← Back
Elevator cooperative
998 Fifth Avenue Apartment House
998 5 AVENUE · BIN 1046660
💬 Discuss this project
1912Year Built
12Stories
D4Building Class
R10Zoning
145,230 sfGross Floor Area
18Units
LL97 CoveredRent Stabilized4 Open Violations ▸FISP: SAFE
Elevator cooperative · Owner of record: 998 5TH AVE CORP · 14,886 sf lot · 9.76 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingCivil
Permit Issued — active, not yet Signed-off
Roof6p · 5 filings · 20 docs
Bulkhead1p · 1 filing · 3 docs
PenthouseUnder Construction13p · 1 filing · 17 docs
Floor 121p · 1 filing · 16 docs
Floor 114p · 2 filings · 20 docs
Floor 101p · 1 filing · 9 docs
Floor 91p · 1 filing · 16 docs
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 11p · 1 filing · 9 docs
Cellar1p · 1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BROWN HARRIS STEVENS3607/08/2026
998 5TH AVE1803/22/2026
BHS MANAGEMENT203/22/2026
998 FIFTH AVENUE7003/22/2026
CHARTER COMMUNICATIONS103/22/2026
BROWN HARRIS STEVENS MANAGEMENT103/22/2026
998 FIFTH AVENUE CORP C O BHS603/21/2026
998 5TH AVENUE CORP C C BHS1103/21/2026
998 5TH AVENUE CORP CO-OP LLC603/21/2026
ACCESS INDUSTRIES703/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BREND RESTORATION LLCGeneral Contractor1507/08/2026
S. DONADIC INCGeneral Contractor1407/08/2026
WARREN OSTROFF ELEC., INCElectrical403/22/2026
FORTE EXPRESS P & H INCPlumbing207/08/2026
TOMASZ PUZAElectrical203/21/2026
NOVA CONSTRUCTION SERVICEGeneral Contractor204/09/2026
RICHARD GRIMAElectrical103/21/2026
ROBERT CHIMENTIElectrical103/22/2026
AQUA PLUMBING & HTNG CORPPlumbing107/08/2026
CHANG, VICTORElectrical103/21/2026
WITTMAN, ROBERTElectrical103/21/2026
CARMINE LIPPOLISElectrical103/21/2026
LEGACY BUILDERS/DEVELOPERS CORPGeneral Contractor104/09/2026
ANTHONY BONAIUTOElectrical103/21/2026
BONAIUTO ANTHONYElectrical103/21/2026
SPRING SCAFFOLDING LLCGeneral Contractor107/08/2026
JOSEPH SORTINOElectrical103/21/2026
KOSTAS TSAHASElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ANTHONY MORALI ARCHITECT4810304/14/2026
WAVIC ENGINEERING PLLC1733101/06/2026
ALAN MARGOLIN & ASSOC423502/17/2023
MOORE ENG. OF NY, DPC9134112/23/2022
SITE SAFETY LLC8555111/17/2022
Building Lifecycle
All (189)Filed (23)Permit Issued (31)Signed Off (13)Facade (FISP) (21)Violation (56)Inspection (16)Objection (4)Special Inspection (25)
07/16/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY MORALI
04/14/2026
Filed — Alteration
Partition, finish, fixture work at Penthouse super's apartment. New HVAC system. No change to use, egress or occupancy filed under this application.
M01336757-P1
04/08/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/09/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
03/04/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/20/2026
Permit issued — Plumbing
M01336757-S1-PL
01/12/2026
Permit issued — General Construction
M01336757-I1-GC-CX
01/06/2026
Filed — Alteration
Partition, finish, fixture work at Penthouse super's apartment. New HVAC system. No change to use, egress or occupancy filed under this application.
M01336757-S1
01/06/2026
Filed — Alteration
Partition, finish, fixture work at Penthouse super's apartment. New HVAC system. No change to use, egress or occupancy filed under this application.
