| Owner | Filings | Most Recent |
|---|---|---|
| UPSTRATE | 2 | 03/22/2026 |
| BLK 406419 | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| WILLIAM MONTAGUE ENGINEER | 4 | 01/14/2025 |
| LOBUE & VALENZIANO, LLP | 6 | 11/06/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| LO BUE VALENZIANO AIA | 12 | 03/21/2026 |
| SRA PLANNING & EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CROWN PLUMBING INC | Plumbing | 4 | 07/08/2026 |
| HIGHLEVEL GROUP INC | General Contractor | 3 | 03/21/2026 |
| DRILON PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| UPSTRATE INC | General Contractor | 2 | 03/21/2026 |
| JB BUZCO PLUMBING, LLC | General Contractor | 1 | 07/08/2026 |
| YU HUA CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SRA PLANNING & EXPEDITING | 5677 | 2 | 11/06/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DRILON PLBG & HTG INC | 04/28/2025 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 04/01/2025 |
| DOB NOW | Curb Cut | Signed-off | YU HUA CONSTRUCTION CORP | 03/03/2025 |
| DOB NOW | Foundation | Permit Issued | UPSTRATE INC | 09/24/2024 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 03/21/2024 |
| DOB NOW | Structural | Permit Issued | HIGHLEVEL GROUP INC | 09/28/2023 |
| DOB NOW | Construction Fence | Signed-off | JB BUZCO PLUMBING, LLC | 08/03/2018 |
| BIS | — | ISSUED | JB BUZCO PLUMBING, LLC | 09/19/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2024 | Signed-off | CROWN PLUMBING INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/19/2024 | Complete | INTELOGIC ELECTRIC, INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2024 | Signed-off | CROWN PLUMBING INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/12/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/30/2025 | Certified Sprinkler (PL)-Sprinkler-Hydro | Certified | View ↗ |
| 04/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/13/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/22/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/12/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/24/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/24/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/14/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/14/2022 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/21/2024 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | WILLIAM MONTAGUE | special |
| 11/21/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | WILLIAM MONTAGUE | special |
| 11/21/2024 | Subgrade Inspections | WILLIAM MONTAGUE | special |
| 11/21/2024 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 11/21/2024 | Fire-Resistant Penetrations and Joints | WILLIAM MONTAGUE | special |
| 11/21/2024 | Concrete - Cast-In-Place | WILLIAM MONTAGUE | special |
| 11/21/2024 | Final | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Structural Wood Frame | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Fire-Resistance Rated Construction | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Energy Code Compliance Inspections | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Footing and Foundation | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Lowest Floor Elevation | WILLIAM MONTAGUE | progress |
| 11/21/2024 | Fenestration areas | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Electric vehicle service equipment requirements | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | HVAC-R and service water piping design and insulation | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Air barrier — testing | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Maintenance information | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Air barrier - visual inspection | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Fenestration air leakage | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Insulation placement and R values | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Interior lighting power | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Permanent certificate | WILLIAM MONTAGUE | energy_progress |
| 11/21/2024 | Fenestration and door U-factor and product ratings | WILLIAM MONTAGUE | energy_progress |