| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/15/2026 | Complete | AL ELECTRICAL GROUP INC | General Wiring |
| 05/15/2026 | Complete | AL ELECTRICAL GROUP INC | — |
| 05/15/2026 | Complete | AL ELECTRICAL GROUP INC | General Wiring |
| 03/22/2023 | Complete | AL ELECTRICAL GROUP INC | 135 meters, 135 new_meters |
| 02/09/2023 | Complete | AL ELECTRICAL GROUP INC | General Wiring |
| 09/21/2022 | Complete | AL ELECTRICAL GROUP INC | — |
| 08/21/2022 | Complete | JAM ELECTRICAL CORP | — |
| 06/29/2022 | Complete | SOLAS ELECTRICAL CORP | — |
| Owner | Filings | Most Recent |
|---|---|---|
| RYTY HOME BUILDERS | 72 | 07/08/2026 |
| GUNHILL BH LLC | 5 | 03/22/2026 |
| BE BRONX BUILDERS | 29 | 03/22/2026 |
| BUILDERS LLC BE | 2 | 03/22/2026 |
| BUILDERS L BE BRONX | 1 | 03/22/2026 |
| GUNHILL BH LLC 1 | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/17/2021 | $4.0M | — | EAST END GUN HILL LLC → GUNHILL BH LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| A DEGREE OF FREEDOM STRUCTURAL ENGI | 4 | 11/27/2023 |
| JOSELOW & ASSOCIATES, LLC | 10 | 11/06/2023 |
| MARIN ARCHITECTS, P.C. | 6 | 10/12/2023 |
| PAUL G. JONES, P.E. | 4 | 01/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CANAS SOLUTIONS | 30 | 03/21/2026 |
| MARIN ARCHITECTS, P.C. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BE BRONX BUILDERS, LLC | General Contractor | 17 | 07/08/2026 |
| CONSOLIDATED SCAFFOLDING | General Contractor | 10 | 07/08/2026 |
| ARIANA CONTRACTING INC | Fire Protection | 4 | 07/08/2026 |
| JUNIOR CARTER MECH. CORP | Plumbing | 3 | 07/08/2026 |
| AL ELECTRICAL GROUP INC 005120 | General Contractor | 1 | 03/22/2026 |
| AL ELECTRICAL GROUP INC | Electrical | 1 | 03/22/2026 |
| JUNIOR CARTER MECH | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| DOMINICK R. PILLA | 1300 | 16 | 11/27/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Boiler Equipment | Signed-off | JUNIOR CARTER MECH. CORP | 10/13/2023 |
| DOB NOW | Plumbing | Signed-off | JUNIOR CARTER MECH. CORP | 08/18/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 07/06/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/05/2023 |
| DOB NOW | Foundation | Signed-off | BE BRONX BUILDERS, LLC | 06/28/2023 |
| DOB NOW | Structural | Signed-off | BE BRONX BUILDERS, LLC | 06/28/2023 |
| DOB NOW | Support of Excavation | Signed-off | BE BRONX BUILDERS, LLC | 06/28/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BE BRONX BUILDERS, LLC | 06/27/2023 |
| DOB NOW | Standpipe | Signed-off | ARIANA CONTRACTING INC | 05/24/2023 |
| DOB NOW | General Construction | Permit Issued | BE BRONX BUILDERS, LLC | 05/17/2023 |
| DOB NOW | Construction Fence | Signed-off | BE BRONX BUILDERS, LLC | 02/06/2023 |
| DOB NOW | Standpipe | Signed-off | ARIANA CONTRACTING INC | 12/15/2022 |
| DOB NOW | Standpipe | Signed-off | ARIANA CONTRACTING INC | 12/07/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/12/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 07/02/2022 |
| DOB NOW | Plumbing | Signed-off | JUNIOR CARTER MECH. CORP | 07/01/2022 |
| DOB NOW | Structural | Signed-off | BE BRONX BUILDERS, LLC | 06/30/2022 |
| DOB NOW | General Construction | Permit Issued | BE BRONX BUILDERS, LLC | 05/19/2022 |
| DOB NOW | Standpipe | Signed-off | ARIANA CONTRACTING INC | 05/16/2022 |
| DOB NOW | Foundation | Signed-off | BE BRONX BUILDERS, LLC | 04/11/2022 |
| DOB NOW | Support of Excavation | Signed-off | BE BRONX BUILDERS, LLC | 03/21/2022 |
| DOB NOW | Construction Fence | Signed-off | BE BRONX BUILDERS, LLC | 03/21/2022 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/08/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/01/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/26/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/23/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 09/29/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/27/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/27/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 08/23/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 08/23/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 08/22/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/19/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 03/19/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 03/10/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/19/2022 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/30/2023 | Excavations - Sheeting, Shoring, and Bracing | Dominick Pilla | special |
| 11/06/2023 | Mechanical Systems | Dominick Pilla | special |
| 11/06/2023 | Final | Dominick Pilla | progress |
| 11/06/2023 | HVAC-R and service water heating equipment | Dominick Pilla | energy_progress |
| 11/06/2023 | Shutoff dampers | Dominick Pilla | energy_progress |
| 11/06/2023 | HVAC-R and service water heating system controls | Dominick Pilla | energy_progress |
| 11/06/2023 | Maintenance information | Dominick Pilla | energy_progress |
| 11/06/2023 | Metering | Dominick Pilla | energy_progress |
| 11/06/2023 | HVAC-R and service water piping design and insulation | Dominick Pilla | energy_progress |
| 11/06/2023 | Heating Systems | Dominick Pilla | special |
| 11/06/2023 | Heating Systems | Dominick Pilla | special |
| 11/06/2023 | Maintenance information | Dominick Pilla | energy_progress |
| 11/06/2023 | HVAC-R and service water piping design and insulation | Dominick Pilla | energy_progress |
| 11/06/2023 | Metering | Dominick Pilla | energy_progress |
| 11/06/2023 | HVAC-R and service water heating equipment | Dominick Pilla | energy_progress |
| 11/06/2023 | HVAC-R and service water heating system controls | Dominick Pilla | energy_progress |
| 11/06/2023 | Shutoff dampers | Dominick Pilla | energy_progress |
| 11/06/2023 | Final | Dominick Pilla | progress |
| 11/06/2023 | Mechanical Systems | Dominick Pilla | special |
| 10/27/2023 | Lighting controls | Dominick Pilla | energy_progress |
| 10/27/2023 | Metering | Dominick Pilla | energy_progress |
| 10/27/2023 | Lighting in dwelling units | Dominick Pilla | energy_progress |
| 10/27/2023 | Fenestration and door U-factor and product ratings | Dominick Pilla | energy_progress |
| 10/27/2023 | Exterior lighting power | Dominick Pilla | energy_progress |
| 10/27/2023 | Air barrier - visual inspection | Dominick Pilla | energy_progress |