M01336757-I1
01/05/2026
Cycle 9 facade report submitted
12/31/2025
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
12/31/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)
Certified
View inspection ↗
12/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ANTHONY MORALI
12/22/2025
Special inspection requirement — HVAC-R and service water heating system controls
LOUIS LIPSON
12/22/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
LOUIS LIPSON
12/22/2025
Special inspection requirement — HVAC-R and service water heating equipment
LOUIS LIPSON
12/22/2025
Special inspection requirement — Duct leakage testing, insulation and design
LOUIS LIPSON
12/19/2025
Special inspection requirement — Energy Code Compliance Inspections
LOUIS LIPSON
12/19/2025
Special inspection requirement — Interior lighting power
LOUIS LIPSON
12/19/2025
Special inspection requirement — Lighting controls
LOUIS LIPSON
12/19/2025
Special inspection requirement — Air barrier - visual inspection
LOUIS LIPSON
12/19/2025
Special inspection requirement — Lighting in dwelling units
LOUIS LIPSON
12/19/2025
Special inspection requirement — Post-installed Anchors
DARIUSZ LUCZAK
12/18/2025
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed and shoring via supported scaffold and per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01304093-I1
12/18/2025
Special inspection requirement — Mechanical Systems
ANTHONY MORALI
12/18/2025
Special inspection requirement — Final
LOUIS LIPSON
12/17/2025
Cycle 9 facade report signed — SAFE
12/12/2025
Cycle 9 facade inspection completed
12/12/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/05/2025
Signed off — Alteration
FACADE AND EXTERIOR MASONRY REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
M00696242-I1
12/05/2025
Signed off — Alteration
M00796453-I1
11/26/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/24/2025
Filed — Alteration
Installation of a temporarily heavy-duty sidewalk shed and shoring via supported scaffold and per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01304093-I1
10/24/2025
Signed off — Alteration
M01030577-I1
10/24/2025
Permit issued — Supported Scaffold
M01304093-I1-SH
10/24/2025
Permit issued — Supported Scaffold
M01304093-I1-SF
10/03/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/27/2025
Cycle 9 facade report submitted
08/26/2025
Cycle 9 facade inspection completed
08/26/2025
Cycle 9 facade report signed — UNSAFE
07/25/2025
Signed off — Alteration
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
M01235246-I1
07/16/2025
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
07/16/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
07/15/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
06/06/2025
Permit issued — Suspended Scaffold
M01235246-I1-SC
06/05/2025
Filed — Alteration
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
M01235246-I1
05/19/2025
Signed off — Alteration
M00748006-I1
05/19/2025
Signed off — Alteration
MECHANICAL WORK PROPOSED FOR AN EXISTING APARTMENT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M00748393-I1
05/16/2025
Signed off — Alteration
RENOVATION OF AN EXISTING APARTMENT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M00748079-I1
04/23/2025
Signed off — Alteration
PLUMBING WORK PROPOSED FOR AN EXISTING APARTMENT. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M00748405-I1
04/04/2025
Permit issued — General Construction
M00696242-I1-GC
04/02/2025
Permit issued — Suspended Scaffold
M01030577-I1-SC
03/04/2025
Signed off — Alteration
TEMPORARY INSTALLATION AND USE OF SIDEWALK SHED AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M00863212-I1
02/12/2025
Filed — Alteration
FACADE AND EXTERIOR MASONRY REPAIRS AS PER DRAWINGS. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS INVOLVED UNDER THIS APPLICATION.
M00696242-P2
12/09/2024
Cycle 9 facade report submitted
12/09/2024
Cycle 9 facade report signed — UNSAFE
12/06/2024
Cycle 9 facade inspection completed
08/14/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY CUSTOM COLOR SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY
M00929915-I1
08/01/2024
Permit issued — Structural
