← Back
Two family frame
GERVIL STREET
STATEN ISLAND · Arden Heights-Rossville · BIN 5175450
💬 Discuss this project
2025Year Built
2Stories
B2Building Class
R3-1Zoning
2,450 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · Owner of record: GERVIL INC. · 4,180 sf lot · 0.59 FAR built · Flood zone X
Locations of Work
PlumbingCivil
Floor 23p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Basement1p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BRIDLE ESTATES1607/08/2026
MASON MAGUIRE LLC903/22/2026
CASA MASON ESTATES203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH M. MORACE, A.I.A., ARCHITECT702/03/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPEDIA CONSULTING603/21/2026
BLUE STAR HOLDING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BRIDLE ESTATES INCGeneral Contractor307/08/2026
NIRO INCGeneral Contractor107/08/2026
FLOW-RIGHT PLBG & HTG CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
C&P DESIGN CONSULTANT8472212/11/2025
Building Lifecycle
All (59)Filed (7)Permit Issued (4)Signed Off (4)Violation (2)Inspection (8)Objection (4)Special Inspection (30)
03/23/2026
Signed off — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-I1
03/21/2026
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
03/11/2026
Signed off — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S3
02/11/2026
Signed off — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S4
02/10/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/10/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/03/2026
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-P3
02/02/2026
Special inspection requirement — Air barrier continuity plan testing
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Concrete - Cast-In-Place
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Subgrade Inspections
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
WILLIAM MONTAGUE
02/02/2026
Special inspection requirement — Wood – Prefabricated I-Joists
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Mechanical Systems
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Footing and Foundation
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Final
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Structural Wood Frame
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Fire-Resistance Rated Construction
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Permanent certificate
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Fenestration areas
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Duct leakage testing, insulation and design
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Ventilation and air distribution system
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Fenestration air leakage
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Maintenance information
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Electric vehicle service equipment requirements
Stanislav Pilipenko
02/02/2026
Special inspection requirement — HVAC-R and service water heating equipment
Stanislav Pilipenko
02/02/2026
Special inspection requirement — HVAC-R and service water heating system controls
Stanislav Pilipenko
02/02/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Lighting in dwelling units
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Air barrier — testing
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Air barrier - visual inspection
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Interior lighting power
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Protection of exposed foundation insulation
Stanislav Pilipenko
02/02/2026
Special inspection requirement — Insulation placement and R values
Stanislav Pilipenko
01/12/2026
Signed off — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S2
01/05/2026
Objection resolved — Addressed
12/29/2025
Objection raised — Scope
12/22/2025
Permit issued — Curb Cut
S00702797-S4-CC
12/11/2025
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-P2
12/02/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/02/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/13/2025
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-P1
07/17/2025
Violation issued (ECB, closed)
Construction
07/17/2025
Violation issued (ECB, closed)
Construction
07/02/2025
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S4
05/15/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/01/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
03/26/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
03/20/2025
Permit issued — Plumbing
S00702797-S3-PL
03/11/2025
Permit issued — Construction Fence
S00702797-S2-FN
02/20/2025
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S3
02/20/2025
Permit issued — Earth Work
S00702797-I1-GC-CX
02/19/2025
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-S2
04/19/2022
Objection raised — Scope
04/19/2022
Objection resolved — Addressed
03/29/2022
Filed — New Building
PROPOSED INSTALLATION OF TEMPORARY CONSTRUCTION FENCE. FENCE APPLIES TO 230 & 234 GERVIL STREET.
