1 | 03/22/2026 |
| HI-Tech Wiring Electrical Services | Electrical | 1 | 03/21/2026 |
| Wesbuilt Construction Man | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Munyc Architecture | 5224 | 4 | 05/19/2026 |
| Hyke Engineering & Management | 2422 | 3 | 11/05/2024 |
| Biz Designs | 6312 | 2 | 10/22/2024 |
| Shalat Architects | 2036 | 2 | 10/22/2024 |
| RHL Engineering | 712 | 2 | 11/21/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | J Simon Associates | 01/27/2026 |
| DOB NOW | Plumbing | Signed-off | Marathon Mechanical | 08/04/2025 |
| DOB NOW | Plumbing | Signed-off | Zerega Contracting | 11/26/2024 |
| DOB NOW | General Construction | Signed-off | Wesbuilt Construction Man | 11/12/2024 |
| DOB NOW | General Construction | Signed-off | Tatras Construction | 08/09/2024 |
| DOB NOW | Plumbing | Signed-off | Marathon Mechanical | 07/26/2024 |
| DOB NOW | General Construction | Signed-off | Tatras Construction | 07/23/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 12/04/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CS Bridge | 12/06/2022 |
| DOB NOW | General Construction | Signed-off | J Simon Associates | 11/22/2022 |
| DOB NOW | Plumbing | Signed-off | MPC Plumbing & Heating | 08/05/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | Colgate Enterprise | 04/09/2020 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 04/08/2020 |
| DOB NOW | Construction Fence | Signed-off | Colgate Enterprise | 10/17/2019 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 04/18/2019 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 04/10/2019 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 04/04/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Colgate Enterprise | 12/17/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | Colgate Enterprise | 12/17/2018 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 06/27/2018 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 06/27/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | Colgate Enterprise | 05/15/2018 |
| DOB NOW | Supported Scaffold | Signed-off | Colgate Enterprise | 05/15/2018 |
| BIS | OT | ISSUED | Star-Cel Waterproofing | 07/02/2020 |
| BIS | EQ | ISSUED | Star-Cel Waterproofing | 05/21/2019 |
| BIS | OT | ISSUED | Dartom Construction | 05/01/2019 |
| BIS | PL | ISSUED | Hydrokinetic Plumbing & Heating I | 02/12/2019 |
| BIS | OT | ISSUED | Dartom Construction | 02/07/2019 |
| BIS | OT | ISSUED | Star-Cel Waterproofing | 12/31/2018 |
| BIS | OT | ISSUED | Star-Cel Waterproofing | 08/03/2018 |
| BIS | EQ | ISSUED | Star-Cel Waterproofing | 06/01/2018 |
| BIS | MH | ISSUED | Command Cooling | 02/10/2017 |
| BIS | OT | ISSUED | Command Cooling | 02/10/2017 |
| BIS | MH | ISSUED | Command Cooling | 01/12/2017 |
| BIS | OT | ISSUED | Command Cooling | 01/12/2017 |
| BIS | MH | ISSUED | Smi Construction Mangement | 03/04/2016 |
| BIS | OT | ISSUED | Total Home Improvement SE | 08/17/2015 |
| BIS | MH | ISSUED | Total Home Improvement SE | 08/17/2015 |
| BIS | OT | ISSUED | Orchid Construction | 08/05/2015 |
| BIS | PL | ISSUED | A.R.L. Plumbing & Heating | 07/14/2015 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/09/2026 | Complete | Lume Electric | — |
| 03/20/2026 | Complete | Apollo Electric NYG | — |
| 09/26/2025 | Permit Issued | Accurate Electrical Contractors | General Wiring |
| 06/15/2025 | Complete | Power Full Electric | General Wiring |
| 05/29/2024 | Complete | Power Full Electric | General Wiring |
| 09/27/2023 | Complete | Apollo Electric | General Wiring |
| 05/17/2023 | Cancelled | Riviera Electric | General Wiring |
| 12/27/2022 | Permit Issued | Apollo Electric | — |
| 12/05/2022 | Complete | Nash Electric Services | — |
| 11/20/2019 | Permit Issued | New Century Electrical Contracting | — |
| 02/08/2019 | Complete | Glendale Electl Contng | General Wiring |
| 05/08/2018 | Complete | Nash Electric Services | — |
| 01/28/2018 | Complete | Jem Electrical Contracting | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/15/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/15/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/18/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/19/2026 | Lighting in dwelling units | Matthias Mueller | energy_progress |
| 05/19/2026 | Post-installed Anchors | Matthias Mueller | special |
| 05/19/2026 | Fire-Resistant Penetrations and Joints | Matthias Mueller | special |
| 05/19/2026 | Final | Matthias Mueller | progress |
| 05/19/2026 | Energy Code Compliance Inspections | Matthias Mueller | progress |
| 04/08/2025 | Final | Gene Hu | progress |
| 04/08/2025 | Post-installed Anchors | Gene Hu | special |
| 04/08/2025 | Fire-Resistant Penetrations and Joints | Gene Hu | special |
| 04/08/2025 | Fire-Resistance Rated Construction | Gene Hu | progress |
| 11/03/2024 | Post-installed Anchors | Gene Hu | special |
| 11/03/2024 | Fire-Resistant Penetrations and Joints | Gene Hu | special |
| 11/03/2024 | Fire-Resistance Rated Construction | Gene Hu | progress |
| 11/03/2024 | Final | Gene Hu | progress |
| 10/04/2024 | Interior lighting power | Edward Shalat | energy_progress |
| 10/04/2024 | Lighting controls | Edward Shalat | energy_progress |
| 10/04/2024 | Lighting in dwelling units | Edward Shalat | energy_progress |
| 10/04/2024 | Fire-Resistance Rated Construction | Edward Shalat | progress |
| 10/04/2024 | Final | Edward Shalat | progress |
| 10/03/2024 | Tenant Protection Plan Compliance | JEFF AKERMAN | special |
| 10/03/2024 | Fire-Resistant Penetrations and Joints | Edward Shalat | special |
| 09/25/2024 | Fire-Resistant Penetrations and Joints | Edward Shalat | special |
| 09/25/2024 | Tenant Protection Plan Compliance | JEFF AKERMAN | special |
| 05/28/2024 | Post-installed Anchors | Gene Hu | special |
| 05/28/2024 | Final | Gene Hu | progress |
| 05/28/2024 | Fire-Resistant Penetrations and Joints | Gene Hu | special |