M00796453-I1-ST
Latest 60 of 189 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAQUA PLUMBING & HTNG CORP01/20/2026
DOB NOWGeneral ConstructionPermit IssuedLEGACY BUILDERS/DEVELOPER01/12/2026
DOB NOWSupported ScaffoldSigned-offNOVA CONSTRUCTION SERVICE10/24/2025
DOB NOWSupported ScaffoldSigned-offNOVA CONSTRUCTION SERVICE10/24/2025
DOB NOWSuspended ScaffoldSigned-offBREND RESTORATION LLC06/06/2025
DOB NOWGeneral ConstructionSigned-offBREND RESTORATION LLC04/04/2025
DOB NOWSuspended ScaffoldSigned-offBREND RESTORATION LLC04/02/2025
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC08/01/2024
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC07/30/2024
DOB NOWMechanical SystemsSigned-offSAPOL CONSTRUCTION LLC07/30/2024
DOB NOWGeneral ConstructionSigned-offSAPOL CONSTRUCTION LLC07/29/2024
DOB NOWSupported ScaffoldSigned-offBREND RESTORATION LLC04/30/2024
DOB NOWSidewalk ShedSigned-offBREND RESTORATION LLC04/29/2024
DOB NOWGeneral ConstructionSigned-offBREND RESTORATION LLC04/17/2024
DOB NOWSuspended ScaffoldSigned-offBREND RESTORATION LLC04/09/2024
DOB NOWPlumbingSigned-offFORTE EXPRESS P & H INC09/21/2023
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC09/08/2023
DOB NOWProtection and Mechanical MethodsSigned-offBREND RESTORATION LLC08/24/2023
DOB NOWGeneral ConstructionSigned-offSAPOL CONSTRUCTION LLC08/02/2023
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC08/01/2023
DOB NOWMechanical SystemsSigned-offSAPOL CONSTRUCTION LLC08/01/2023
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC08/01/2023
DOB NOWGeneral ConstructionSigned-offBREND RESTORATION LLC05/25/2023
DOB NOWSupported ScaffoldSigned-offBREND RESTORATION LLC05/05/2023
DOB NOWSidewalk ShedSigned-offBREND RESTORATION LLC05/05/2023
DOB NOWMechanical SystemsSigned-offSAPOL CONSTRUCTION LLC03/15/2023
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC02/14/2023
DOB NOWStructuralSigned-offSAPOL CONSTRUCTION LLC01/19/2023
DOB NOWGeneral ConstructionSigned-offSAPOL CONSTRUCTION LLC01/05/2023
DOB NOWGeneral ConstructionSigned-offSAPOL CONSTRUCTION LLC09/21/2022
DOB NOWPlumbingSigned-offFORTE EXPRESS P & H INC09/21/2022
BISPLISSUEDFORTE EXPRESS P & H INC10/25/2021
BISMHISSUEDS. DONADIC INC07/01/2021
BISOTISSUEDS. DONADIC INC07/01/2021
BISOTISSUEDS. DONADIC INC01/27/2021
BISMHISSUEDS. DONADIC INC01/27/2021
BISPLISSUEDFORTE EXPRESS P & H INC09/24/2020
BISOTISSUEDINTERIOR MANAGEMENT LLC03/05/2020
BISOTISSUEDINTERIOR MANAGEMENT LLC03/05/2020
BISOTISSUEDINTERIOR MANAGEMENT LLC03/05/2020
+ 41 more permits on file
1 project · most recent 04/14/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/14/2026Permit IssuedLEGACY BUILDERS/DEVELOPERAir Conditioning Systems
Cooling
Fujitsu FUJITSU - AOU36RLXFZH 36,400 BTU · Condensing Unit ×2
FUJITSU - ASUH07KPAS 7,000 BTU · Fan Coil Indoor ×1
FUJITSU - ASUH09KPAS 10,000 BTU · Fan Coil Indoor ×1
FUJITSU - ASUH12KPAS 14,000 BTU · Fan Coil Indoor ×1
FUJITSU - ASUH15KPAS 15,000 BTU · Fan Coil Indoor ×1
1 project · most recent 04/14/2026
Gas Water/Sanitary
FiledStatusContractorScope
04/14/2026Permit IssuedAQUA PLUMBING & HTNG CORPGas, Water/Sanitary
20 projects · most recent 11/19/2025
General Wiring HVAC Wiring Lighting
FiledStatusContractorScope
11/19/2025CompleteTOP SHELF ELECTRIC CORP—
02/19/2025CompleteWARREN OSTROFF ELEC., INC1 meters, 1 new_meters
09/07/2023CompleteTOP SHELF ELECTRIC CORP—
05/08/2023CompleteTOP SHELF ELECTRIC CORP—
09/09/2022CompleteWARREN OSTROFF ELEC., INC—
12/27/2021CompleteWARREN OSTROFF ELEC., INCGeneral Wiring, HVAC Wiring
05/21/2021CompleteWARREN OSTROFF ELEC., INC—
04/01/2021CompleteWARREN OSTROFF ELEC., INCGeneral Wiring, Lighting
01/07/2021CompleteROBERT CHIMENTIGeneral Wiring
08/21/2020CompleteTOP SHELF ELECTRIC CORP—
08/05/2020CompleteTOP SHELF ELECTRIC CORP—
06/12/2020CompleteRESPONSE ELECTRIC INC.General Wiring
03/12/2020CompleteWARREN OSTROFF ELEC., INC—
03/06/2020CompleteWARREN OSTROFF ELEC., INC—
02/19/2020CompleteCENTURY ELECTRIC LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 16
DateTypeResultReport
