| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/15/2020 | $498K | — | Private party → Private party | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| LESTER KATZ, NCARB | 5 | 01/23/2024 |
| EYAL LEVITT ARCHITECT PC | 2 | 05/04/2023 |
| R AND O ENGINEERING. P.C. | 2 | 03/12/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITER GROUP | 8 | 03/21/2026 |
| BDF DESIGN | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| UPPERLEVEL CONSTRUCTION | General Contractor | 7 | 03/22/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 3 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| D & F CONSTRUCTION GROUP | General Contractor | 1 | 03/22/2026 |
| FRIED ELECTRIC CO. | Electrical | 1 | 03/22/2026 |
| A M B MECHANICAL | Plumbing | 1 | 03/22/2026 |
| BT'S PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| HORBRIDGE PLUMBING HEAT | General Contractor | 1 | 03/22/2026 |
| SHTRAL ELECT'L CONT'G COR | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 7 | 01/23/2024 |
| METRO FIRE CONTROL LLC | 4538 | 2 | 05/04/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | UPPERLEVEL CONSTRUCTION | 12/18/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 06/08/2023 |
| DOB NOW | Plumbing | Signed-off | HORBRIDGE PLUMBING & HEAT | 01/06/2023 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 02/18/2022 |
| DOB NOW | Foundation | Signed-off | UPPERLEVEL CONSTRUCTION | 03/24/2021 |
| BIS | — | ISSUED | UPPERLEVEL CONSTRUCTION | 09/19/2023 |
| BIS | — | ISSUED | UPPERLEVEL CONSTRUCTION | 02/15/2023 |
| BIS | — | ISSUED | UPPERLEVEL CONSTRUCTION | 08/23/2022 |
| BIS | — | ISSUED | UPPERLEVEL CONSTRUCTION | 02/09/2022 |
| BIS | — | ISSUED | UPPERLEVEL CONSTRUCTION | 03/26/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2024 | Complete | SHTRAL ELECT'L CONT'G COR | General Wiring |
| 09/14/2021 | Complete | FRIED ELECTRIC CO. | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/31/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/22/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/20/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/18/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/14/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/15/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/20/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/20/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2023 | Sprinkler Systems | JEFFREY HANDLER | special |
| 05/08/2023 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 03/20/2023 | Sprinkler Systems | JEFFREY HANDLER | special |
| 03/20/2023 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 11/08/2022 | HVAC insulation and sealing | ELIAS RASABI | energy_progress |
| 11/08/2022 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 11/08/2022 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 11/08/2022 | HVAC and service water heating equipment | ELIAS RASABI | energy_progress |
| 11/08/2022 | HVAC and service water heating system controls | ELIAS RASABI | energy_progress |
| 03/11/2021 | Footing and Foundation | ELIAS RASABI | progress |
| 03/11/2021 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 03/11/2021 | Post-installed Anchors | ELIAS RASABI | special |
| 03/11/2021 | Structural Steel - High Strength Bolting | ELIAS RASABI | special |
| 03/11/2021 | Structural Steel - Welding | ELIAS RASABI | special |
| 03/11/2021 | Wood – High-Load Diaphragms | ELIAS RASABI | special |
| 03/11/2021 | Wood – Metal-Plate-Connected Trusses | ELIAS RASABI | special |
| 03/11/2021 | Structural Wood Frame | ELIAS RASABI | progress |
| 03/11/2021 | Subsurface Conditions – Fill Placement & In-Place Density | ELIAS RASABI | special |
| 03/11/2021 | Subsurface Investigations (Borings/Test Pits) | Soorjbally Harilall | special |
| 03/11/2021 | Final | ELIAS RASABI | progress |
| 03/11/2021 | Structural Stability – Alterations of existing buildings | ELIAS RASABI | special |
| 03/11/2021 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 03/11/2021 | Subgrade Inspections | ELIAS RASABI | special |
| 03/04/2021 | Structural Steel - Details | ELIAS RASABI | special |
| 03/04/2021 | Structural Cold-Formed Steel | ELIAS RASABI | special |