| Owner | Filings | Most Recent |
|---|---|---|
| C A SENECA CONSTRUCTION | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 6 | 01/05/2026 |
| C&P DESIGN CONSULTANTS | 1 | 06/23/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L GASS | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BRADLEY ASSOCIATES OF SI | General Contractor | 5 | 04/09/2026 |
| CHARLES J. DEHART JR P&H | Plumbing | 3 | 07/08/2026 |
| C P DESIGN CONSULTANTS | General Contractor | 2 | 03/22/2026 |
| JOSEPH MORACE | Electrical | 1 | 03/21/2026 |
| MERCURY FIRE SUPP INC | Fire Protection | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 3 | 01/05/2026 |
| C&P DESIGN CONSULTANT | 8472 | 2 | 01/05/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BRADLEY ASSOCIATES OF SI | 12/02/2025 |
| DOB NOW | Plumbing | Signed-off | CHARLES J. DEHART JR P&H | 11/05/2025 |
| DOB NOW | Foundation | Permit Issued | BRADLEY ASSOCIATES OF SI | 10/16/2025 |
| DOB NOW | Plumbing | Signed-off | MERCURY FIRE SUPP INC | 08/11/2025 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 07/28/2025 |
| DOB NOW | Plumbing | Signed-off | CHARLES J. DEHART JR P&H | 06/18/2025 |
| DOB NOW | General Construction | Permit Issued | BRADLEY ASSOCIATES OF SI | 06/06/2025 |
| DOB NOW | Construction Fence | Signed-off | BRADLEY ASSOCIATES OF SI | 05/29/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2026 | Signed-off | MERCURY FIRE SUPP INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2026 | Signed-off | CHARLES J. DEHART JR P&H | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Complete | B & R ELEC'L CONTR'G, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2026 | Signed-off | BRADLEY ASSOCIATES OF SI | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/20/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/18/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/22/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/16/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/11/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 11/05/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/29/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/28/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/26/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/19/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 08/18/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/08/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/14/2026 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 01/14/2026 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 01/14/2026 | Subgrade Inspections | anthony santoro | special |
| 01/14/2026 | Concrete - Cast-In-Place | anthony santoro | special |
| 01/14/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Stanislav Pilipenko | special |
| 01/14/2026 | Mechanical Systems | anthony santoro | special |
| 01/14/2026 | Footing and Foundation | anthony santoro | progress |
| 01/14/2026 | Structural Wood Frame | anthony santoro | progress |
| 01/14/2026 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 01/14/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 01/14/2026 | Final | anthony santoro | progress |
| 01/14/2026 | HVAC-R and service water heating equipment | anthony santoro | energy_progress |
| 01/14/2026 | Protection of exposed foundation insulation | anthony santoro | energy_progress |
| 01/14/2026 | Air barrier — testing | anthony santoro | energy_progress |
| 01/14/2026 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 01/14/2026 | Insulation placement and R values | anthony santoro | energy_progress |
| 01/14/2026 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 01/14/2026 | Interior lighting power | anthony santoro | energy_progress |
| 01/14/2026 | Ventilation and air distribution system | anthony santoro | energy_progress |
| 01/14/2026 | Permanent certificate | anthony santoro | energy_progress |
| 01/14/2026 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |
| 01/14/2026 | Fenestration air leakage | anthony santoro | energy_progress |
| 01/14/2026 | Maintenance information | anthony santoro | energy_progress |
| 01/14/2026 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 01/14/2026 | Duct leakage testing, insulation and design | anthony santoro | energy_progress |