| Owner | Filings | Most Recent |
|---|---|---|
| 2846 PARTNERS | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CHUN FENG, ARCHITECT | 1 | 11/22/2024 |
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 2 | 11/16/2021 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 04/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| AMERGY SOLAR | 2 | 03/21/2026 |
| BLUE STAR HOLDING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMERGY SOLAR INC | General Contractor | 3 | 03/21/2026 |
| BLUE STAR GROUP LLC | General Contractor | 3 | 07/08/2026 |
| CAPITAL CONTR P&H CORP | Plumbing | 1 | 07/08/2026 |
| R&M PIPING & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 1 | 11/22/2024 |
| A TECH ENGINEERING NYC, P | 6738 | 1 | 04/16/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | AMERGY SOLAR INC | 11/29/2024 |
| DOB NOW | Curb Cut | Signed-off | BLUE STAR GROUP LLC | 06/02/2022 |
| DOB NOW | Plumbing | Signed-off | R&M PIPING & HTG INC | 04/20/2022 |
| DOB NOW | Plumbing | Signed-off | CAPITAL CONTR P&H CORP | 06/18/2021 |
| DOB NOW | Foundation | Signed-off | BLUE STAR GROUP LLC | 06/11/2021 |
| BIS | — | ISSUED | BLUE STAR GROUP LLC | 03/31/2022 |
| BIS | — | ISSUED | BLUE STAR GROUP LLC | 11/17/2021 |
| BIS | — | ISSUED | BLUE STAR GROUP LLC | 10/29/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2024 | Complete | I.P. ELECTRIC INC | — |
| 02/11/2022 | Complete | TRUE ELECTRIC CORP. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/17/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/13/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/09/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/26/2022 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 04/25/2022 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/23/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2021 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/20/2024 | Fire-Resistant Penetrations and Joints | Chun Feng | special |
| 11/20/2024 | Structural Stability – Alterations of existing buildings | Chun Feng | special |
| 11/20/2024 | Energy Code Compliance Inspections | Chun Feng | progress |
| 11/20/2024 | Final | Chun Feng | progress |
| 11/20/2024 | Air barrier - visual inspection | Chun Feng | energy_progress |