| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/30/2026 | Permit Issued | HT PLUMBING & HEATING COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/25/2022 | Complete | FIBERTEK DATA & ELEC CORP | — |
| 12/24/2021 | Complete | JONG HYUN KIM | — |
| 12/24/2021 | Complete | JONG HYUN KIM | — |
| 12/19/2021 | Complete | JONG HYUN KIM | — |
| 02/16/2021 | Complete | SKY ELECTRIC LLC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| ALIBABANOW | 9 | 04/09/2026 |
| JRS CONSTRUCTION & EXPEDI | 8 | 03/22/2026 |
| MGZ BUILDERS | 6 | 03/22/2026 |
| SION CONSULTING ENGINEERI | 1 | 03/22/2026 |
| ZHINGRI/MGZ BUILDERS CORP | 1 | 03/22/2026 |
| STARLING CASTLE HILL REALTY | 2 | 03/21/2026 |
| ARCHITECTURAL DESIGN SOLUTIONS | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/18/2016 | $50K | — | STARLING CASTLE HILL REALTY CORP. → UNITED NOSTRAND LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| CHK PLUS INC | 3 | 06/30/2026 |
| ARC-HI-TECT ASSOCIATE INC | 3 | 12/28/2021 |
| ALLEN SHINFELD, P.E. PLLC | 5 | 12/23/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| YOUN DESIGN CORP | 10 | 03/21/2026 |
| ARCHITECTURAL DESIGN SOLUTIONS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NEPTUNE SIGNS AWNINGS | Scaffold | 4 | 07/08/2026 |
| L&J PLG & HTG CO OF NY IN | Plumbing | 4 | 07/08/2026 |
| LIBERTY RENOVATION CORP | General Contractor | 3 | 03/21/2026 |
| YOUN DESIGN CORP | General Contractor | 3 | 03/21/2026 |
| BLUE RIDGE CONSTRUCTION | General Contractor | 3 | 03/21/2026 |
| HT PLUMBING & HEATING COR | Plumbing | 1 | 07/04/2026 |
| SKY ELECTRIC LLC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARC-HI-TECH ASSOCIATES IN | 6963 | 6 | 06/30/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HT PLUMBING & HEATING COR | 03/12/2026 |
| DOB NOW | General Construction | Signed-off | BLUE RIDGE CONSTRUCTION | 05/06/2022 |
| DOB NOW | Plumbing | Permit Issued | L&J PLG & HTG CO OF NY IN | 03/18/2022 |
| DOB NOW | General Construction | Signed-off | YOUN DESIGN CORP | 02/28/2022 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 01/26/2022 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 01/26/2022 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 12/30/2021 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 12/30/2021 |
| DOB NOW | General Construction | Signed-off | LIBERTY RENOVATION CORP | 10/14/2021 |
| BIS | EQ | ISSUED | JRS CONSTRUCTION & EXPEDITING | 06/17/2020 |
| BIS | PL | ISSUED | INFINITI ESC PLUMBING COR | 12/20/2019 |
| BIS | EQ | ISSUED | JRS CONSTRUCTION & EXPEDITING | 07/18/2019 |
| BIS | — | ISSUED | JRS CONSTRUCTION & EXPEDITING | 07/18/2019 |
| BIS | — | ISSUED | JRS CONSTRUCTION & EXPEDITING | 07/18/2019 |
| BIS | — | ISSUED | MGZ BUILDERS CORP | 09/08/2017 |
| BIS | — | ISSUED | MGZ BUILDERS CORP | 09/08/2017 |
| BIS | EQ | ISSUED | MGZ BUILDERS CORP | 09/01/2017 |
| BIS | — | ISSUED | MGZ BUILDERS CORP | 09/01/2017 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/21/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/26/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/07/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/16/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 05/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/16/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/10/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 01/31/2022 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 01/18/2022 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2026 | Fire-Resistant Penetrations and Joints | IGOR LISOVENKO | special |
| 07/07/2026 | Energy Code Compliance Inspections | IGOR LISOVENKO | progress |
| 07/07/2026 | Maintenance information | IGOR LISOVENKO | energy_progress |
| 05/07/2026 | Maintenance information | IGOR LISOVENKO | energy_progress |
| 05/07/2026 | Energy Code Compliance Inspections | IGOR LISOVENKO | progress |
| 05/07/2026 | Fire-Resistant Penetrations and Joints | IGOR LISOVENKO | special |
| 02/05/2026 | Fire-Resistant Penetrations and Joints | IGOR LISOVENKO | special |
| 02/05/2026 | Energy Code Compliance Inspections | IGOR LISOVENKO | progress |
| 02/05/2026 | Maintenance information | IGOR LISOVENKO | energy_progress |
| 12/20/2021 | Structural Steel - Welding | IGOR LISOVENKO | special |
| 12/20/2021 | Final | IGOR LISOVENKO | progress |
| 12/20/2021 | Maintenance information | IGOR LISOVENKO | energy_progress |
| 12/20/2021 | Air barrier - visual inspection | IGOR LISOVENKO | energy_progress |
| 12/20/2021 | Structural Steel - Details | IGOR LISOVENKO | special |
| 12/20/2021 | Structural Cold-Formed Steel | IGOR LISOVENKO | special |
| 12/20/2021 | Mechanical Systems | IGOR LISOVENKO | special |