07/16/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/08/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/09/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/04/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/31/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
12/31/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)CertifiedView ↗
12/12/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/26/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/03/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/16/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
07/16/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
07/15/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
08/08/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/03/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/06/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
04/16/2026Fire-Resistant Penetrations and JointsANTHONY MORALIspecial
12/22/2025Fire-Resistant Penetrations and JointsANTHONY MORALIspecial
12/22/2025HVAC-R and service water heating system controlsLOUIS LIPSONenergy_progress
12/22/2025HVAC-R and service water piping design and insulationLOUIS LIPSONenergy_progress
12/22/2025HVAC-R and service water heating equipmentLOUIS LIPSONenergy_progress
12/22/2025Duct leakage testing, insulation and designLOUIS LIPSONenergy_progress
12/19/2025Energy Code Compliance InspectionsLOUIS LIPSONprogress
12/19/2025Interior lighting powerLOUIS LIPSONenergy_progress
12/19/2025Lighting controlsLOUIS LIPSONenergy_progress
12/19/2025Air barrier - visual inspectionLOUIS LIPSONenergy_progress
12/19/2025Lighting in dwelling unitsLOUIS LIPSONenergy_progress
12/19/2025Post-installed AnchorsDARIUSZ LUCZAKspecial
12/18/2025Mechanical SystemsANTHONY MORALIspecial
12/18/2025FinalLOUIS LIPSONprogress
06/30/2023Tenant Protection Plan Compliance—special
06/30/2023FinalRobert Batesprogress
12/23/2022Structural Stability – Alterations of existing buildingsChristine Hobsonspecial
12/23/2022Tenant Protection Plan ComplianceYoung Suhspecial
12/23/2022Structural Steel - WeldingChristine Hobsonspecial
08/19/2022FinalChristine Hobsonprogress
08/19/2022Structural Steel - DetailsChristine Hobsonspecial
07/26/2022Fire-Resistance Rated ConstructionYoung Suhprogress
07/26/2022Post-installed AnchorsYoung Suhspecial
05/31/2022Fire-Resistant Penetrations and JointsYoung Suhspecial
05/31/2022FinalYoung Suhprogress
▾Documents — 805 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch23
09/01/2026M00796453-I1Request digital key ↗
08/31/2026M00748006-I1Request digital key ↗
08/31/2026M00863212-I1Request digital key ↗
Showing 3 of 23 on file for this type
▸Applications & Permits195
▸BISWORK PERMIT APPLICATION102
03/09/2020123177463Open ↗
03/09/2020123520145Open ↗
03/09/2020123177463Open ↗
Showing 3 of 102 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION78
01/10/2022123469031Open ↗
06/25/2020123177463Open ↗
01/21/2020123520145Open ↗
Showing 3 of 78 on file for this type
▸DOB NOWLPC Approval/Permit14
08/17/2026M01336757-P1Open ↗
08/13/2026M00696242-I1Open ↗
08/13/2026M01336757-I1Open ↗
Showing 3 of 14 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
10/16/2020123177463Open ↗
▸Seals & Professional Certifications149
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION102
03/27/2020123520145Open ↗
03/27/2020123520145Open ↗
07/17/2019122962865Open ↗
Showing 3 of 102 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/02/2026M00748079-I1Open ↗
08/31/2026M00748006-I1Open ↗
08/31/2026M00863212-I1Open ↗
Showing 3 of 22 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
10/25/2017104527549Open ↗
Showing 1 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/13/2026M01336757-I1Open ↗
09/13/2026M01336757-I1Open ↗
09/02/2026M00748079-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/13/2026M01336757-I1Open ↗
09/13/2026M01336757-I1Open ↗
09/02/2026M00748079-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Trade Schedules & Equipment67
▸BISSELF-CERT PLUMBING NOTICE16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 16 on file for this type
▸BISSCHEDULE B - PLUMBING15
06/25/2020123177463Open ↗
Showing 1 of 15 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE15
