| Owner | Filings | Most Recent |
|---|---|---|
| EDGEWATER PARK OWNER COOPERATIVE | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MARK ANTHONY ARCHITECTURE PC | 11 | 11/04/2024 |
| ENSIGN ENGINEERING, P.C. | 2 | 01/10/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 20 | 03/21/2026 |
| CITY WIDE EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FOREMOST CONTRACTING & BU | General Contractor | 14 | 07/08/2026 |
| ARA PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| SCOTT MILET | Electrical | 1 | 03/21/2026 |
| RELIABLE PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CROSSCHECK INSPECTION SER | 544 | 12 | 11/04/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | RELIABLE PLBG & HTG CORP | 02/04/2025 |
| DOB NOW | Plumbing | Signed-off | ARA PLUMBING CORP | 12/10/2024 |
| DOB NOW | Plumbing | Signed-off | ARA PLUMBING CORP | 03/26/2024 |
| DOB NOW | General Construction | Signed-off | FOREMOST CONTRACTING & BU | 03/25/2024 |
| DOB NOW | Foundation | Signed-off | FOREMOST CONTRACTING & BU | 03/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | FOREMOST CONTRACTING & BU | 03/25/2024 |
| DOB NOW | General Construction | Signed-off | FOREMOST CONTRACTING & BU | 03/24/2023 |
| DOB NOW | Mechanical Systems | Signed-off | FOREMOST CONTRACTING & BU | 03/24/2023 |
| DOB NOW | Foundation | Signed-off | FOREMOST CONTRACTING & BU | 03/24/2023 |
| DOB NOW | Plumbing | Signed-off | ARA PLUMBING CORP | 03/22/2023 |
| BIS | OT | ISSUED | DORINO CIVETTA AND SONS INC | 06/27/1997 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/18/2024 | Complete | METROPOLITAN ELECTRIC CO | General Wiring |
| 04/25/2024 | Complete | METROPOLITAN ELECTRIC CO | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/06/2024 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 11/06/2024 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 11/06/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 10/30/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 10/30/2024 | HVAC-R and service water heating equipment | EUGENE BIFULCO | energy_progress |
| 10/30/2024 | HVAC-R and service water heating system controls | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Footing and Foundation | EUGENE BIFULCO | progress |
| 05/09/2024 | Insulation placement and R values | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Subgrade Inspections | EUGENE BIFULCO | special |
| 05/09/2024 | Concrete - Cast-In-Place | EUGENE BIFULCO | special |
| 05/09/2024 | Subsurface Conditions – Fill Placement & In-Place Density | EUGENE BIFULCO | special |
| 05/09/2024 | Fenestration areas | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Fenestration and door U-factor and product ratings | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Interior lighting power | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 05/09/2024 | Air barrier - visual inspection | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Fenestration air leakage | EUGENE BIFULCO | energy_progress |
| 05/09/2024 | Fire-Resistance Rated Construction | EUGENE BIFULCO | progress |
| 05/09/2024 | Final | EUGENE BIFULCO | progress |
| 05/09/2024 | Energy Code Compliance Inspections | EUGENE BIFULCO | progress |
| 05/06/2024 | Insulation placement and R values | EUGENE BIFULCO | energy_progress |
| 05/06/2024 | Subgrade Inspections | EUGENE BIFULCO | special |
| 05/06/2024 | Concrete - Cast-In-Place | EUGENE BIFULCO | special |
| 05/06/2024 | Fire-Resistant Penetrations and Joints | EUGENE BIFULCO | special |
| 05/06/2024 | Subsurface Conditions – Fill Placement & In-Place Density | EUGENE BIFULCO | special |