| Owner | Filings | Most Recent |
|---|---|---|
| PLATINUM SERVICES NY | 25 | 07/08/2026 |
| TRI STATE CRANE SERVICE | 3 | 03/22/2026 |
| NYC DEPT OF HOUSING PRESERVATION | 4 | 03/21/2026 |
| DEKALB COMMONS NY LLC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DAGHER ENGINEERING PLLC | 5 | 10/31/2025 |
| ADVANCED ENGINEERING & INSPECT. PLL | 1 | 08/27/2024 |
| JAMES STOUT ARCHITECT & ASSOCIATES | 1 | 08/22/2024 |
| ASHRAF CORP | 5 | 07/28/2024 |
| TOHFAZ UDDIN PE PC | 2 | 05/08/2024 |
| HANSEN ENGINEERING, PC | 1 | 07/25/2023 |
| CIVIL DESIGN WORKS LLC | 2 | 11/12/2021 |
| KPFF CONSULTING ENGINEERS | 1 | 11/12/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| WILLIAM VITACCO ASSOCIATES | 12 | 03/21/2026 |
| JM ZONING, LLC. | 3 | 03/21/2026 |
| PLATINUM SERVICES NY | 8 | 03/21/2026 |
| KD DESIGNS | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| PROFESSIONAL DESIGN CONSULTANTS LL | 2 | 03/21/2026 |
| SUNKEEPER SOLAR ELECTRIC LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLATINUM SERVICES NY LLC | General Contractor | 10 | 07/08/2026 |
| PROCIDA CONSTRUCTION CORP. | General Contractor | 10 | 07/08/2026 |
| CARA PLUMBING GROUP INC | Plumbing | 6 | 07/08/2026 |
| MANENGEERING BUREAU INC | Fire Protection | 4 | 07/08/2026 |
| J.J.C. STUCCO AND CARPENT | General Contractor | 3 | 07/08/2026 |
| SUNKEEPER SOLAR ELECTRIC | General Contractor | 2 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 5 | 10/31/2025 |
| JAMES J STOUT ARCHITECTS | 5913 | 1 | 08/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 09/05/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 09/05/2025 |
| DOB NOW | Solar | Signed-off | SUNKEEPER SOLAR ELECTRIC | 07/29/2025 |
| DOB NOW | Mechanical Systems | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/11/2025 |
| DOB NOW | Construction Fence | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/11/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 04/30/2025 |
| DOB NOW | Supported Scaffold | Signed-off | J.J.C. STUCCO AND CARPENT | 04/07/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATINUM SERVICES NY LLC | 03/31/2025 |
| DOB NOW | Supported Scaffold | Signed-off | J.J.C. STUCCO AND CARPENT | 02/06/2025 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM SERVICES NY LLC | 02/06/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 02/06/2025 |
| DOB NOW | Earth Work | Signed-off | PROCIDA CONSTRUCTION CORP. | 12/16/2024 |
| DOB NOW | Structural | Signed-off | PROCIDA CONSTRUCTION CORP. | 12/16/2024 |
| DOB NOW | Sprinklers | Signed-off | MANENGEERING BUREAU INC | 11/06/2024 |
| DOB NOW | Sprinklers | Signed-off | MANENGEERING BUREAU INC | 11/04/2024 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 09/05/2024 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 09/05/2024 |
| DOB NOW | Supported Scaffold | Signed-off | J.J.C. STUCCO AND CARPENT | 08/28/2024 |
| DOB NOW | Solar | Signed-off | SUNKEEPER SOLAR ELECTRIC | 08/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/18/2024 |
| DOB NOW | Construction Fence | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/18/2024 |
| DOB NOW | Supported Scaffold | Signed-off | PLATINUM SERVICES NY LLC | 05/03/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATINUM SERVICES NY LLC | 04/03/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 02/09/2024 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM SERVICES NY LLC | 02/09/2024 |
| DOB NOW | Structural | Signed-off | PROCIDA CONSTRUCTION CORP. | 12/13/2023 |
| DOB NOW | Earth Work | Signed-off | PROCIDA CONSTRUCTION CORP. | 12/12/2023 |
| DOB NOW | Sprinklers | Signed-off | MANENGEERING BUREAU INC | 11/06/2023 |
| DOB NOW | Standpipe | Signed-off | MANENGEERING BUREAU INC | 11/03/2023 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 08/24/2023 |
| DOB NOW | Plumbing | Signed-off | PRIME PLMBG & HTG OF NY | 08/24/2023 |
| DOB NOW | Construction Fence | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/28/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PROCIDA CONSTRUCTION CORP. | 07/28/2023 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 04/30/2025 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 04/30/2025 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 04/29/2024 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 04/29/2024 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 08/14/2023 |
| BIS | — | ISSUED | PROCIDA CONSTRUCTION CORP. | 08/14/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/08/2025 | Complete | XTREME ELECTRIC INC | General Wiring |
| 08/26/2025 | Complete | TOTAL ELECTRIC SOLUTIONS | General Wiring |
| 08/14/2024 | Complete | SUNKEEPER SOLAR LLC | — |
| 04/23/2024 | Complete | XTREME ELECTRIC INC | — |
| 04/10/2024 | Complete | ILLUMINOUS ELECTRIC CORP. | — |
| 02/07/2024 | Complete | ILLUMINOUS ELECTRIC CORP. | General Wiring |
| 12/06/2023 | Complete | XTREME ELECTRIC INC | General Wiring |
| 10/09/2023 | Complete | XTREME ELECTRIC INC | 1 meters, 1 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/17/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/30/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/28/2025 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 08/28/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 08/12/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/12/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 12/30/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/25/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/22/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/07/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/29/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/15/2025 | Final | Soorjbally Harilall | progress |
| 10/15/2025 | Mechanical Systems | SOORJBALLY HARILALL | special |
| 08/15/2024 | Energy Code Compliance Inspections | JAMES J STOUT | progress |
| 08/15/2024 | Final | JAMES J STOUT | progress |
| 08/15/2024 | Fire-Resistant Penetrations and Joints | JAMES J STOUT | special |
| 08/15/2024 | Air barrier - visual inspection | JAMES J STOUT | energy_progress |
| 08/15/2024 | Structural Stability – Alterations of existing buildings | JAMES J STOUT | special |
| 04/06/2023 | Final | — | progress |
| 04/06/2023 | Mechanical Systems | — | special |