08/20/2019123469031Open ↗
01/14/2019123177463Open ↗
07/30/2018123469031Open ↗
Showing 3 of 15 on file for this type
▸BISEQUIPMENT USE PERMITS8
05/20/2022123469031Open ↗
05/17/2022123469031Open ↗
10/16/2020123177463Open ↗
Showing 3 of 8 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT8
05/20/2022123469031Open ↗
05/17/2022123469031Open ↗
10/16/2020123177463Open ↗
Showing 3 of 8 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
10/16/2020123177463Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
10/16/2020123177463Open ↗
▸Safety & Tenant Protection6
▸BISTenant Protection Plan and Notes5
07/30/2018123469031Open ↗
07/11/2018123520145Open ↗
12/13/2017123177463Open ↗
Showing 3 of 5 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
07/30/2018123469031Open ↗
▸Environmental & Asbestos44
▸BISASBESTOS: CERTIFICATION (DEP ACP5)17
08/14/2018123469031Open ↗
07/11/2018123520145Open ↗
12/13/2017123177463Open ↗
Showing 3 of 17 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/17/2026M01336757-P1Open ↗
08/13/2026M01336757-I1Open ↗
08/13/2026M00696242-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form5
08/31/2026M00748006-I1Open ↗
08/27/2026M00748405-I1Open ↗
08/15/2026M00748079-I1Open ↗
Showing 3 of 5 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance29
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTR8: Energy Code Progress Inspections4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISENERGY CODE 1ST REVIEW COMPLETE2
07/30/2018123469031Open ↗
07/11/2018123520145Open ↗
▸Inspections & Test Reports9
▸BISTECHNICAL REPORT: RESPONSIBILITY4
10/16/2020123177463Open ↗
10/16/2020123177463Open ↗
10/16/2020123177463Open ↗
Showing 3 of 4 on file for this type
▸BISMECHANICAL SYSTEMS1
05/17/2022123469031Open ↗
▸BISPOST-INSTALLED ANCHORS1
05/17/2022123469031Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
05/17/2022123469031Open ↗
▸BISSPRAYED FIRE-RESISTANT MATERIALS1
05/17/2022123469031Open ↗
▸BISTECHNICAL REPORT: PILE DRIVING1
04/04/2018122786468Open ↗
▸Approvals, Objections & Sign-offs99
▸BISLANDMARKS APPROVAL39
03/27/2020123520145Open ↗
07/30/2018123469031Open ↗
07/24/2018123520145Open ↗
Showing 3 of 39 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST31
05/18/2022123469031Open ↗
10/16/2020123177463Open ↗
03/27/2020123520145Open ↗
Showing 3 of 31 on file for this type
▸BISADMINISTRATIVE OBJECTIONS15
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 15 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION8
10/23/2020123177463Open ↗
08/14/2018123469031Open ↗
04/04/2018122786468Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS SIGNOFF2
05/18/2022123469031Open ↗
11/07/2018122962865Open ↗
▸BISSHED LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISBSA-CPC APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSUPERSEDING LETTER1
03/02/2017122786468Open ↗
▸BISFINAL1
05/17/2022123469031Open ↗
▸Cost, Insurance & Ownership70
▸BISCOST AFFIDAVIT69
10/16/2020123177463Open ↗
03/27/2020123520145Open ↗
01/21/2020123520145Open ↗
Showing 3 of 69 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/17/2022123469031Open ↗
▸Filing & Intake Forms94
▸BISADDITIONAL INFORMATION40
09/10/2019123469031Open ↗
09/10/2019123469031Open ↗
09/10/2019123469031Open ↗
Showing 3 of 40 on file for this type
▸BISEFILING COVER SHEET33
07/30/2018123469031Open ↗
07/30/2018123469031Open ↗
07/11/2018123520145Open ↗
Showing 3 of 33 on file for this type
▸BISBOROUGH INTAKE FORM21
03/27/2020123520145Open ↗
03/18/2020123520145Open ↗
01/21/2020123520145Open ↗
Showing 3 of 21 on file for this type
▸Other Documents20
▸DOB NOWProof of Historic Building9
08/13/2026M00748405-P3Open ↗
08/13/2026M00748405-P1Open ↗
08/13/2026M00748405-P2Open ↗
Showing 3 of 9 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISDepartment of Consumer Affairs (DCA) Form2
08/02/2018123520145Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWManufacturer's Specifications2
08/13/2026M01030577-I1Open ↗
08/13/2026M01235246-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M01030577-I1Open ↗
08/13/2026M01235246-I1Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type