| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 9 | 07/08/2026 |
| R S CONTRACTING NY | 2 | 03/22/2026 |
| LOKETCH GROUP | 15 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/03/2022 | $4.6M | — | — → — | $1,162/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 10/28/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 10 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 01/21/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 01/21/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 01/21/2021 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 01/21/2021 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 11/10/2021 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 10/29/2021 |
| BIS | PL | ISSUED | PRIME PIPING & HEATING IN | 08/11/2021 |
| BIS | PL | ISSUED | AMOK INC | 07/21/2021 |
| BIS | PL | ISSUED | AMOK INC | 07/12/2021 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 11/17/2020 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 11/17/2020 |
| BIS | PL | ISSUED | AMOK INC | 07/08/2020 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 02/21/2020 |
| BIS | — | ISSUED | R & S CONTRACTING NY INC | 02/21/2020 |
| BIS | OT | ISSUED | R & S CONTRACTING NY INC | 01/31/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2021 | Complete | V. VASS ELECTRIC CORP | — |
| 11/10/2020 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/29/2021 | Final | Paul Perdek | progress |