S00702797-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offNIRO INC12/22/2025
DOB NOWPlumbingSigned-offFLOW-RIGHT PLBG & HTG COR03/20/2025
DOB NOWConstruction FenceSigned-offBRIDLE ESTATES INC03/11/2025
DOB NOWEarth WorkPermit IssuedBRIDLE ESTATES INC02/20/2025
1 project · most recent 02/03/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
02/03/2026Signed-offFLOW-RIGHT PLBG & HTG CORGas, Storm, Water/Sanitary
1 project · most recent 05/01/2025
General Wiring
FiledStatusContractorScope
05/01/2025CompleteD AND H ELECTRICAL CONSTGeneral Wiring
1 project · most recent 02/03/2026
Concrete Wood
FiledStatusContractorScope
02/03/2026Signed-offNIRO INCConcrete, Wood
1 project · most recent 02/03/2026
Fence
FiledStatusContractorScope
02/03/2026Signed-offNIRO INCFence
1 project · most recent 02/03/2026
Earthwork
FiledStatusContractorScope
02/03/2026Signed-offNIRO INCEarthwork
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
03/21/2026Certified Sprinkler - SP - RoughingCertifiedView ↗
02/10/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/10/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
12/02/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/02/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/15/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/01/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
03/26/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 60
DateRequirementInspectorRole
02/02/2026Air barrier continuity plan testingStanislav Pilipenkoenergy_progress
02/02/2026Concrete - Cast-In-PlaceStanislav Pilipenkospecial
02/02/2026Fire-Resistant Penetrations and JointsStanislav Pilipenkospecial
02/02/2026Subgrade InspectionsStanislav Pilipenkospecial
02/02/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationStanislav Pilipenkospecial
02/02/2026Subsurface Investigations (Borings/Test Pits)WILLIAM MONTAGUEspecial
02/02/2026Wood – Prefabricated I-JoistsStanislav Pilipenkospecial
02/02/2026Mechanical SystemsStanislav Pilipenkospecial
02/02/2026Footing and FoundationStanislav Pilipenkoprogress
02/02/2026FinalStanislav Pilipenkoprogress
02/02/2026Structural Wood FrameStanislav Pilipenkoprogress
02/02/2026Energy Code Compliance InspectionsStanislav Pilipenkoprogress
02/02/2026Fire-Resistance Rated ConstructionStanislav Pilipenkoprogress
02/02/2026Permanent certificateStanislav Pilipenkoenergy_progress
02/02/2026Fenestration areasStanislav Pilipenkoenergy_progress
02/02/2026Duct leakage testing, insulation and designStanislav Pilipenkoenergy_progress
02/02/2026Ventilation and air distribution systemStanislav Pilipenkoenergy_progress
02/02/2026Fenestration air leakageStanislav Pilipenkoenergy_progress
02/02/2026Maintenance informationStanislav Pilipenkoenergy_progress
02/02/2026Electric vehicle service equipment requirementsStanislav Pilipenkoenergy_progress
02/02/2026HVAC-R and service water heating equipmentStanislav Pilipenkoenergy_progress
02/02/2026HVAC-R and service water heating system controlsStanislav Pilipenkoenergy_progress
02/02/2026HVAC-R and service water piping design and insulationStanislav Pilipenkoenergy_progress
02/02/2026Fenestration and door U-factor and product ratingsStanislav Pilipenkoenergy_progress
02/02/2026Lighting in dwelling unitsStanislav Pilipenkoenergy_progress
Latest 25 of 60.
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/24/2026S00702797-I1Request digital key ↗
08/24/2026S00702797-P3Request digital key ↗
08/24/2026S00702797-P2Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
11/18/2025540234673Open ↗
11/08/2024540265381Open ↗
08/19/2022540234673Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
12/03/2024540265381Open ↗
08/25/2022540234673Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026S00702797-P2Open ↗
08/13/2026S00702797-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026S00702797-I1Open ↗
08/13/2026S00702797-P2Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00702797-I1Open ↗
▸Seals & Professional Certifications23
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/24/2026S00702797-I1Open ↗
08/24/2026S00702797-P3Open ↗
08/24/2026S00702797-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/30/2026S00702797-P2Open ↗
08/30/2026S00702797-P2Open ↗
08/30/2026S00702797-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
08/30/2026S00702797-P2Open ↗
08/30/2026S00702797-P2Open ↗
08/30/2026S00702797-P2Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
11/08/2024540265381Open ↗
08/19/2022540234673Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
11/08/2024540265381Open ↗
08/19/2022540234673Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026S00702797-P2Open ↗
08/13/2026S00702797-I1Open ↗
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist2
08/13/2026S00702797-I1Open ↗
08/13/2026S00702797-P2Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00702797-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026S00702797-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026S00702797-I1Open ↗
▸Inspections & Test Reports5
▸BISBPP-9 - Request for Builders Pavement Field Inspection2
12/03/2024540265381Open ↗
08/19/2022540234673Open ↗
▸DOB NOWSOIL REPORT2
08/13/2026S00702797-P2Open ↗
08/13/2026S00702797-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00702797-I1Open ↗
▸Approvals, Objections & Sign-offs4
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff3
12/03/2024540265381Open ↗
08/25/2022540234673Open ↗
08/19/2022540234673Open ↗
▸BISSUPERSEDING LETTER1
11/18/2025540234673Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET2
11/08/2024540265381Open ↗
08/19/2022540234673Open ↗
▸Other Documents11
▸BISBPP - SUPPORTING DOCUMENTATION4
12/03/2024540265381Open ↗
12/03/2024540265381Open ↗
08/25/2022540234673Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial2
08/13/2026S00702797-I1Open ↗
08/13/2026S00702797-P2Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026S00702797-I1Open ↗
08/13/2026S00702797-P2Open ↗
▸DOB NOWProperty Ownership Certification2
08/24/2026S00702797-P2Open ↗
08/24/2026S00702797-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00702797-I1Open ↗